PROJECT CHARTER

1. High-level project scope

The project's major goal is to change three existing traditional data centers by transferring applications to the cloud and satisfying the client's core demands. The project's goal is to develop an effective plan to transition legacy data centers to the cloud, both on-premise and in the cloud, by identifying a client's requirements and business needs, determining the cost, creating a schedule, conducting stakeholder analysis, developing a high-level communication plan, resource plan, and identifying project risks early and creating a plan.

2. High-level project requirements

The project's high-level requirements for upgrading three data centers:

· Within the $1.5 million budget, move 145 business applications and infrastructure to the cloud, including 450 windows servers, 550 Unix servers, and 350 legacy AIX, VMWare, and ESX servers.

· Determine the characteristics and capabilities of a data center in order to store more data without compromising security or privacy, avoid data loss, carry out business activities, and fulfill the primary demands and expectations of stakeholders.

· Using common tools, such as Microsoft project management, to define the project's core tasks and build a timetable.

· Using modern project financial management software to anticipate the cost and budget required to complete the project, conduct cost-benefit analysis, manage the budget, and achieve success.

· Using common tools such as the RACI matrix to analyze stakeholders, decide and plan resources, conduct activities, and execute projects according to the plan produced.

· Improving a data center's efficiency by storing data, providing faster access to resources and data, simplifying data center management, reducing expenses, and promoting production

3. Business needs

Manage a huge quantity of data connected to the business, minimize data loss, avoid security and privacy problems, access resources at any time, execute operations and deliver services to customers that match their expectations, and boost satisfaction in service offerings are among the business needs. It is also necessary to reduce efforts in handling data centers on which sensitive information related to the business is stored, reduce the cost of upgrading and managing data centers and provide higher-quality services by transforming data centers and shifting applications and infrastructure to the cloud.

4. Early estimation and forecasted cost

It is necessary to identify essential resources required to complete the project in order to estimate and anticipate project costs early on. The following is the project's estimated cost:

Project resource

Cost estimation

Purchasing data center infrastructure and systems

$1,85,000

Setup of infrastructure

$45,000

Hardware and software design

$10,000

Development of applications

$25000

Data center

$1,00,000

Total cost

$2,55,000

5. Stakeholders

The following are the important stakeholders linked with the project:

Role in the project

Responsibility

Interest

Project manager

Create a project plan by identifying requirements.

High

Software engineer

Develop data center modules

High

Data center inspector

Examine whether the data center was built to fulfill the demands of the company.

High

IT analyst

Analyze the data center's functional and non-functional requirements.

Medium

Testing engineer

Create test scenarios and put the data center to the test.

Medium

6. High-level communication plan

The project's high-level communication strategy focuses on enhancing engagement and information flow within it in order to connect with the team, convey changes, offer updates, and complete the project on time. It is then followed by:

Communication

Frequency

Audience

Mode

Stakeholder update

Monthly

Project stakeholders

Newsletter

Board meeting

Weekly

Board of directors for project

Video conference

Team meetings

Daily

Project team

Meeting

Discussing issues

Daily

Project team

Email, newsletter and social medial communication

7. High-level resource plan

The resources required to complete the project and fulfill the business's core needs are as follows:

Phase

Task

Resource

Design

Creating a detailed design for a data center.

Project manager

Analysis

Functional and non-functional analysis for data center and reporting

Data center and IT analyst and architect

Build

Build and test various data center modules such as login, administration, and reporting.

Software developer

Testing

Creating a test matrix, writing test cases, and performing data center testing

QA analyst

8. Early risk indications

Early risk indications focuses on recognizing project-related risks early in order to establish their importance, impact on the organization, and generate management measures. The following are the early risk indicators for the project based on the demands and project requirements:

Risk type

Priority

Quality risk

2

Scope risk

2

Strategic risk

2

Schedule risk

1

Budget risk

1