homework problem

islandgyal
HWSpreadsheet1.xlsx

Lecture 4 Example Modified

Use this example for your HW assignment. This example differs from the lecture example.
Problem Statement
A 10" well connect has been proposed to move 30,000 Mscfd of gas to a trunk line along with a six unit equity compressor station. It is assumed that the new well connect will take approximately one year to build and revenue will not be realized until year one. The flow rate will decline by 90% during the first year of well life and 5% for the remainder of the contract. The contract term is for 10 years only. Assume Labor cost will be 40% of year one revenue for time zero and time one and 30% of the revenue of each of the following years there after. Determine the cost of service at 13% company hurdle rate? What is the NPV of this project at the company hurdle rate? What is the actual rate of return for this project assuming a cost of service to be $0.5/MMBTU?
Initial values
Initial Flow Rate = 30000 Mscfd
Pipe Diameter = 10 in Nominal Pipe
Pipe Length = 5.25 miles
Gas Heating Value = 1100 BTU/scf
Costs and Price
Cost of Service = $0.0500 /MMBTU
Pipe Cost = $100,000.00 /in-mile
Six Unit Equity Compressor station = $13,000,000 /station
Company Hurdle Rate = 13.00%
Assume Labor cost is 30% of Revenue
Volumes
Volumes (Mscf) 0 10,950,000.00 1,095,000.00 547,500.00 273,750.00 136,875.00 68,437.50 34,218.75 17,109.38 8,554.69 4,277.34
Energy Volumes (MMBTU) 0 12,045,000.00 1,204,500.00 602,250.00 301,125.00 150,562.50 75,281.25 37,640.63 18,820.31 9,410.16 4,705.08
Cost Analysis
Year 0 1 2 3 4 5 6 7 8 9 10
Pipeline Costs = -$5,250,000.00
Compression Costs = -$13,000,000
Labor Costs = -$87,928,500.00 -$87,928,500.00 -$6,594,637.50 -$3,297,318.75 -$1,648,659.38 -$824,329.69 -$412,164.84 -$206,082.42 -$103,041.21 -$51,520.61 -$25,760.30
Income = $0.00 $219,821,250.00 $21,982,125.00 $10,991,062.50 $5,495,531.25 $2,747,765.63 $1,373,882.81 $686,941.41 $343,470.70 $171,735.35 $85,867.68
Total Costs = -$106,178,500.00 -$87,928,500.00 -$6,594,637.50 -$3,297,318.75 -$1,648,659.38 -$824,329.69 -$412,164.84 -$206,082.42 -$103,041.21 -$51,520.61 -$25,760.30
Sum Total = -$106,178,500.00 $131,892,750.00 $15,387,487.50 $7,693,743.75 $3,846,871.88 $1,923,435.94 $961,717.97 $480,858.98 $240,429.49 $120,214.75 $60,107.37
Total Costs with 15% contingency = -$122,105,275.00 -$101,117,775.00 -$7,583,833.13 -$3,791,916.56 -$1,895,958.28 -$947,979.14 -$473,989.57 -$236,994.79 -$118,497.39 -$59,248.70 -$29,624.35
Sum Total with contingency = -$122,105,275.00 $118,703,475.00 $14,398,291.88 $7,199,145.94 $3,599,572.97 $1,799,786.48 $899,893.24 $449,946.62 $224,973.31 $112,486.66 $56,243.33
No Contingency Dollars
NPV @ 13.00% = $32,141,370.18
IRR = 40.271%
Profit = $56,429,117.63
Payback Period ~ 6.53 yrs
With Contingency Dollars
NPV @ 13.00% = $3,154,058.96
IRR = 15.270%
Profit = $25,338,540.42
Payback Period ~ 8.28 yrs

Volume Decline

Volume Decline 0 1 2 3 4 5 6 7 8 9 10 10950000 1095000 547500 273750 136875 68437.5 34218.75 17109.375 8554.6875 4277.34375

Years

Volume (Mscf)

HW 4 Well Data

Cum Volume
2019 75,296
2020 114,613
2021 79,534
2022 54,812
2023 46,212
2024 46,096
2025 38,134
2026 ???
2027 ???
2028 ???