Cost ROI
ID Task
Mode
WBS Task Name Duration Start Finish
1 1 Hungry Tiger Project 140 days Mon 7/29/19 Fri 2/7/20
2 1.1 Feasibility Planning 5 days Mon 7/29/19 Fri 8/2/19
3 1.1.1 Analyze The Business Need & Target Market 2 days Mon 7/29/19 Tue 7/30/19
4 1.1.2 Estimate Project Cost & Budgeting 2 days Mon 7/29/19 Tue 7/30/19
5 1.1.3 Risk Assessment 1 day Fri 8/2/19 Fri 8/2/19
6 1.2 Requirement Gathering 15 days Mon 8/5/19 Fri 8/23/19
7 1.2.1 Disucssion with stakeholders 3 days Mon 8/5/19 Wed 8/7/19
8 1.2.2 Priortizing Product Features 3 days Thu 8/8/19 Mon 8/12/19
9 1.2.3 Prepare Business Requirement Document (BRD) 3 days Tue 8/13/19 Thu 8/15/19
10 1.2.4 Prepare Use Cases 3 days Fri 8/16/19 Tue 8/20/19
11 1.2.5 BRD & Use Case Approvals 3 days Wed 8/21/19 Fri 8/23/19
12 1.3 System Design 20 days Mon 8/26/19 Fri 9/20/19
13 1.3.1 Create Pretotype 5 days Mon 8/26/19 Fri 8/30/19
14 1.3.2 Payment Functionality Design 3 days Mon 9/2/19 Wed 9/4/19
15 1.3.3 GPS Functionality Design 3 days Thu 9/5/19 Mon 9/9/19
16 1.3.4 Security Feature 3 days Tue 9/10/19 Thu 9/12/19
17 1.3.5 Embed Audio-Video Functionality 3 days Fri 9/13/19 Tue 9/17/19
18 1.3.6 Data Model 3 days Wed 9/18/19 Fri 9/20/19
19 1.4 Application Development & Testing 100 days Mon 9/23/19 Fri 2/7/20
20 1.4.1 Coding 60 days Mon 9/23/19 Fri 12/13/19
21 1.4.1.1 Payment Functionality Module Dev 40 days Mon 9/23/19 Fri 11/15/19
22 1.4.1.2 Integration with third party payment portal 10 days Mon 11/18/19 Fri 11/29/19
Amar,Prakash Punia
Prakash Priyadarshi
Srikanth
Amar
Srikanth
Jesny,Vikram
16 21 26 31
July 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Midnight Tiger Residen
Date: Fri 7/26/19
ID Task
Mode
WBS Task Name Duration Start Finish
23 1.4.1.3 Integration with google maps, waze & maps 55 days Mon 9/23/19 Fri 12/6/19
24 1.4.1.4 User role & user access definition 30 days Mon 9/23/19 Fri 11/1/19
25 1.4.1.5 2-factor authentication on login & payment screens 15 days Mon 11/4/19 Fri 11/22/19
26 1.4.1.6 Audio-Video preview feature 5 days Mon 12/2/19 Fri 12/6/19
27 1.4.1.7 Unit Testing 5 days Mon 12/9/19 Fri 12/13/19
28 1.4.2 Functional Testing 35 days Mon 12/16/19 Fri 1/31/20
29 1.4.2.1 Functional Testing 15 days Mon 12/16/19 Fri 1/3/20
30 1.4.2.2 Integration Testing 10 days Mon 1/6/20 Fri 1/17/20
31 1.4.2.3 System Testing 10 days Mon 1/20/20 Fri 1/31/20
32 1.4.3 User Acceptance Testing 5 days Mon 2/3/20 Fri 2/7/20
33 1.4.3.1 Business testing 5 days Mon 2/3/20 Fri 2/7/20
16 21 26 31
July 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: Midnight Tiger Residen
Date: Fri 7/26/19
Amar,Prakash Punia
Prakash Priyadarshi
Srikanth
Amar
Srikanth
Jesny,Vikram
Amar
Venkata
Venkata
Venkata
Venkata
Venkata
Ravi
Srujan
Srujan
31 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 3 8
July 2019 August 2019 September 2019 October 2019 November 2019 December 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: Midnight Tiger Residen
Date: Fri 7/26/19
Ravi
Venkata
Venkata
Srujan
12/13
Jesny,Vikram,Android Phone[1 2 handsets],Ipad[1 1 count],Iphone[1 2 handsets]
Amar,Vikram,Android Phone[1 2 handsets],Ipad[1 1 count],Iphone[1 2 handsets]
Amar,Jesny,Vikram,Android Phone[1 2 handsets],Ipad[1 1 count],Iphone[1 2 handsets]
31 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 3 8
July 2019 August 2019 September 2019 October 2019 November 2019 December 2019
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: Midnight Tiger Residen
Date: Fri 7/26/19
Amar,Prakash Punia
Prakash Priyadarshi
Srikanth
Amar
Srikanth
Jesny,Vikram
Amar
Venkata
Venkata
Venkata
Venkata
Venkata
Ravi
Srujan
Srujan
8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2 7 12 17 22 27 1 6 11 16
December 2019 January 2020 February 2020 March 2020 April 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: Midnight Tiger Residen
Date: Fri 7/26/19
Ravi
Venkata
Venkata
Srujan
12/13
Jesny,Vikram,Android Phone[1 2 handsets],Ipad[1 1 count],Iphone[1 2 handsets]
Amar,Vikram,Android Phone[1 2 handsets],Ipad[1 1 count],Iphone[1 2 handsets]
Amar,Jesny,Vikram,Android Phone[1 2 handsets],Ipad[1 1 count],Iphone[1 2 handsets]
8 13 18 23 28 2 7 12 17 22 27 1 6 11 16 21 26 2 7 12 17 22 27 1 6 11 16
December 2019 January 2020 February 2020 March 2020 April 2020
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: Midnight Tiger Residen
Date: Fri 7/26/19