Running head:  SIMPLIFIED PROJECT PLAN 1

SIMPLIFIED PROJECT PLAN 2

Simplified Project Plan

Name

Institution

The project to be implemented involves the development of Bank Management Software and entails the use of the waterfall model. Selecting a methodology is essential since it gives a framework of the overall process and associated project documents as well as the deliverables that will control the project development cycle from start to close. The waterfall model ensures that the development phases flow seamlessly and is subdivided into separate sequential stages where the result of the preceding phase becomes the input of the succeeding phase.

In the waterfall model, the development team moves through the stages of development. The phases include; Analysis, Requirements Specification, Design, Coding, and Implementation, Testing and integration. The sequence flow from one phase to another in a top to bottom fashion. Theoretically, all the requirements are initially specified as well as the scope of the project. The app is designed according to the requirements where it is implemented and tested devoid of any modifications. The final product is then delivered to the customer.

Development phases for the project include:

· Requirements gathering and elicitation where the system requirement objectives are met. The user requirements for the system will entail Financial / Management Accounting, Treasury and Risk Management as well as Bank Communication Management.

· The system design phase will enable proper determination of the hardware and software requirements that describes the entire system architecture.

· The Implementation phase involves the development of application modules which are tested separately to establish their functionality.

· The Integration and Testing phase will entail the integration of the individual modules into a single system which is then tested as a single system. Also, user acceptance testing is done at this phase

· System implementation phase. This phase follows the successful integration and testing phase where it is deployed.

· The maintenance phase occurs after the system is implemented to correct or add new modules to meet customer’s changing needs or scope creep.

Simplified project plan for a Bank Management Software

Task Mode

Task Name

Duration

Start

Finish

Predecessors

Auto Scheduled

Bank Management Software Development

23 days

Wed 5/2/18

Fri 6/1/18

Auto Scheduled

Application conception and initiation

2 days

Wed 5/2/18

Thu 5/3/18

Auto Scheduled

Project plan

2 days

Wed 5/2/18

Thu 5/3/18

Auto Scheduled

Requirement analysis and specification

3 days

Fri 5/4/18

Tue 5/8/18

Auto Scheduled

Develop Financial / Management Accounting requirements

1 day

Fri 5/4/18

Fri 5/4/18

3

Auto Scheduled

Supply Chain Management

1 day

Mon 5/7/18

Mon 5/7/18

5

Auto Scheduled

Treasury Applications

1 day

Mon 5/7/18

Mon 5/7/18

5

Auto Scheduled

Treasury and Risk Management

1 day

Mon 5/7/18

Mon 5/7/18

5

Auto Scheduled

Bank Communication Management

1 day

Mon 5/7/18

Mon 5/7/18

5

Auto Scheduled

Finalize Requirement specification draft

2 days

Mon 5/7/18

Tue 5/8/18

5

Auto Scheduled

Design

7 days

Wed 5/9/18

Thu 5/17/18

Auto Scheduled

Design specification

4 days

Wed 5/9/18

Mon 5/14/18

10

Auto Scheduled

Configuration management

3 days

Tue 5/15/18

Thu 5/17/18

12

Auto Scheduled

Coding and implementation

7 days

Tue 5/15/18

Wed 5/23/18

Auto Scheduled

operational source code and unit test

7 days

Tue 5/15/18

Wed 5/23/18

12

Auto Scheduled

Integration and testing

4 days

Thu 5/24/18

Tue 5/29/18

Auto Scheduled

Validate startup on deployed hardware

2 days

Thu 5/24/18

Fri 5/25/18

15

Auto Scheduled

Perform OS, and application testing

2 days

Mon 5/28/18

Tue 5/29/18

17

Auto Scheduled

Deployment of System

3 days

Mon 5/28/18

Wed 5/30/18

Auto Scheduled

Configure and deploy production hardware

2 days

Mon 5/28/18

Tue 5/29/18

13,17

Auto Scheduled

Load software to deployed hardware

1 day

Wed 5/30/18

Wed 5/30/18

20,18

Auto Scheduled

Maintenance

3 days

Wed 5/30/18

Fri 6/1/18

Auto Scheduled

Obtain updates regarding key deliverables from the project team

2 days

Wed 5/30/18

Thu 5/31/18

18

Auto Scheduled

Hold formal customer review after, project plan approval and pilot testing

1 day

Fri 6/1/18

Fri 6/1/18

18,23

References