Communication Plan and Project Schedule

Dynisha Beamon

Strayer University

Professor: Peter Freeman

BUS375

May 22, 2022

Communication between Team Members and Stakeholders

Indian Census Communication Plan

The following communication plan will be conducted and follow the project duration period to facilitate reliable dissemination and communication of information between the entity's team members and the stakeholders. The organization understands that communication is a vital aspect of the company's success in its projects. The first phase of communication will be based on email distribution. The purpose of the communication via email platform will be to inform both the team members and the stakeholders about the primary goals and objectives of the project. The first phase of information will inform the stakeholders on the forward motion regarding how the Indian census will be conducted and getting the investigator employees on board.

               The second phase will comprise communication from dealer project team members to the project management. Here, the project manager will assess the numbers behind the potential deal of conducting the Indian Census effectively. The department will also share the overview and updates on the project status with the organization's stakeholders. Phase three will involve the organization's HR department and project management. The human resource department will coordinate the individuals will send to the field to conduct census activities and operations. The department will also report the field progress to the organizational management for further directives.

               The Indian Census project will have numerous stakeholders, including mathematicians, data analysts, research scientists, and software engineers. The role of mathematicians will be to formulate mathematics models and equations for estimating the Indian population. On the other hand, data analysts will play the role of analyzing the collected data from surveillance. Also, they will check the prediction algorithms that will be utilized in the application of android. The research scientists will play the role of working on additional tasks outside the three stakeholders' scope. Besides, the software engineers will play the role of coding and programming application programs to obtain the required findings.

Project Schedule for the Project

Indian Census Schedule Plan

           The project will take approximately two months to complete. The project's primary focus is to evaluate the viability of a non-intrusive census, develop the best mathematical model convenient for computing India's population size, and predict the possible trends in the Indian population. The project's primary stakeholders will include mathematicians, research scientists, data analysts, and software engineers as the key stakeholder in my project. The project's current status is 20 percent, and by 15th July 2022, the project is expected to have been completed.

PROJECT NAME

Indian Census

PROJECT MANAGER

PROJECT DELIVERABLE

Age, occupation and Gender

SCOPE STATEMENT

The scope of the project is to create a project plan on the plausible non-intrusive ways of

conducting census in India

START DATE

20/05/2022

END DATE

15/07/2022

OVERALL PROGRESS

20%

AT RISK

TASK NAME

ASSIGNED TO

START DATE

END DATE

DURATION in days

STATUS

1

Project Charter

Project Manager

20/05

28/05

8

2

Project Research

Research & Development Manager

29/05

12/06

14

3

Project Projections

Human Resource Management

13/06

14/06

2

4

Stakeholders

Project Manager

15/06

29/06

14

5

Budgeting

Accounting Manager

30/06

02/07

3

6

Risk Management

Project Manager and Sponsors

03/07

08/07

5

7

Status and Tracking

Human Resource Management

09/07

14/07

5

5