Project scheduling assignment

Rosemaryz
Excercise18.docx

18. The optical disk project team has started gathering the information necessary to develop the project network—predecessor activities and activity times in weeks. The results of their meeting are found in the following table.

Activity Description Duration Predecessor

1 Define scope 6 None

2 Define customer problems 3 1

3 Define data records and relationships 5 1

4 Mass storage requirements 5 2, 3

5 Consultant needs analysis 10 2 3

6 Prepare installation network 3 4, 5

7 Estimate costs and budget 2 4, 5

8 Design section “point” system 1 4, 5

9 Write request proposal 5 4, 5

10 Compile vendor list 3 4, 5

11 Prepare mgmt. control system 5 6, 7

12 Prepare comparison report 5 9, 10

13 Compare system “philosophies” 3 8, 12

14 Compare total installation 2 8, 12

15 Compare cost of support 3 8, 12

16 Compare customer satisfaction level 10 8, 12

17 Assign philosophies points 1 13

18 Assign installation cost 1 14

19 Assign support cost 1 15

20 Assign customer satisfaction points 1 16

21 Select best system 1 11, 17, 18, 19, 20

22 Order system 1 21

The project team has requested that you create a network for the project, and deter-mine if the project can be completed in 45 weeks.