Executing The Project
Project Management: Achieving Competitive Advantage
Fifth Edition
Chapter 8
Cost Estimation and Budgeting
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
If this PowerPoint presentation contains mathematical equations, you may need to check that your computer has the following installed:
1) MathType Plugin
2) Math Player (free versions available)
3) NVDA Reader (free versions available)
1
Learning Objectives
8.1 Understand the various types of common project costs and key differences between them.
8.2 Apply common forms of cost estimation for project work, including ballpark estimates, definitive estimates, parametric estimates, and learning curve.
8.3 Apply top-down, bottom-up, activity-based, and time-phased budgeting procedures for cost management.
8.4 Recognize the appropriateness of applying contingency funds for cost estimation.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
P M B o K Core Concepts
Project Management Body of Knowledge (P M B o K) covered in this chapter includes:
Plan Cost Management (P M B o K 7.1)
Estimate Costs (P M B o K 7.2)
Determine Budget (P M B o K 7.3)
Control Costs (P M B o K 7.4)
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Cost Management
Cost management has been defined to encompass data collection, cost accounting, and cost control.
Cost accounting and cost control serve as the chief mechanisms for identifying and maintaining control over project costs.
Cost estimation processes create a reasonable budget baseline for the project.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Common Sources of Project Cost
Labor
Materials
Subcontractors
Equipment and facilities
Travel
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Types of Costs
Direct Versus Indirect
Recurring Versus Nonrecurring
Fixed Versus Variable
Normal Versus Expedited
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 8.2 Project Price Breakdown
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Table 8.2 Cost Classifications
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Cost Estimation
Ballpark (order of magnitude)
Comparative
Feasibility
Definitive
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Learning Curves
Each doubling of output results in a reduction in time to perform the last iteration.
Where :
Yx = the time required for the x unit of output
a = the time required for the initial unit of output
X = the number of units to be produced
b = learning curve slope
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 8.6 Unit Learning Curve Log-Linear Model
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Software Project Estimation—Function Points
Function Point Analysis is a system for estimating the size of software projects based on what the software does.
Function Points are a standard unit of measure that represents the functional size of a software application.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 8.7 Software Project Development Activities as a Function of Size
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Table 8.4 Complexity Weighting Table for Function Point Analysis
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Table 8.5 Function Point Calculations for Restaurant Reorder System
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Problems with Cost Estimation
Low initial estimates
Unexpected technical difficulties
Lack of definition
Specification changes
External factors
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Creating a Project Budget
The budget is a plan that identifies the resources, goals, and schedule that allows a firm to achieve those goals.
Figure 8.8 The Relationship Among W B S, Scheduling, and Budgeting
Top-down
Bottom-up
Activity-based costing (A B C)
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Activity-Based Costing
Projects use activities and activities use resources.
Assign costs to activities that use resources.
Identify cost drivers associated with this activity.
Compute a cost rate per cost driver unit or transaction.
Multiply the cost driver rate times the volume of cost
driver units used by the project.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Table 8.6 Sample Project Budget
| Activity | Direct Costs | Budget Overhead | Total Cost |
| Survey | 3,500 | 500 | 4,000 |
| Design | 7,000 | 1,000 | 8,000 |
| Clear Site | 3,500 | 500 | 4,000 |
| Foundation | 6,750 | 750 | 7,500 |
| Framing | 8,000 | 2,000 | 10,000 |
| Plumb and Wire | 3,750 | 1,250 | 5,000 |
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Table 8.7 Sample Budget Tracking Planned and Actual Activity Costs
| Activity | Direct Costs | Budget Overhead | Total Cost |
| Survey | 4,000 | 4,250 | 250 |
| Design | 8,000 | 8,000 | - 0 - |
| Clear Site | 4,000 | 3,500 | (500) |
| Foundation | 7,500 | 8,500 | 1,000 |
| Framing | 10,000 | 11,250 | 1,250 |
| Plumb and Wire | 5,000 | 5,150 | 150 |
| Total | 38,500 | 40,650 | 2,150 |
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Table 8.8 Example of a Time-Phased Budget
| Activity | January | February | Months March | April | May | Total by Activity |
| Survey | 4,000 | Blank | Blank | Blank | Blank | 4,000 |
| Design | Blank | 5,000 | 3,000 | Blank | Blank | 8,000 |
| Clear Site | Blank | 4,000 | Blank | Blank | Blank | 4,000 |
| Foundation | Blank | Blank | 7,500 | Blank | Blank | 7,500 |
| Framing | Blank | Blank | Blank | 8,000 | 2,000 | 10,000 |
| Plumb and Wire | Blank | Blank | Blank | 1,000 | 4,000 | 5,000 |
| Monthly Planned | 4,000 | 9,000 | 10,500 | 9,000 | 6,000 | Blank |
| Cumulative | 4,000 | 13,000 | 23,500 | 32,500 | 38,500 | 38,500 |
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Figure 8.9 Cumulative Budgeted Cost of the Project
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Budget Contingencies
The allocation of extra funds to cover uncertainties and improve the chance of finishing on time.
Contingencies are needed because:
Project scope may change
Murphy’s Law is present
Cost estimation must anticipate interaction costs
Normal conditions are rarely encountered
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Benefits to Contingency Funding
Recognizes future contains unknowns
Adds provision for company plans for an increase in project cost
Applies contingency fund as an early warning signal to a potential overdrawn budget
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Summary
Understand the various types of common project costs and key differences between them.
Apply common forms of cost estimation for project work, including ballpark estimates, definitive estimates, parametric estimates, and learning curve.
Apply top-down, bottom-up, activity-based, and time-phased budgeting procedures for cost management.
Recognize the appropriateness of applying contingency funds for cost estimation.
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
Copyright
Copyright © 2019, 2016, 2013 Pearson Education, Inc. All Rights Reserved
±
30%
±
15%
±
10%
±
5%
=
b
x
YaX
(
)
= log learning %log(2)