Chapter 3: A Case Study
This case study provides an example of what’s involved in initiating, planning, executing, controlling, and closing an IT project
Note: This case study provides a big picture view of
managing a project
Case Study: JWD Consulting's Project Management Intranet Site
It is good practice to lay the groundwork for a project before it officially starts
Senior managers often perform several pre-initiation tasks, including the following:
Determine the scope, time, and cost constraints for the project
Identify the project sponsor
Select the project manager
Develop a business case for a project
Meet with the project manager to review the process and expectations for managing the project
Determine if the project should be divided into two or more smaller projects
Project Pre-initiation
Business Case
Business Case (contd)
Business Case (contd)
Initiating a project includes recognizing and starting a new project or project phase
The main goal is to formally select and start off projects
Project Initiation
Stakeholder Register
Stakeholder Management Strategy
Contents are often sensitive, so do not publish this document.
Project Charter
A project does not exist until the charter is created. When the charter exists, the project begins.
The charter contains a high level description of the project and its objectives, and maybe an overview of the business case.
The most important aspect of the charter is that it grants to the project manager the authority to spend money and use the organization's resources to accomplish project activities.
Usually the project manager, senior managers, sponsors, and clients all sign the project charter.
A project charter is not used to manage changes that occur during a project. If large-scale project changes make the charter obsolete or outdated, a new charter should be issued. If a project manager feels the urge to update the charter, this is a sign that the current project is obsolete—a new project is required, not a modification of the existing one.
Project Charters
Project Charters
It’s good practice to hold a kick-off meeting at the beginning of a project so that stakeholders can meet each other, review the goals of the project, and discuss future plans
Kick-off Meetings
Kick-off Meeting Agenda
The main purpose of project planning is to guide execution
Plan must be realistic and useful
Every knowledge area includes planning information
Key outputs included in the JWD project include:
A team contract
A project scope statement
A work breakdown structure (WBS)
A project schedule, in the form of a Gantt chart with all dependencies and resources entered
A list of prioritized risks (part of a risk register)
Project Planning
Team Conduct
JWD Consulting Intranet Site Project Baseline Gantt Chart
List of Prioritized Risks
Usually takes the most time and resources to perform project execution
Project managers must use their leadership skills to handle the many challenges that occur during project execution
A milestone report can help focus on completing major milestones
Project Executing
Project Executing
Part of Milestone Report
Involves measuring progress toward project objectives, monitoring deviation from the plan, and taking correction actions
Affects all other process groups and occurs during all phases of the project life cycle
Outputs include performance reports, change requests, and updates to various plans
Project Monitoring and Controlling
Project Monitoring and Controlling
Involves gaining stakeholder and customer acceptance of the final products and services
Even if projects are not completed, they should be closed out to learn from the past
Outputs include project archives and lessons learned, part of organizational process assets
Most projects also include a final report and presentation to the sponsor/senior management
Project Closing
Project Closing
Lessons Learned