| Bottom-Up Estimate [All detail resources] |
| | Unit | Intensity | Duration | Effort | Total | Unit | Extension $ |
| | | | (Day) | | Unit | Cost |
| W1 Prefabrication House | | | | | | | $58,310 |
| W1.1 Design Document | | | | | | | $22,080 |
| W1.1.1 Architecture Design Drawing | | | | | | | $13,880 |
| W1.1.1.1 Exterior Design Drawing | | | | | | | $7,050 |
| R1 Supervisor |
| R1.1 Design Manager | Staff Hour | 1 | 20 | 20 | 160 | $30 | $4,800 |
| R2 Designer and Technician |
| R2.1 Architect | Day | 1 | 30 | 30 | 30 | $60 | $1,800 |
| R2.9 Draftman |
| R2.9.1 Architecture Draftsman | Day | 1 | 15 | 15 | 15 | $20 | $300 |
| R4 Equipment and Tools |
| R4.13 AutoCAD2002 | N/A | 1 | 10 | 10 | ** | ** | $75 |
| R4.14 3D Viz Program | N/A | 1 | 10 | 10 | ** | ** | $75 |
| W1.1.1.2 Interior Design Drawing | | | | | | | $3,900 |
| R1 Supervisor |
| R1.1 Design Manager | Staff Hour | 1 | 10 | 10 | 80 | $30 | $2,400 |
| R2 Designer and Technician |
| R2.2 Interior Designer | Day | 1 | 20 | 20 | 20 | $60 | $1,200 |
| R2.9 Draftman |
| R2.9.3 Interior Draftman | Day | 1 | 15 | 15 | 15 | $20 | $300 |
| R4 Equipment and Tools |
| R4.13 AutoCAD2002 | N/A | 1 | 10 | 10 | ** | ** | ** |
| R4.14 3D Viz Program | N/A | 1 | 5 | 5 | ** | ** | ** |
| W1.1.1.3 Landscape Design Drawing | | | | | | | $2,930 |
| R1 Supervisor |
| R1.1 Design Manager | Staff Hour | 1 | 2 | 2 | 16 | $30 | $480 |
| R2 Designer and Technician |
| R2.3 Landscape Designer | Day | 1 | 20 | 20 | 20 | $60 | $1,200 |
| R2.8 Sanitary Engineer | Day | 1 | 15 | 15 | 15 | $50 | $750 |
| R2.9 Draftman |
| R2.9.1 Landscaping Draftman | Day | 1 | 15 | 15 | 15 | $20 | $300 |
| R4 Equipment and Tools |
| R4.1 Survey Equipment | Day | 1 | 5 | 5 | 5 | $40 | $200 |
| R4.13 AutoCAD2002 | Day | 1 | 10 | 10 | ** | ** | ** |
| R4.14 3D Viz Program | Day | 1 | 5 | 5 | ** | ** | ** |
| W1.1.2 Engineer Design Drawing | | | | | | | $3,600 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 20 | 20 | 20 | $50 | $1,000 |
| R2 Designer and Technician |
| R2.4 Civil Engineer | Day | 1 | 20 | 20 | 20 | $60 | $1,200 |
| R2.5 Structural Engineer | Day | 1 | 20 | 20 | 20 | $50 | $1,000 |
| R2.9 Draftman |
| R2.9.2 Engineering Draftsman | Day | 1 | 20 | 20 | 20 | $20 | $400 |
| R4 Equipment and Tools |
| R4.13 AutoCAD2002 | N/A | 1 | 20 | 20 | ** | ** | ** |
| W1.1.3 Infrastructure Design Drawing | | | | | | | $4,600 |
| W1.1.3.1 Electrical Design Drawing | | | | | | | $1,200 |
| R2 Designer and Technician |
| R2.7 Electrical Engineer | Day | 1 | 20 | 20 | 20 | $50 | $1,000 |
| R2.9 Draftman |
| R2.9.2 Engineering Draftsman | Day | 1 | 10 | 10 | 10 | $20 | $200 |
| R4 Equipment and Tools |
| R4.13 AutoCAD2002 | N/A | 1 | 10 | 10 | ** | ** | ** |
| W1.1.3.2 Water Supply Design Drawing | | | | | | | $2,200 |
| R2 Designer and Technician |
| R2.6 Machanical Engineer | Day | 1 | 20 | 20 | 20 | $50 | $1,000 |
| R2.8 Sanitary Engineer | Day | 1 | 20 | 20 | 20 | $50 | $1,000 |
| R2.9 Draftman |
| R2.9.2 Engineering Draftsman | Day | 1 | 10 | 10 | 10 | $20 | $200 |
| R4 Equipment and Tools |
| R4.13 AutoCAD2002 | N/A | 1 | 10 | 10 | ** | ** | ** |
| W1.1.3.3 Air-Conditioning Design Drawing | | | | | | | $1,200 |
| R2 Designer and Technician |
| R2.6 Machanical Engineer | Day | 1 | 20 | 20 | 20 | $50 | $1,000 |
| R2.9 Draftman |
| R2.9.2 Engineering Draftsman | Day | 1 | 10 | 10 | 10 | $20 | $200 |
| R4 Equipment and Tools |
| R4.13 AutoCAD2002 | N/A | 1 | 10 | 10 | ** | ** | ** |
| W1.2 Structure | | | | | | | $30,040 |
| W1.2.1 Building Structure | | | | | | | $22,300 |
| W1.2.1.1 First Floor | | | | | | | $11,515 |
| W1.2.1.1.1 Bearing-Wall Foundation Structure | | | | | | | $4,460 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 5 | 5 | 5 | $50 | $250 |
| R2 Designer and Technician |
| R2.5 Structural Engineer | Day | 1 | 5 | 5 | 5 | $50 | $250 |
| R3 Construction Technician |
| R3.3 Carperter | Day | 3 | 2 | 6 | 6 | $10 | $60 |
| R3.5 Sheet-Metal Worker | Day | 3 | 5 | 15 | 15 | $10 | $150 |
| R3.6 Laborer | Day | 3 | 3 | 9 | 9 | $10 | $90 |
| R3.7 Welding Technician | Day | 2 | 3 | 6 | 6 | $10 | $60 |
| R4 Equipment and Tools |
| R4.1 Survey Equipment | Day | 1 | 1 | 1 | 1 | $40 | $40 |
| R4.2 Dump Truck | Day | 1 | 3 | 3 | 3 | $20 | $60 |
| R4.3 Backhoe | Day | 1 | 2 | 2 | 2 | $50 | $100 |
| R4.4 Pile Driver | Day | 1 | 2 | 2 | 2 | $20 | $40 |
| R4.5 Trailer | Day | 1 | 5 | 5 | 5 | $25 | $125 |
| R4.6 Welding Machine | Day | 1 | 3 | 3 | 3 | $20 | $60 |
| R4.7 Concrete Mixer | Day | 1 | 5 | 5 | 5 | $25 | $125 |
| R4.10 Concrete Pump | Day | 1 | 5 | 5 | 5 | $60 | $300 |
| R4.11 Bucket Truck | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.12 Tractor | Day | 1 | 5 | 5 | 5 | $25 | $125 |
| R5 Material |
| R5.1 Structural | Ton | 0.50 Tons | * | * | 0.5 | $300 | $150 |
| R5.3 Concrete | Bag | 10 Bags | * | * | 10 | $10 | $100 |
| R5.6 Reinforce Steel | Ton | 1 Ton | * | * | 1 | $300 | $300 |
| R5.7 Pile | Pile | 40 Piles | * | * | 40 | $50 | $2,000 |
| W1.2.1.1.2 Long-Span Column Structure | | | | | | | $1,245 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R2 Designer and Technician |
| R2.5 Structural Engineer | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R3 Construction Technician |
| R3.3 Carperter | Day | 3 | 2 | 6 | 6 | $10 | $60 |
| R3.5 Sheet-Metal Worker | Day | 3 | 2 | 6 | 6 | $10 | $60 |
| R3.6 Laborer | Day | 3 | 3 | 9 | 9 | $10 | $90 |
| R3.7 Welding Technician | Day | 2 | 2 | 4 | 4 | $10 | $40 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 2 | 2 | 2 | $20 | $40 |
| R4.7 Concrete Mixer | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.10 Concrete Pump | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R5 Material |
| R5.1 Structural | Ton | 0.50 Tons | * | * | 0.5 | $300 | $150 |
| R5.3 Concrete | Bag | 10 Bags | * | * | 10 | $10 | $100 |
| R5.6 Reinforce Steel | Ton | 0.50 Ton | * | * | 0.5 | $300 | $150 |
| W1.2.1.1.3 Pre-Fabrication Floor | | | | | | | $1,765 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 2 | 2 | 2 | $50 | $100 |
| R2 Designer and Technician |
| R2.4 Civil Engineer | Day | 1 | 2 | 2 | 2 | $60 | $120 |
| R2.5 Structural Engineer | Day | 1 | 2 | 2 | 2 | $50 | $100 |
| R3 Construction Technician |
| R3.3 Carperter | Day | 3 | 1 | 3 | 3 | $10 | $30 |
| R3.5 Sheet-Metal Worker | Day | 1 | 2 | 2 | 2 | $10 | $20 |
| R3.6 Laborer | Day | 3 | 2 | 6 | 6 | $10 | $60 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 2 | 2 | 2 | 20 | $40 |
| R4.7 Concrete Mixer | Day | 1 | 2 | 2 | 2 | 25 | $50 |
| R4.8 Power Float | Day | 1 | 2 | 2 | 2 | 60 | $120 |
| R4.9 Crane | Day | 1 | 2 | 2 | 2 | 50 | $100 |
| R4.10 Concrete Pump | Day | 1 | 2 | 2 | 2 | 60 | $120 |
| R4.12 Tractor | Day | 1 | 2 | 2 | 2 | $25 | $50 |
| R5 Material |
| R5.1 Structural | Ton | 0.25 Tons | * | * | 0.25 | $300 | $75 |
| R5.3 Concrete | Bag | 3 Bags | * | * | 3 | $10 | $30 |
| R5.4 Pre-Fabrication Panel | Panel | 10 Panels | * | * | 10 | $75 | $750 |
| W1.2.1.1.4 Adjustable Pre-Fabrication Wall | | | | | | | $3,085 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 1 | 1 | 1 | $50 | $50 |
| R2 Designer and Technician |
| R2.4 Civil Engineer | Day | 1 | 1 | 1 | 1 | $60 | $60 |
| R2.5 Structural Engineer | Day | 1 | 1 | 1 | 1 | $50 | $50 |
| R3 Construction Technician |
| R3.3 Carperter | Day | 3 | 1 | 3 | 3 | $10 | $30 |
| R3.5 Sheet-Metal Worker | Day | 3 | 1 | 3 | 3 | $10 | $30 |
| R3.6 Laborer | Day | 3 | 1 | 3 | 3 | $10 | $30 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 2 | 2 | 2 | $20 | $40 |
| R4.7 Concrete Mixer | Day | 1 | 2 | 2 | 2 | $25 | $50 |
| R4.8 Power Float | Day | 1 | 2 | 2 | 2 | $60 | $120 |
| R4.9 Crane | Day | 1 | 2 | 2 | 2 | $50 | $100 |
| R4.10 Concrete Pump | Day | 1 | 2 | 2 | 2 | $60 | $120 |
| R4.12 Tractor | Day | 1 | 2 | 2 | 2 | $25 | $50 |
| R5 Material |
| R5.1 Structural | Ton | 0.25 Tons | * | * | 0.25 | $300 | $75 |
| R5.3 Concrete | Bag | 3 Bags | * | * | 3 | $10 | $30 |
| R5.4 Pre-Fabrication Panel | Panel | 30 Panels | * | * | 30 | $75 | $2,250 |
| W1.2.1.1.5 Waterproof Concrete' Infrastructure Control Room | | | | | | | $960 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 2 | 2 | 2 | $50 | $100 |
| R2 Designer and Technician |
| R2.5 Structural Engineer | Day | 1 | 2 | 2 | 2 | $50 | $100 |
| R3 Construction Technician |
| R3.3 Carperter | Day | 3 | 2 | 6 | 6 | $10 | $60 |
| R3.5 Sheet-Metal Worker | Day | 2 | 2 | 4 | 4 | $10 | $40 |
| R3.6 Laborer | Day | 3 | 2 | 6 | 6 | $10 | $60 |
| R3.7 Welding Technician | Day | 2 | 2 | 4 | 4 | $10 | $40 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 2 | 2 | 2 | $20 | $40 |
| R4.7 Concrete Mixer | Day | 1 | 2 | 2 | 2 | $25 | $50 |
| R4.10 Concrete Pump | Day | 1 | 2 | 2 | 2 | $60 | $120 |
| R5 Material |
| R5.1 Structural | Ton | 0.50 Tons | * | * | 0.5 | $300 | $150 |
| R5.3 Concrete | Bag | 5 Bags | * | * | 5 | $10 | $50 |
| R5.6 Reinforce Steel | Ton | 0.50 Ton | * | * | 0.5 | $300 | $150 |
| W1.2.1.2 Second Floor | | | | | | | $4,860 |
| W1.2.1.2.1 Light-Weight Bearing Wall | | | | | | | $1,760 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R2 Designer and Technician |
| R2.5 Structural Engineer | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R2.4 Civil Engineer | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R3 Construction Technician |
| R3.5 Sheet-Metal Worker | Day | 3 | 3 | 9 | 9 | $10 | $90 |
| R3.3 Carperter | Day | 3 | 3 | 9 | 9 | $10 | $90 |
| R3.7 Welding Technician | Day | 2 | 3 | 6 | 6 | $10 | $60 |
| R3.6 Laborer | Day | 4 | 3 | 12 | 12 | $10 | $120 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 3 | 3 | 3 | $20 | $60 |
| R4.7 Concrete Mixer | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.8 Power Float | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R4.9 Crane | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R4.10 Concrete Pump | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R4.12 Tractor | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R5 Material |
| R5.1 Structural | Ton | 0.25 Tons | * | * | 0.25 | $300 | $75 |
| R5.3 Concrete | Bag | 5 Bags | * | * | 5 | $10 | $50 |
| R5.6 Reinforce Steel | Ton | 0.25 Ton | * | * | 0.25 | $300 | $75 |
| WW1.2.1.2.2 Pre-Fabrication Floor | | | | | | | $1,845 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 1 | 1 | 1 | $50 | $50 |
| R2 Designer and Technician |
| R2.5 Structural Engineer | Day | 1 | 1 | 1 | 1 | $50 | $50 |
| R2.4 Civil Engineer | Day | 1 | 1 | 1 | 1 | $60 | $60 |
| R3 Construction Technician |
| R3.5 Sheet-Metal Worker | Day | 3 | 1 | 3 | 3 | $10 | $30 |
| R3.3 Carperter | Day | 2 | 1 | 2 | 2 | $10 | $20 |
| R3.6 Laborer | Day | 4 | 1 | 4 | 4 | $10 | $40 |
| R3.7 Welding Technician | Day | 2 | 1 | 2 | 2 | $10 | $20 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 3 | 3 | 3 | $20 | $60 |
| R4.7 Concrete Mixer | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.8 Power Float | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R4.9 Crane | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R4.10 Concrete Pump | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R4.12 Tractor | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R5 Material |
| R5.1 Structural | | 0.25 Tons | * | * | 0.25 | $300 | $75 |
| R5.3 Concrete | | 3 Bags | * | * | 3 | $10 | $30 |
| R5.4 Pre-Fabrication Panel | | 10 Panels | * | * | 10 | $75 | $750 |
| W1.2.1.2.3 Long-Span Column Structure | | | | | | | $1,255 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R2 Designer and Technician |
| R2.5 Structural Engineer | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R3 Construction Technician |
| R3.3 Carperter | Day | 2 | 2 | 4 | 4 | $10 | $40 |
| R3.4 Laborer | Day | 4 | 3 | 12 | 12 | $10 | $120 |
| R3.5 Sheet-Metal Worker | Day | 3 | 2 | 6 | 6 | $10 | $60 |
| R3.7 Welding Technician | Day | 2 | 2 | 4 | 4 | $10 | $40 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 2 | 2 | 2 | $20 | $40 |
| R4.7 Concrete Mixer | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.10 Concrete Pump | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R5 Material |
| R5.1 Structural | Ton | 0.50 Tons | * | * | 0.5 | $300 | $150 |
| R5.3 Concrete | Bag | 10 Bags | * | * | 10 | $10 | $100 |
| R5.6 Reinforce Steel | Ton | 0.50 Ton | * | * | 0.5 | $300 | $150 |
| W1.2.1.3 Roof Floor | | | | | | | $5,925 |
| W1.2.1.3.1 I-Beam Steel Structure | | | | | | | $2,100 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 2 | 2 | 2 | $50 | $100 |
| R2 Designer and Technician |
| R2.5 Structural Engineer | Day | 1 | 2 | 2 | 2 | $50 | $100 |
| R3 Construction Technician |
| R3.3 Carperter | Day | 2 | 2 | 4 | 4 | $10 | $40 |
| R3.5 Sheet-Metal Worker | Day | 2 | 2 | 4 | 4 | $10 | $40 |
| R3.6 Laborer | Day | 3 | 2 | 6 | 6 | $10 | $60 |
| R3.7 Welding Technician | Day | 2 | 2 | 4 | 4 | $10 | $40 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 2 | 2 | 2 | $20 | $40 |
| R4.9 Crane | Day | 1 | 2 | 2 | 2 | $50 | $100 |
| R4.12 Tractor | Day | 1 | 2 | 2 | 2 | $25 | $50 |
| R5 Material |
| R5.3 Concrete | Bag | 3 Bags | * | * | 3 | $10 | $30 |
| R5.8 I-Beam Steel | Beam | 30 Beams | * | * | 30 | $50 | $1,500 |
| W1.2.1.3.2 Cement Insulation Tile | | | | | | | $2,545 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 1 | 1 | 1 | $50 | $50 |
| R2 Designer and Technician |
| R2.5 Structural Engineer | Day | 1 | 1 | 1 | 1 | $50 | $50 |
| R3 Construction Technician |
| R3.6 Laborer | Day | 3 | 1 | 3 | 3 | $10 | $30 |
| R3.7 Welding Technician | Day | 2 | 1 | 2 | 2 | $10 | $20 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 1 | 1 | 1 | 20 | $20 |
| R4.7 Concrete Mixer | Day | 1 | 1 | 1 | 1 | 25 | $25 |
| R4.9 Crane | Day | 1 | 1 | 1 | 1 | $25 | $25 |
| R5 Material |
| R5.1 Structural | Ton | 0.25 Ton | * | * | 0.25 | $300 | $75 |
| R5.11 Tile | Box | 75 Box | * | * | 75 | $30 | $2,250 |
| W1.2.1.3.3 Water Repellent Cement Floor | | | | | | | $1,280 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R2 Designer and Technician |
| R2.5 Structural Engineer | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R3 Construction Technician |
| R3.2 Plumber | Day | 2 | 2 | 4 | 4 | $15 | $60 |
| R3.3 Carpenter | Day | 2 | 2 | 4 | 4 | $10 | $40 |
| R3.6 Laborer | Day | 3 | 3 | 9 | 9 | $10 | $90 |
| R3.7 Welding Technician | Day | 2 | 2 | 4 | 4 | $10 | $40 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 2 | 2 | 2 | $20 | $40 |
| R4.7 Concrete Mixer | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.8 Power Float | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R4.10 Concrete Pump | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R5 Material |
| R5.1 Structural | Ton | 0.25 Tons | * | * | 0.25 | $300 | $75 |
| R5.3 Concrete | Bag | 5 Bags | * | * | 5 | $10 | $50 |
| R5.6 Reinforce Steel | Ton | 0.5 Ton | * | * | 0.5 | $300 | $150 |
| W1.2.2 Landscape Structure | | | | | | | $7,740 |
| W1.2.2.1 Swimming Pool Structure | | | | | | | $4,980 |
| R1 Supervisor |
| R1.2 Construction Manager | Day | 1 | 5 | 5 | 5 | $50 | $250 |
| R2 Designer and Technician |
| R2.4 Civil Engineer | Day | 1 | 5 | 5 | 5 | $60 | $300 |
| R2.5 Structural Engineer | Day | 1 | 5 | 5 | 5 | $50 | $250 |
| R2.6 Mechanical Engineer | Day | 1 | 5 | 5 | 5 | $50 | $250 |
| R3 Construction Technician |
| R3.3 Carperter | Day | 3 | 3 | 9 | 9 | $10 | $90 |
| R3.5 Sheet-Metal Worker | Day | 3 | 3 | 9 | 9 | $10 | $90 |
| R3.6 Laborer | Day | 5 | 5 | 25 | 25 | $10 | $250 |
| R3.7 Welding Technician | Day | 3 | 3 | 9 | 9 | $10 | $90 |
| R4 Equipment and Tools |
| R4.1 Survey Equipment | Day | 1 | 1 | 1 | 1 | $40 | $40 |
| R4.2 Dump Truck | Day | 1 | 3 | 3 | 3 | $20 | $60 |
| R4.3 Backhoe | Day | 1 | 2 | 2 | 2 | $50 | $100 |
| R4.4 Pile Driver | Day | 1 | 2 | 2 | 2 | $20 | $40 |
| R4.5 Trailer | Day | 1 | 5 | 5 | 5 | $25 | $125 |
| R4.6 Welding Machine | Day | 2 | 3 | 6 | 6 | $20 | $120 |
| R4.7 Concrete Mixer | Day | 1 | 5 | 5 | 5 | $25 | $125 |
| R4.10 Concrete Pump | Day | 1 | 5 | 5 | 5 | $60 | $300 |
| R4.11 Bucket Truck | Day | 1 | 5 | 5 | 5 | $25 | $125 |
| R4.12 Tractor | Day | 1 | 5 | 5 | 5 | $25 | $125 |
| R5 Material |
| R5.1 Structural | Ton | 1 Ton | * | * | 1 | $300 | $300 |
| R5.3 Concrete | Bag | 15 Bags | * | * | 15 | $10 | $150 |
| R5.6 Reinforce Steel | Ton | 1 Ton | * | * | 1 | $300 | $300 |
| R5.7 Pile | Pile | 30 Piles | * | * | 30 | $50 | $1,500 |
| W1.2.2.2 Road Structure | | | | | | | $2,760 |
| R2 Designer and Technician |
| R2.4 Civil Engineer | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R2.5 Structural Engineer | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R3 Construction Technician |
| R3.3 Carperter | Day | 2 | 2 | 4 | 4 | $10 | $40 |
| R3.5 Sheet-Metal Worker | Day | 2 | 3 | 6 | 6 | $10 | $60 |
| R3.6 Laborer | Day | 3 | 3 | 9 | 9 | $10 | $90 |
| R3.7 Welding Technician | Day | 2 | 3 | 6 | 6 | $10 | $60 |
| R4 Equipment and Tools |
| R4.1 Survey Equipment | Day | 1 | 1 | 1 | 1 | $40 | $40 |
| R4.2 Dump Truck | Day | 1 | 3 | 3 | 3 | $20 | $60 |
| R4.3 Backhoe | Day | 1 | 1 | 1 | 1 | $50 | $50 |
| R4.4 Pile Driver | Day | 1 | 2 | 2 | 2 | $20 | $40 |
| R4.5 Trailer | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.6 Welding Machine | Day | 1 | 3 | 3 | 3 | $20 | $60 |
| R4.7 Concrete Mixer | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.10 Concrete Pump | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R4.11 Bucket Truck | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.12 Tractor | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R5 Material |
| R5.1 Structural | Ton | 0.5 Ton | * | * | 0.5 | $300 | $150 |
| R5.3 Concrete | Bag | 15 Bags | * | * | 15 | $10 | $150 |
| R5.6 Reinforce Steel | Ton | 0.5 Ton | * | * | 0.5 | $300 | $150 |
| R5.7 Pile | Pile | 20 Piles | * | * | 20 | $50 | $1,000 |
| W1.3 Infrastructure Equipment | | | | | | | $6,190 |
| W1.3.1 Sub-Structure' Waste Water Recovering Tank | | | | | | | $1,930 |
| R2 Designer and Technician |
| R2.5 Structural Engineer | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R2.6 Mechanical Engineer | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R3 Construction Technician |
| R3.4 Sanitary Technician | Day | 2 | 3 | 6 | 6 | $15 | $90 |
| R3.6 Laborer | Day | 3 | 3 | 9 | 9 | $10 | $90 |
| R3.7 Welding Technician | Day | 1 | 3 | 3 | 3 | $10 | $30 |
| R4 Equipment and Tools |
| R4.1 Survey Equipment | Day | 1 | 1 | 1 | 1 | $40 | $40 |
| R4.2 Dump Truck | Day | 1 | 2 | 2 | 2 | $20 | $40 |
| R4.3 Backhoe | Day | 1 | 1 | 1 | 1 | $50 | $50 |
| R4.5 Trailer | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.6 Welding Machine | Day | 1 | 3 | 3 | 3 | $20 | $60 |
| R4.7 Concrete Mixer | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.10 Concrete Pump | Day | 1 | 3 | 3 | 3 | $60 | $180 |
| R4.11 Bucket Truck | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R4.12 Tractor | Day | 1 | 3 | 3 | 3 | $25 | $75 |
| R5 Material |
| R5.1 Structural | Ton | 0.25 Tons | * | * | 0.25 | $300 | $75 |
| R5.3 Concrete | Bag | 5 Bags | * | * | 5 | $10 | $50 |
| R5.7 Pile | Pile | 10 Piles | * | * | 10 | $50 | $500 |
| R5.9 Water Waste Recovering Tank | Tank | 1 Tank | * | * | 1 | $125 | $125 |
| W1.3.2 Central Air-Conditioning Machine System | | | | | | | $2,820 |
| R2 Designer and Technician |
| R2.6 Mechanical Engineer | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R2.7 Electrical Engineer | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R3 Construction Technician |
| R3.1 Electrician | Day | 2 | 3 | 6 | 6 | $15 | $90 |
| R3.6 Laborer | Day | 2 | 3 | 6 | 6 | $10 | $60 |
| R3.8 Mechanical Technician | Day | 2 | 3 | 6 | 6 | $15 | $90 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 3 | 3 | 3 | $20 | $60 |
| R4.9 Crane | Day | 1 | 3 | 3 | 3 | $50 | $150 |
| R5 Material |
| R5.2 Electrical |
| R5.2.1 Electrical Line | Loop | 20 Loops | * | * | 20 | 50 | $1,000 |
| R5.2.1 Electrical Electrical Control Box | Box | 2 Boxes | * | * | 2 | 250 | $500 |
| R5.5 Central Air-conditioning System | Machine | 1 Machine | * | * | 1 | $370 | $370 |
| R5.10 Ducts | Line | 10 Lines | * | * | 10 | $20 | $200 |
| W1.3.3 Plumbing System | | | | | | | $1,440 |
| R2 Designer and Technician |
| R2.8 Sanitary Engineer | Day | 1 | 4 | 4 | 4 | $50 | $200 |
| R3 Construction Technician |
| R3.2 Plumber | Day | 2 | 4 | 8 | 8 | $15 | $120 |
| R3.4 Sanitary Technician | Day | 2 | 4 | 8 | 8 | $15 | $120 |
| R3.6 Laborer | Day | 3 | 4 | 12 | 12 | $10 | $120 |
| R4 Equipment and Tools |
| R4.6 Welding Machine | Day | 1 | 4 | 4 | 4 | $20 | $80 |
| R4.9 Crane | Day | 1 | 4 | 4 | 4 | $50 | $200 |
| R5 Material |
| R5.10 Ducts | Line | 30 Lines | * | * | 30 | $20 | $600 |
| * This item use an exact amount of material, not depending on the duration. |
| ** One-time Payment of Tool has no effort. It will be calculate only one-time, which is in the Exterior design drawing. |
| N/A is one time payment tool |