Earned Value

PV EV AC BAC CV SV CPI SPI EAC ETC
Comments From the PM's Diary Status Date Planned Value Earned Value Actual Cost Schedule Performance Cost Performance Budget at Completion Cost Variance Schedule Variance Cost Performance Index Schedule Performance Index Estimate at Completion Estimate to Complete
So excited to get started! 12-Jul $0 $0 $0 On Schedule On Budget $251,335 $0 $0 0.0 0.0 $0 $0
Wow, work went quicker than anticipated, finished 3 days early! 26-Jul $15,055 $21,260 $17,595 $251,335
Uh-Oh, new Customer Requirements, added 3 days! 2-Aug $27,580 $32,473 $33,875 $251,335
Uh-Oh (again), need 4 more days for Design Specs! 30-Aug $71,580 $68,720 $70,655 $251,335
Uh-Oh (sigh), it will take a little longer (1 week) for coding the extra requirements! 8-Nov $203,330 $186,170 $200,905 $251,335
Hey! Unit and System Tests went very well, finished 6 days early! 30-Nov $251,335 $251,335 $248,460 $251,335