Executing The Project

venkatesh2512
Chapter8.CostEstimationandBudgeting.pptx

Project Management: Achieving Competitive Advantage

Fifth Edition

Chapter 8

Cost Estimation and Budgeting

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

If this PowerPoint presentation contains mathematical equations, you may need to check that your computer has the following installed:

1) MathType Plugin

2) Math Player (free versions available)

3) NVDA Reader (free versions available)

1

Learning Objectives

8.1 Understand the various types of common project costs and key differences between them.

8.2 Apply common forms of cost estimation for project work, including ballpark estimates, definitive estimates, parametric estimates, and learning curve.

8.3 Apply top-down, bottom-up, activity-based, and time-phased budgeting procedures for cost management.

8.4 Recognize the appropriateness of applying contingency funds for cost estimation.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

P M B o K Core Concepts

Project Management Body of Knowledge (P M B o K) covered in this chapter includes:

Plan Cost Management (P M B o K 7.1)

Estimate Costs (P M B o K 7.2)

Determine Budget (P M B o K 7.3)

Control Costs (P M B o K 7.4)

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Cost Management

Cost management has been defined to encompass data collection, cost accounting, and cost control.

Cost accounting and cost control serve as the chief mechanisms for identifying and maintaining control over project costs.

Cost estimation processes create a reasonable budget baseline for the project.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Common Sources of Project Cost

Labor

Materials

Subcontractors

Equipment and facilities

Travel

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Types of Costs

Direct Versus Indirect

Recurring Versus Nonrecurring

Fixed Versus Variable

Normal Versus Expedited

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 8.2 Project Price Breakdown

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.2 Cost Classifications

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Cost Estimation

Ballpark (order of magnitude)

Comparative

Feasibility

Definitive

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Learning Curves

Each doubling of output results in a reduction in time to perform the last iteration.

Where :

Yx = the time required for the x unit of output

a = the time required for the initial unit of output

X = the number of units to be produced

b = learning curve slope

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 8.6 Unit Learning Curve Log-Linear Model

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Software Project Estimation—Function Points

Function Point Analysis is a system for estimating the size of software projects based on what the software does.

Function Points are a standard unit of measure that represents the functional size of a software application.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 8.7 Software Project Development Activities as a Function of Size

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.4 Complexity Weighting Table for Function Point Analysis

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.5 Function Point Calculations for Restaurant Reorder System

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Problems with Cost Estimation

Low initial estimates

Unexpected technical difficulties

Lack of definition

Specification changes

External factors

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Creating a Project Budget

The budget is a plan that identifies the resources, goals, and schedule that allows a firm to achieve those goals.

Figure 8.8 The Relationship Among W B S, Scheduling, and Budgeting

Top-down

Bottom-up

Activity-based costing (A B C)

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Activity-Based Costing

Projects use activities and activities use resources.

Assign costs to activities that use resources.

Identify cost drivers associated with this activity.

Compute a cost rate per cost driver unit or transaction.

Multiply the cost driver rate times the volume of cost

driver units used by the project.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.6 Sample Project Budget

Activity Direct Costs Budget Overhead Total Cost
Survey 3,500 500 4,000
Design 7,000 1,000 8,000
Clear Site 3,500 500 4,000
Foundation 6,750 750 7,500
Framing 8,000 2,000 10,000
Plumb and Wire 3,750 1,250 5,000

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.7 Sample Budget Tracking Planned and Actual Activity Costs

Activity Direct Costs Budget Overhead Total Cost
Survey 4,000 4,250 250
Design 8,000 8,000 - 0 -
Clear Site 4,000 3,500 (500)
Foundation 7,500 8,500 1,000
Framing 10,000 11,250 1,250
Plumb and Wire 5,000 5,150 150
Total 38,500 40,650 2,150

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Table 8.8 Example of a Time-Phased Budget

Activity January February Months March April May Total by Activity
Survey 4,000 Blank Blank Blank Blank 4,000
Design Blank 5,000 3,000 Blank Blank 8,000
Clear Site Blank 4,000 Blank Blank Blank 4,000
Foundation Blank Blank 7,500 Blank Blank 7,500
Framing Blank Blank Blank 8,000 2,000 10,000
Plumb and Wire Blank Blank Blank 1,000 4,000 5,000
Monthly Planned 4,000 9,000 10,500 9,000 6,000 Blank
Cumulative 4,000 13,000 23,500 32,500 38,500 38,500

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Figure 8.9 Cumulative Budgeted Cost of the Project

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Budget Contingencies

The allocation of extra funds to cover uncertainties and improve the chance of finishing on time.

Contingencies are needed because:

Project scope may change

Murphy’s Law is present

Cost estimation must anticipate interaction costs

Normal conditions are rarely encountered

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Benefits to Contingency Funding

Recognizes future contains unknowns

Adds provision for company plans for an increase in project cost

Applies contingency fund as an early warning signal to a potential overdrawn budget

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Summary

Understand the various types of common project costs and key differences between them.

Apply common forms of cost estimation for project work, including ballpark estimates, definitive estimates, parametric estimates, and learning curve.

Apply top-down, bottom-up, activity-based, and time-phased budgeting procedures for cost management.

Recognize the appropriateness of applying contingency funds for cost estimation.

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

Copyright

Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved

±

30%

±

15%

±

10%

±

5%

=

b

x

YaX

(

)

= log learning %log(2)