Upload your Project Closure Report

chaitu9z00
Doc2.doc

Deliverable Acceptance

State Agency – Website Redesign and Consolidation

Project Manager: Joey Bishop

Project Number: PROJ004797

Task Manager (if applicable):

Acceptance/Rejection Date:

Contract Number: 14-PSC-88888

Review Due Date: March 10, 2014

Description of Deliverables

80 Hours Onsite Support for Development Cutover- The support of State Agency in the release and cutover to production is provided with an onsite Catapult result.

Criteria for acceptance: Resource supports the troubleshooting and fix resolutions required to keep site up and operational from a Monrovia Industries scope responsibility through February 21.

Methods used to assess quality:

Review of test plan and test scripts and test results.

Deliverable Acceptance

Accepted Rejected

Reason(s) for Rejection (Please be specific about what is missing or not working.)

Completed By:

Date: Customer:

Date: Project Manager:

Submitted by Tom Sheives, Project Manager

Date Submitted: March 10, 2014

OIT-EPPMO-PM-0012-Project Deliverables Acceptance Form V01.doc August 2012