Create a Gantt chart for the project. Requirements: You must have 20 entries.

dmjanuzzi14
CopyofGanttChartitemization.xlsx

Sheet1

Task Resource ID $/hour est. duration of task % completed milestones Deadline Start After
Establish Costs, High & Low Rob 20 6 hrs 0 Product price index 11/17 immediately
Cash Flow Statement Rob 20 3 hrs 0 11/17 immediately
Learn Portal Dawn-Marie 20 3 hours 0 complete navigation exam after 4 weeks 11/20 immediately
Area Availablity Study Dawn-Marie 20 20 hrs metrics on pbc 11/17 immediately
Display ad for November issue Dawn-Marie 20 2 hrs 100 11/10 immediately
Display ad for December Dawn-Marie 20 2 hrs 0 12/5 immediately
Column for December issue Dawn-Marie 20 2 hours 75 column to editing 12/5 immediately
Layout for December New dog feature Pamela 40 2 hrs 0 set typeface, submit page for approval, 11/20, 11/27 immediately
Editing of Article Editor 20 2 days 0 one week after 6
Project Charter Projection Agenda Jerry 40 2 weeks 0 scope statement after 6
Project Charter Constraints Agenda Jerry 40 3 weeks 0 risk analysis after 6
Venture Capital Search jerry 40 6 weeks 0 top 3 resources must complete #10 first then start
Establish VC Contract Jerry 40 2 weeks 0
Establish Franchisor Contract Rob 20 1 week 0 after 14
E & O and Insurances Dawn-Marie 20 2 weeks 0 policy after # 7
Pet Insurance Dawn-Marie 20 1 week 0 policy after # 7
Itemize Market Research for franchises Rob 20 1 week 0 after # 7
Identify risks of #14 Rob 20 0 after 15
Create WBS Dawn-Marie 20 4 weeks 0 after 15
Resource Leveling Jerry 2 weeks after 14