Homework fro week 1 and 2

ksteele030479
KSteeleOPS574Week1Assignment.docx

OPS/574 v1

Process Improvement Flowchart

OPS/574 v1

Page 2 of 2

C:\Users\djshirey\OneDrive - University of Phoenix\F_Drive\Style Guides\UPX Logos\Horizontal format\UOPX_Sig_Hor_Black_Medium.png

Process Improvement Flowchart

As-Is Process Flow Chart Evaluation

Select a process from an organization you work for or are familiar with. You will use this process in your Week 2 & Week 4 Signature Assignments as well.

Create a flowchart of the as-is process using Microsoft Word, PowerPoint, Vizio, or Excel.

Evaluate the efficacy of your process using process improvement techniques.

After using the line graph to evaluate the past few documents it was notable that it was taking documents longer and longer to get done. Each document at least took 5 weeks because of the assigned review lengths and the missed emails between individuals.

Process Improvement Flow Chart

Determine how the process can be improved based on the results of your evaluation.

There are a few things that can be combined to cut times and emails between individuals.

Define metrics and measure the current process. 

Metrics are measures that every organization uses to either compare, asses, or track something that management needs data on or they want to improve on something. For this process we will be using a plot graph to plot how long it takes a document to get done with the hopes of improving the current document review process.

 

Use process improvement techniques to improve the process. Create a flow chart of the improved process using Microsoft Word, PowerPoint, Vizio, or Excel. Use your professional judgment to ascertain how the future process will perform according to your metrics. 

Summary

Write a 525-word executive summary that includes the following: 

· A brief description of the process based on the flowchart of processes current state 

· The results of your process evaluation and how the weak points can be strengthened. Include a description of the process improvement technique(s) used. 

· A brief description of process improvements based on the process of the future state 

· How you anticipate the future process will perform based on metrics used to evaluate process current state

· A description of your process improvement project to achieve the process future state

 

Executive Summary

Current Process

This process is for engineering documents that get written and released to the fleet. Currently, the way the process goes is that the engineer writes or updates a document and sends it to the product integrity team lead when complete. Then, the lead will receive that email and assign a Technical Writer (TW) to edit and send the document through the document review process. That TW will receive the document and edit the document and then email the engineer requesting a list of reviewers that need to review the document. Once the TW receives that list of reviewers the TW sends the document out for technical review. Once they receive the comments from the technical review, they send them to the author of the document to approve or disapprove of the comments. Then, comments that were approved are then incorporated into the document and it is sent out for a formal review. Once that review is over, they make all needed changes and send it to the Chief Engineer and IPT lead for comments or signature. If there are comments, then those need to go to the author once again for approval. If not, the TW prints out the signature page and goes around to get that signature page signed by all approving officials.

Why it does not work anymore

The current document review process as is does not work for the current needs of this organization. While it did work at some time right now this process takes way too much time to complete. Since everything is done by email it currently takes about 5-6 weeks to get one document complete from start to finish. This data was gathered y plotting on a graph how long each document took from start to finish for the past year. Now a days these documents need to be produced way faster than before because of the need of them in the fleet. Once the new process is incorporated the time will be cut dramatically. As much of the items will be combined or cut where that is possible. With that being done there will be less time because there will be less emails, not that much time wasted as people will not be sitting on emails or waiting on email replies.

Anticipated Metrics

For the next six months we will track all documents from start to finish and create a second plot graph that shows exactly the length of time. This will show how the time was cut to almost if not half of the current time because there is no waiting on email replies or waiting on TW to receive their documents.

Future Updates

Once these changes are incorporated and all issues are resolved there will be more changes that will take place in this process in the future. The signature review and actual signature signing of the document will be electronically instead of walking from work center to work center looking for individuals to sign in pen. This will also reduce time in the future as there will not be a need to walk and look for people. The TW will also attend morning status meetings to provide management with statuses of documents so everyone will be held accountable.

References

Metrics. Investopedia. (2020). Retrieved from https://www.investopedia.com/terms/m/metrics.asp

What are Metrics and Why are they Important? MSG Management Study Guide (2020). Retrieved from https://www.managementstudyguide.com/what-are-metrics.htm

Copyright 2020 by University of Phoenix. All rights reserved.

Copyright 2020 by University of Phoenix. All rights reserved.

Engineer writes/

update a process

They send the

document to the

Product Integrity Team

Lead

When the Lead receives

the email, he/ she

assigns the document to

a TW

TW receives the

document, edits the

document contacts the

engineer to ask for

reviewers

Once they receive the

list, they send it out for

technical review

(1week)

They get it back with all

the comments. Get

those comments

approved by author

incorporate them into

the document. And then

send it out again for a

Formal review

(~2weeks)

They get it back with all

the comments. Get

those comments

approved by author

once again and then

incorporate them into

the document. And then

send it to the Chief

Engineer and IPT lead

for a Signature review (1

week)

If they are fine with

the document, they

will sign it. If not,

they will send

comments back.

Engineer writes/

update a process

They send the

document to a TW in

the Product Integrity

Team w/ list of

reviewers

TW receives the

document, edits the

document, and sends it

out for 1 - week

technical review

They get it back with all

the comments. Get

those comments

approved by author

incorporate them into

the document. And then

send it out again for a

Formal review (include

Chief Engineer and IPT

Lead (~2weeks)

If no comments

back, then they will

sign it. If comments

are received the

TW will incorporate

them and send it

for a 2-day review

and get it signed.