1.0

2.0:

Product Research

· Task 1: Find similar designs

1. Members Responsible: everyone

2. Objective: To find current technology on the market

3. Deliverables: A literature survey

4. Required Resources: A computer for research

5. Schedule/Cost Estimate: February 1-February 7. No cost

· Task 2: Find potential competition

1. Members Responsible: everyone

2. Objective: To find existing products with the same application

3. Deliverables: Links to the products

4. Required Resources: A computer for research

5. Schedule/Cost Estimate: February 7-February 14. No cost

Product Planning

· Task 1: Anticipate manufacturing requirements

1. Members Responsible: Devontay, Mohanned

2. Objective: To consider future costs, personnel, and equipment needed

3. Deliverables: A few paragraphs

4. Required Resources: A computer for research

5. Schedule/Cost Estimate: February 14-February 21. No cost

· Task 2: Find customer requirements

1. Members Responsible: everyone

2. Objective: To find the needs of the customer

3. Deliverables: Survey results

4. Required Resources: survey, and potential customers

5. Schedule/Cost Estimate: February 21-February 28. No cost

Product Development

· Task 1: Design product

1. Members Responsible: Noah, Dakota

2. Objective: To brainstorm and develop ideas for the product

3. Deliverables: Sketches and a decision on how the product will work

4. Required Resources: A computer

5. Schedule/Cost Estimate: February 28-March 7. No cost

· Task 2: Create models and drawings for components

1. Members Responsible: Devontay, Mohanned

2. Objective: To create the components and drawings

3. Deliverables: Models and prints

4. Required Resources: computer with modeling capabilities

5. Schedule/Cost Estimate: March 7-March 14. No cost

Testing and Validation

· Task 1: Analyze stresses in ANSYS

1. Members Responsible: Adam, Noah

2. Objective: To anticipate potential failure in our product

3. Deliverables: Stress and deformation results

4. Required Resources: A computer with ANSYS

5. Schedule/Cost Estimate: March 14-March 21. No cost

· Task 2: Create Prototype

1. Members Responsible: Dakota

2. Objective: To create and test a prototype

3. Deliverables: prototype

4. Required Resources: 3D printer, and metal spring

5. Schedule/Cost Estimate: March 21-March 28. Cost-printing material ($2)

Product Development

· Task 1: Find a manufacturer (molds and assembly process)

1. Members Responsible: everyone

2. Objective: To find a manufacturer to create our product

3. Deliverables: a manufacturer report

4. Required Resources: A computer, and connections

5. Schedule/Cost Estimate: undetermined. Cost-?

· Task 2: Develop marketing plan and sell product

1. Members Responsible: everyone

2. Objective: To finalize the product into the market

3. Deliverables: finished product

4. Required Resources: manufacturing process and potential sellers

5. Schedule/Cost Estimate: undetermined. Cost-?

Product Research

Design Organization: Group 5    

Date:  2/25/18    

Proposed Product Name: Reel Quik    

Task  1    

Name of Task:  Find Similar Design    

Objective :  To find similar technology on the market    

Deliverables:  Literature survey    

     

Decisions needed:

Decision 1:  Research Products    

Decision 2:  Create literature survey    

Personnel needed

Title:  Researcher     Hours:  3     Percent full time:     

Title:  Researcher    Hours:  3     Percent full time:     

Time estimate Total hours:  6     Lapsed time(include units):      

Sequence: Predecessors:       Successors:  Find Potential Competition    

Start Date:  2/1/18     Finish Date:  2/7/18    

Costs: Capital Equipment  N/A     Disposables:  N/A    

Task  2    

Name of Task:  Find Potential Competition    

Objective :  To find existing products with the same application    

Deliverables:  Links to the products    

     

Decisions needed:

Decision 1:  Determine whether product is in the same application    

Decision 2:      

Personnel needed

Title:  Researcher     Hours:  3     Percent full time:     

Title:  Researcher     Hours:  3     Percent full time:     

Time estimate Total hours:  6     Lapsed time(include units):      

Sequence: Predecessors:       Successors:      

Start Date:  2/7/18     Finish Date:  2/14/18    

Costs: Capital Equipment       Disposables:      

Team member:  Noah    

Prepared by: Noah    

Team member:  Dakota    

Checked by: Dakota    

Team member:  Adam    

Approved by: Noah    

Team member:  Devontay, Mohanned    

The Mechanical Design Process Designed by Professor David G. Ullman

Copyright 2008, McGraw Hill Form # 10.0

Product Planning

Design Organization: Group 5    

Date:  2/25/18    

Proposed Product Name: Reel Quik    

Task  1    

Name of Task:  Anticipate Manufacturing Requirements    

Objective :  To consider future costs, personnel, and equipment needed   

Deliverables:  A few paragraphs    

     

Decisions needed:

Decision 1:  Determine manufacturing possibilities    

Decision 2:      

Personnel needed

Title:  Designer     Hours:  3     Percent full time:     

Title:       Hours:       Percent full time:     

Time estimate Total hours:  3     Lapsed time(include units):      

Sequence: Predecessors:       Successors:      

Start Date:  2/14/18     Finish Date:  2/21/18    

Costs: Capital Equipment  N/A     Disposables:  N/A    

Task  2    

Name of Task:  Find Customer Requirements    

Objective :  To find the needs of the customer    

Deliverables:  Survey results    

     

Decisions needed:

Decision 1:  Determine how to meet the customer needs    

Decision 2:      

Personnel needed

Title:  Surveyor     Hours:  5     Percent full time:     

Title:  Surveyor     Hours:  5     Percent full time:     

Time estimate Total hours:  10     Lapsed time(include units):      

Sequence: Predecessors:  Find potential competition     Successors:  product development    

Start Date:  2/21/18     Finish Date:  2/28/18    

Costs: Capital Equipment       Disposables:      

Team member:  Noah    

Prepared by: Noah    

Team member:  Dakota    

Checked by: Dakota    

Team member:  Adam    

Approved by: Noah    

Team member:  Devontay, Mohanned    

The Mechanical Design Process Designed by Professor David G. Ullman

Copyright 2008, McGraw Hill Form # 10.0

Product Development

Design Organization: Group 5    

Date:  2/25/18    

Proposed Product Name: Reel Quik    

Task  1    

Name of Task:  Design Product    

Objective :  To brainstorm and develop ideas for the product   

Deliverables: sketches    

     

Decisions needed:

Decision 1:  Determine how the product will work    

Decision 2:      

Personnel needed

Title:  Designer     Hours:   4    Percent full time:     

Title:  Designer     Hours:   4    Percent full time:     

Time estimate Total hours:  8     Lapsed time(include units):      

Sequence: Predecessors:  customer survey     Successors:  create models and drawings for components    

Start Date:  2/28/18     Finish Date:  3/7/18    

Costs: Capital Equipment  N/A     Disposables:  N/A    

Task  2    

Name of Task:  Create models and drawings for components    

Objective :  To create the components and drawings    

Deliverables:  Models and Prints    

     

Decisions needed:

Decision 1:  Determine if design incorporates customer needs and will work    

Decision 2:      

Personnel needed

Title:  Designer     Hours:  4     Percent full time:     

Title:  Designer     Hours:  4     Percent full time:     

Time estimate Total hours:  8     Lapsed time(include units):      

Sequence: Predecessors:  Determine how product will work     Successors:      

Start Date:  3/7/18     Finish Date:  3/14/18    

Costs: Capital Equipment       Disposables:      

Team member:  Noah    

Prepared by: Noah    

Team member:  Dakota    

Checked by: Dakota    

Team member:  Adam    

Approved by: Noah    

Team member:  Devontay, Mohanned    

The Mechanical Design Process Designed by Professor David G. Ullman

Copyright 2008, McGraw Hill Form # 10.0

Testing and Validation

Design Organization: Group 5    

Date:  2/25/18    

Proposed Product Name: Reel Quik    

Task  1    

Name of Task:  Analyze stresses in ANSYS    

Objective :  To anticipate future failures in our prodcut   

Deliverables: stress and deformation results    

     

Decisions needed:

Decision 1:  Determine what loads to apply    

Decision 2:      

Personnel needed

Title:  Designer     Hours:  3     Percent full time:     

Title:  Designer     Hours:  3     Percent full time:     

Time estimate Total hours:  6     Lapsed time(include units):      

Sequence: Predecessors:  Create models and Drawings     Successors:  Create a prototype    

Start Date:  3/14/18     Finish Date:  3/21/18    

Costs: Capital Equipment  N/A     Disposables:  N/A    

Task  2    

Name of Task:  Create Prototype    

Objective :  To create and test a prototype    

Deliverables:  prototype    

     

Decisions needed:

Decision 1:  Determine if the design works as expected    

Decision 2:      

Personnel needed

Title:  Designer     Hours:  3     Percent full time:     

Title:       Hours:       Percent full time:     

Time estimate Total hours:  3     Lapsed time(include units):      

Sequence: Predecessors:  Analyze stresses in ANSYS     Successors:      

Start Date:  3/7/18     Finish Date:  3/14/18    

Costs: Capital Equipment  3D printer     Disposables:      

Team member:  Noah    

Prepared by: Noah    

Team member:  Dakota    

Checked by: Dakota    

Team member:  Adam    

Approved by: Noah    

Team member:  Devontay, Mohanned    

The Mechanical Design Process Designed by Professor David G. Ullman

Copyright 2008, McGraw Hill Form # 10.0

Product Development

Design Organization: Group 5    

Date:  2/25/18    

Proposed Product Name: Reel Quik    

Task  1    

Name of Task:  Find a manufacturer (mold and assembly process)    

Objective :  To find a manufacturer to create our product   

Deliverables: A manufacturer report    

     

Decisions needed:

Decision 1:  Determine exactly what our process requires    

Decision 2:      

Personnel needed

Title:  Designer     Hours:   40    Percent full time:     

Title:  Designer     Hours:   40    Percent full time:     

Time estimate Total hours:  3     Lapsed time(include units):      

Sequence: Predecessors:  Anticipate Manufacutring needs     Successors:  Determine where to sell product    

Start Date:  Unsure     Finish Date: Unsure    

Costs: Capital Equipment  N/A     Disposables:  N/A    

Task  2    

Name of Task:  Develop marketing plan and sell product    

Objective :  To finalize the product into the market    

Deliverables:  finished product    

     

Decisions needed:

Decision 1:  Determine where to sell the product    

Decision 2:      

Personnel needed

Title:  Marketing Agent     Hours:   40    Percent full time:     

Title:       Hours:       Percent full time:     

Time estimate Total hours:  3     Lapsed time(include units):      

Sequence: Predecessors:  find a manufacturer     Successors:      

Start Date:  Unsure     Finish Date:  Unsure    

Costs: Capital Equipment       Disposables:      

Team member:  Noah    

Prepared by: Noah    

Team member:  Dakota    

Checked by: Dakota    

Team member:  Adam    

Approved by: Noah    

Team member:  Devontay, Mohanned    

The Mechanical Design Process Designed by Professor David G. Ullman

Copyright 2008, McGraw Hill Form # 10.0

4.0

a.

b.

Product Planning Task 1 = = = 3 hours

References