PROJECT CHARTER
1. High-level project scope
The project's major goal is to change three existing traditional data centers by transferring applications to the cloud and satisfying the client's core demands. The project's goal is to develop an effective plan to transition legacy data centers to the cloud, both on-premise and in the cloud, by identifying a client's requirements and business needs, determining the cost, creating a schedule, conducting stakeholder analysis, developing a high-level communication plan, resource plan, and identifying project risks early and creating a plan.
2. High-level project requirements
The project's high-level requirements for upgrading three data centers:
· Within the $1.5 million budget, move 145 business applications and infrastructure to the cloud, including 450 windows servers, 550 Unix servers, and 350 legacy AIX, VMWare, and ESX servers.
· Determine the characteristics and capabilities of a data center in order to store more data without compromising security or privacy, avoid data loss, carry out business activities, and fulfill the primary demands and expectations of stakeholders.
· Using common tools, such as Microsoft project management, to define the project's core tasks and build a timetable.
· Using modern project financial management software to anticipate the cost and budget required to complete the project, conduct cost-benefit analysis, manage the budget, and achieve success.
· Using common tools such as the RACI matrix to analyze stakeholders, decide and plan resources, conduct activities, and execute projects according to the plan produced.
· Improving a data center's efficiency by storing data, providing faster access to resources and data, simplifying data center management, reducing expenses, and promoting production
3. Business needs
Manage a huge quantity of data connected to the business, minimize data loss, avoid security and privacy problems, access resources at any time, execute operations and deliver services to customers that match their expectations, and boost satisfaction in service offerings are among the business needs. It is also necessary to reduce efforts in handling data centers on which sensitive information related to the business is stored, reduce the cost of upgrading and managing data centers and provide higher-quality services by transforming data centers and shifting applications and infrastructure to the cloud.
4. Early estimation and forecasted cost
It is necessary to identify essential resources required to complete the project in order to estimate and anticipate project costs early on. The following is the project's estimated cost:
|
Project resource |
Cost estimation |
|
Purchasing data center infrastructure and systems |
$1,85,000 |
|
Setup of infrastructure |
$45,000 |
|
Hardware and software design |
$10,000 |
|
Development of applications |
$25000 |
|
Data center |
$1,00,000 |
|
Total cost |
$2,55,000 |
5. Stakeholders
The following are the important stakeholders linked with the project:
|
Role in the project |
Responsibility |
Interest |
|
Project manager |
Create a project plan by identifying requirements. |
High |
|
Software engineer |
Develop data center modules |
High |
|
Data center inspector |
Examine whether the data center was built to fulfill the demands of the company. |
High |
|
IT analyst |
Analyze the data center's functional and non-functional requirements. |
Medium |
|
Testing engineer |
Create test scenarios and put the data center to the test. |
Medium |
6. High-level communication plan
The project's high-level communication strategy focuses on enhancing engagement and information flow within it in order to connect with the team, convey changes, offer updates, and complete the project on time. It is then followed by:
|
Communication |
Frequency |
Audience |
Mode |
|
Stakeholder update |
Monthly |
Project stakeholders |
Newsletter |
|
Board meeting |
Weekly |
Board of directors for project |
Video conference |
|
Team meetings |
Daily |
Project team |
Meeting |
|
Discussing issues |
Daily |
Project team |
Email, newsletter and social medial communication |
7. High-level resource plan
The resources required to complete the project and fulfill the business's core needs are as follows:
|
Phase |
Task |
Resource |
|
Design |
Creating a detailed design for a data center. |
Project manager |
|
Analysis |
Functional and non-functional analysis for data center and reporting |
Data center and IT analyst and architect |
|
Build |
Build and test various data center modules such as login, administration, and reporting. |
Software developer |
|
Testing |
Creating a test matrix, writing test cases, and performing data center testing |
QA analyst |
8. Early risk indications
Early risk indications focuses on recognizing project-related risks early in order to establish their importance, impact on the organization, and generate management measures. The following are the early risk indicators for the project based on the demands and project requirements:
|
Risk type |
Priority |
|
Quality risk |
2 |
|
Scope risk |
2 |
|
Strategic risk |
2 |
|
Schedule risk |
1 |
|
Budget risk |
1 |