PJM6005 Final Paper

usaggwp
HighFiveGroupWork.docx

Enterprise Project Management Tool Selection and Implementation Project

(WBS)

Sebastian Guevara

Mustafa Bokhary

Xiangling Yang

Jialin Zheng (Catherine)

Junze Li

Surbhi Ithape

Northeastern University

PJM 6005

Michael Madden

Project Overview

The Enterprise Project Management Tool Selection and Implementation (EPMTSI) project is a new project based on previous successful collaborations with TSG. The purpose of the project is to increase the productivity of TSG and the quality of project planning and execution by using more up-to-date and productive PM collaboration tools. The solution should provide TSG's senior managers with the ability to make informed decisions, and provide TSG managers and the TSG board with effective, accurate, and timely project progress information and indicator dashboards. This project provides an opportunity for Tim Inc. to not only consolidate our long-term and outstanding relationship with TSG, but also take it to the next level.

The project's approved budget is $ 650,000, plus an emergency reserve of $ 100,000, controlled by the project sponsor. The project should be fully implemented no later than 1/01/2022, approved and put into operation for widespread use by the enterprise. In addition, the project should complete the project scope statement and detailed plan by the first quarter of 2020 so that the board can approve the project plan integration by the summer of 2020.

WBS

Task Name

1

TSG Project Management Platform Project

1.1

Project Management

1.1.1

Initiation

1.1.1.1

Stakeholder Register

1.1.1.1.1

Develop Stakeholder list

1.1.1.1.2

Contact Key Stakeholders

1.1.1.1.3

Develop Stakeholder register

1.1.1.2

Project Charter

1.1.1.2.1

Review Business case

1.1.1.2.2

Hold first meeting

1.1.1.2.3

Develop Charter

1.1.2

Integrated Project Plan

1.1.2.1

Develop Scope Plan

1.1.2.2

Develop Schedule

1.1.2.3

Develop Budget

1.1.2.4

Develop Risk and Quality Plan

1.1.3

Controlling

1.1.3.1

Performance Documents

1.1.3.1.1

Performance Report

1.1.3.1.2

Project Issues Report

1.1.3.2

Change Control Processes

1.1.3.2.1

Define process

1.1.3.2.2

Develop document templates

1.1.4

Project Planning Complete

1.2

Solution Design

1.2.1

Tool Selection Process

1.2.1.1

Shortlist 4 Potential SW vendors

1.2.1.2

Finalize vendor based on functionality & Price

1.2.2

Project Management Software Tool Selection

1.2.3

Solution Features Layout Design

1.2.4

Dashboard Layout

1.2.5

Final Solution

1.2.6

Finalize Testing Criteria

1.2.7

System Design Complete

1.3

Execution of PM Tool

1.3.1

Project Kick Off Meeting

1.3.2

Verify Users Requirements

1.3.3

System Hardware & Software

1.3.4

Order Solution Hardware & Software

1.3.5

Receive Solution Hardware & Software

1.3.6

Installation of PM Tool Platform

1.3.7

Configure Solution

1.3.8

Integrated Testing of Solution

1.3.9

Execution of PM Tool Complete

1.4

Training

1.4.1

Training Prerequisites

1.4.1.1

Develop Operation Training Module

1.4.1.2

Develop Advanced Training Module

1.4.1.3

Identify Advanced Training Participants

1.4.1.4

Get Management Approval for Training Modules

1.4.2

Conduct Operational Training

1.4.3

Conduct Advanced Training

1.5

Change Management

1.5.1

Assess impact of new PM tool

1.5.2

Propose & Draft Change Management Strategy Initiative

1.6

Closeout

1.6.1

Project Acceptance

1.6.2

Finalize Documentation

1.6.3

Perform Project Audit

1.6.4

Announce Project Closure

WBSD

WBS Level

WBS Code

WBS Element

Name

Description of Work

Deliverables

Committed Resources

Rom

0

1

TSG Project Management Platform Project

Project Name

Completion on Project Successfully

The Project Manager

Stakeholders

Project Team

1

1.1

Project Management

Start of the TSG Project Management

Software of PM and

Project manager

Project Sponsor

1.1.1

Initiation

Initiating the Project work

Business Case and Project Charter

Project Manager

The Operation Manager

1.1.1.1

Project Establishment

Start the process of the project

Project team on duty

Project Manager

Project Team members

1.1.1.2

Stakeholder Identification

Identifying stakeholder’s interest

Mark stakeholders’ interest

Project Manager

Stakeholders

1.1.1.3

Project Charter

Building the project charter

A reliable project charter

Project Manager

Project team members

1.1.1.3.1

Initiate meetings

Meet to identify the project charter

Fundamental of the project charter

Project manager

Project sponsor

Project team members

1.1.1.3.2

Develop Charter and business case

Developing the first version of the project charter

First version of the project charter

Project manager

Project sponsor

Project team members

1.1.2

Integrated Project Plan

Making the first version of project plan

Set up basic elements of the project plan

Project manager

Project sponsor

Project team members

1.1.2.1

Develop Scope Plan

Scope Plan development

Developing the scope plan

Project manager

Project team members

1.1.2.2

Develop Schedule

Schedule set up

Setting up time limits

Project manager

Project team members

1.1.2.3

Develop Risk and Quality Plan

Risk and quality control

A plan to limit the risk and quality

Project manager

Project team members

1.1.2.4

Execution

Start the project

Be prepared to start the project

Project manager

Project team members

1.1.3

Executing all the planned tasks

Get the project into process

Start the project follow all plans

Project manager

Project team members

1.1.3.1

Carrying out meetings for software better execution

Optimize the execution process

New software for better execution

Project manager

Project team members

1.1.3.1.1

 Control and Monitor

Keeping the project on the right track

The project process as planed

Project manager

Project team members

1.1.3.1.2

Performance Documents

Evaluation of the process performance

Keep the planed performance

Project manager

Project team members

1.1.3.2

 Performance Report

Report the project performance so far

Noted the project processing status

Project manager

Project team members

1.1.3.2.1

 Project Issues Report

Report issues that the occurred during processing the project

Clarifying the issue and have a solution

Project manager

Project team members

Project sponsor

1.1.3.2.2

Change Control Processes

Optimized the control process

Gain a better performance

Project manager

Project team members

1.1.3.2.1

Define process

Define the process status of the project

Knowing the process status

Project manager

Project team members

1.1.3.2.2

Develop document templates

Developing templates for later usage

Some usable templates

Project manager

Project team members

1.1.4

Project Planning Complete

Finalized project plans

All project plans completed and ready to be followed

Project manager

Project team members

2

1.2

Solution Design 

Preparing solutions for accident

Reasonable solutions for accidents

Project manager

Project team members

1.2.1

Tool Selection Process

Select tool

Shortlist 4 Potential SW vendors

Project manager

Project team members

1.2.2

Finalize vendor based on functionality & Price

Finalize vendor

Vendor list

Project manager

Project team members

1.2.3

Project Management Software Tool Selection

Select Project Management Software Tool

Project Management Software Tool list

Project manager

Project team members

1.2.4

Solution Features Layout Design

Design Solution Features Layout

Solution Features Layout Draft

Project manager

Project team members

1.2.5

 Dashboard Layout

Doing  Dashboard Layout

 Dashboard Layout File

Project manager

Project team members

1.2.6

 Final Solution

Find Solutions

Solution list

Project manager

Project team members

1.2.7

Finalize Testing Criteria

Pick Finalize Testing Criteria

Finalize Testing Criteria

Project manager

Project team members

1.2.8

System Design Complete

Complete System Design

System Design Plan

Project manager

Project team members

3

1.3

Execution of PM Tool

PM tool related things

PM tool list

Project manager

Project team members

1.3.1

Project Kick Off Meeting

Prepare Project Kick Off Meeting

Project Kick Off Meeting Plan

Project manager

Project team members

1.3.2

Verify Users Requirements

Verify Users Requirements

Requirements list

Project manager

Project team members

1.3.3

 System Hardware & Software

 Pick System Hardware & Software

Contract

Project manager

Project team members

1.3.4

Order Solution Hardware & Software

Order Solution Hardware & Software

Contract

Project manager

Project team members

1.3.5

 Installation of PM Tool Platform

PM Tool Platform Installation

Installation contract

Project manager

Project team members

1.3.6

Configure Solution

Configure Solution

Solution list

Project manager

Project team members

1.3.7

 Integrated Testing of Solution

Integrated solution test

Test report

Project manager

Project team members

1.3.8

Execution of PM Tool Complete

Complete PM tool execution

PM tool execution report

Project manager

Project team members

4

1.4

 Training

Doing training

Training plan

Project manager

Project team members

1.4.1

Training Prerequisites

Prepare training

Training Prerequisites list

Project manager

Project team members

1.4.1.1

Develop Operation Training Module

Develop Operation Training Module

Operation Training Module

Project manager

Project team members

1.4.1.2

Develop Advanced Training Module

Develop Advanced Training Module

Advanced Training Module

Project manager

Project team members

1.4.1.3

 Identify Advanced Training Participants

 Identify Advanced Training Participants

Training Participants

list

Project manager

Project team members

1.4.1.4

Get Management Approval for Training

Module

Get Management Approval for Training

Module

Agreement file

Project manager

Project team members

1.4.2

 Conduct Operational Training

 Conduct Operational Training

Operational Training contract

Project manager

Project team members

1.4.3

Conduct Advanced Training

Conduct Advanced Training

Advanced Training contract

Project manager

Project team members

5

1.5

Change Management

Management change requirements

Change Management Documents

Project manager

Project team members

1.5.1

 Assess impact of new PM tool

Estimate new tool impact

Assessment report

Project manager

Project team members

1.5.2

 Propose & Draft Change Management Strategy Initiative

Propose & Draft Change Management Strategy Initiative

Change Management Strategy Initiative

Project manager

Project team members

6

1.6

Closure

Finish Project

Closure report

Project manager

Project team members

1.6.1

 Project Acceptance

Get agreement

Signature file

Project manager

Project team members

1.6.2

Finalize Documentation

Collect document

Documents

Project manager

Project team members

1.6.3

Perform Project Audit

Project audit process

Project Audit Meeting

Project manager

Project team members

1.6.4

  Announce Project Closure

Prepare project closure

Project Closure

Statement

Project manager

Project team members

COMMENT

100% Rule: The first thing to understand is that the purpose of WBS is to break down the project into the deliverables that it is intended to achieve. The deliverables are decomposed further into sub-deliverables and activities. The decomposed activities add up to include everything that was required to be achieved under the deliverable or sub-deliverable, and those deliverables add up to include everything that was required to be done in the project.

The Enterprise Project Management (PM) Tool Selection and Implementation Project is a major initiative of TestSmart Group (TSG), which is not only complex but also entails a full-fledged organizational change management strategy once implemented. Tim Inc. is fully aware of the customer’s expectations from this project and has, therefore, endeavored to create an exhaustive work breakdown structure using the 100% rule, so that it encompasses that all the agreed deliverables of the project, whether they are internal, external or interim, and nothing is left out in terms of works that is required to be completed under the project.

Starting from Project Management, right down to the closing phase of the project, each deliverable has been broken down into sub-deliverables or activities. The sub-deliverables have been further decomposed into smaller, independent and easy to manage work-packages. The 100% rule has been applied at every level of the WBS hierarchy such that the total work performed at the work package or activity level adds up to the relevant sub-deliverable and the sum of all sub-deliverables, in turn, adds up to the deliverable. The project deliverables, eventually, make up for the entire project.

Let us take the example of Project Management, in our WBS above. The project management is a level 2 deliverable which has been decomposed into 3, level 3 sub-deliverables, namely Initiating, Planning and Controlling using the parent child relationship. These 3 sub-deliverables have further been decomposed into level 4 and sometimes even level 5 activities so that each work package is at an appropriate level where it can be worked upon independently, with clearly defined resources and objectives. It can be seen that the sum of the work at the child level equals 100% of the work required to be delivered under the parent level.

Using the 100% rule, we have been able to ensure that the entire work required to be done under the project has been adequately addressed and no requirement has been overlooked. Similarly, it has also helped us to identify any duplication of work, or any out of scope activity that might have crept into the WBS. By implementing the 100% rule it is safe to assume that the project will and has taken into consideration all of the deliverables it will tackle. This is helpful in managing scope because it lets the stakeholders have a document to be able to refer to, with regards to expectations and what is in scope and out of scope. Everything included in the WBS is assumed to be a deliverable for the project. However, everything outside the WBS is considered out of scope. Therefore this document will help to keep the PM accountable for what is expected to be accomplished at the end of the project.

Reference

Business case retrieved from https://s3.us-east-1.amazonaws.com/blackboard.learn.xythos.prod/5a3148150d016/19001361?response-content-disposition=inline%3B%20filename%2A%3DUTF-8%27%27PJM6005-Team%2520Project%2520Scenario-Master-2020%25281%2529.pdf&response-content-type=application%2Fpdf&X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Date=20200314T000925Z&X-Amz-SignedHeaders=host&X-Amz-Expires=21600&X-Amz-Credential=AKIAIL7WQYDOOHAZJGWQ%2F20200314%2Fus-east-1%2Fs3%2Faws4_request&X-Amz-Signature=4cc5b7443ac9e3a71239b7be04842189625c19cf4b25da5d090eaf1619652c07

Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK® Guide) —Sixth edition.