Project Status Report
Please complete the timeline below by the assigned due date. The purpose of this assignment is to determine a timeline of activities necessary to perform during the implementation phase. This schedule will keep both you and your project team on track and will assist in weekly communication. Please copy and paste some of the introductory the information from your project proposal for consistency. You will utilize this timeline during the implementation of your project in DNP Project III. You may also utilize this form for providing updates during DNP Project III.
|
Introduction |
|
|
Project Site |
PVC Family Practice
|
|
Project Mentor |
Dr. Terrica Woods
|
|
Project Purpose |
To develop a cultural competence training program aimed at enabling the health care providers to gain the knowledge and techniques they can employ to provide quality health care services to African immigrants. |
|
Project Question |
In healthcare workers caring for African Immigrant groups (P), how can an effective cultural competence training program (I) compared to no training program (C) be developed to improve the resource allocation and referrals for African Immigrants (O) in less than 4 weeks (T).
|
|
Project Timeline |
|
|
The purpose of this timeline is to keep you and the project team on track during the implementation phase which will occur in DNP Project III. Intervention or project timeline should be clearly described. Time to carry out implementation, collect data, and evaluate the project should be clearly delineated. Please plan out the activities you will be performing each week during the implementation phase. Please set actual concrete dates for any training, interventions, data collection, and/or data analysis. |
|
|
Week 1 Dates: (Nov 10-16) |
10th- Administering Pretest Survey Questionnaire 11th – Educational Training Training on the purpose and the elements of the project Training the participants on how to use the African Immigrant Cultural Competence Toolkit Training participants on how to use the African Immigrant Resources Toolkit Training participants on how to use the Patient Data Collection Form and the Provider Data Collection Form 12th – Administering the Posttest Survey Questionnaire 15th - Extracting and analyzing data from the questionnaires. 16th- Conducting a remediation session for participants with a grade less than 80 on the posttest. |
|
Week 2 (Nov 17-23) |
17th- 20th - Providing continued support to the participants to ensure efficiency of the progress. 23rd- Collecting data from the Participants’ Provider Data Collection Form
|
|
Week 3 (Dec 1- 7) |
1- 4nd - Providing continued support to the participants to ensure efficiency of the progress. 7th- Collecting data from the Participants’ Provider Data Collection Form |
|
Week 4 (Dec 8-14) |
8th-11th- Providing continued support to the participants to ensure efficiency of the progress. 14th- Collecting data from the Participants’ Provider Data Collection Form |
|
Week 5 (Dec 15-21) |
15th- Data compilation 16-18th- Data analysis 19th- Documentation of findings 20th- Dissemination of findings and presentation |
|
|
|
|
|
|
|
Weekly Summary |
|
|
Clearly and succinctly summarizes project status and discussion includes any updates to the project timeline.
DO NOT COMPLETE THIS NOW- SAVE THIS FOR DNP PROJECT III |
|
|
Week 1 |
Click or tap here to enter text.
|
|
Week 2 |
Click or tap here to enter text.
|
|
Week 3 |
Click or tap here to enter text.
|
|
Week 4 |
Click or tap here to enter text.
|
|
Week 5 |
Click or tap here to enter text.
|