Activity-Based Costing and Analysis

Chapter 17

Wild and Shaw

Financial & Managerial Accounting

8th Edition

Copyright ©2019 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

2 - ‹#›

1

Chapter 17 Learning Objectives

CONCEPTUAL

C1 Distinguish between the plantwide overhead rate method, the departmental overhead rate method, and the activity-based costing method.

C2 Explain cost flows for activity-based costing.

C3 Describe the four types of activities that cause overhead costs.

ANALYTICAL

A1 Identify and assess advantages and disadvantages of the plantwide overhead and departmental overhead rate methods.

A2 Identify and assess advantages and disadvantages of activity-based costing.

PROCEDURAL

P1 Allocate overhead costs to products using the plantwide overhead rate method.

P2 Allocate overhead costs to products using the departmental overhead rate method.

P3 Allocate overhead costs to products using activity-based costing.

© McGraw-Hill Education 

2 - ‹#›

Distinguish between the plantwide overhead rate method, the departmental overhead rate method, and the activity-based costing method.

Learning Objective C1

© McGraw-Hill Education 

2 - ‹#›

Assigning Overhead Costs (1 of 2)

Goods in Process

Cost of Goods Sold

Labor

Materials

Indirect

Indirect

Finished Goods

Factory Overhead

Direct

Direct

Allocate

4

Learning Objective C1: Distinguish between the plantwide overhead rate method, the departmental overhead rate method, and the activity-based costing method.

© McGraw-Hill Education 

2 - ‹#›

4

Product cost consists of direct materials, direct labor, and overhead (indirect costs). Because direct materials and direct labor can be traced to units of output, assigning these costs to products is straightforward.

Overhead costs, however, are not directly related to production and cannot be traced to units of product like direct materials and direct labor can. We must use an allocation system to assign overhead costs.

Assigning Overhead Costs (2 of 2)

Overhead can be assigned to production in one of three ways:

Single plant-wide overhead rate

Departmental overhead rates

Activity-based costing

5

Learning Objective C1: Distinguish between the plantwide overhead rate method, the departmental overhead rate method, and the activity-based costing method.

© McGraw-Hill Education 

2 - ‹#›

5

There are three methods of overhead allocation: the single plantwide overhead rate method; the departmental overhead rate method; and the activity-based costing method.

Alternative Methods of Overhead Allocation

6

Exhibit 17.1

© McGraw-Hill Education 

Learning Objective C1: Distinguish between the plantwide overhead rate method, the departmental overhead rate method, and the activity-based costing method.

2 - ‹#›

The plantwide overhead rate method and the departmental overhead rate method use volume-based measures such as direct labor hours or machine hours to allocate overhead costs to products. The plantwide method uses a single rate and the departmental rate uses at least two rates.

Activity-based costing focuses on activities and their costs. Rates based on these activities are used to assign overhead to products in proportion to the amount of activity required to produce them. Activity-based costing typically uses more overhead allocation rates than the plantwide and departmental methods.

6

Allocate overhead costs to products using the plantwide overhead rate method.

Learning Objective P1

© McGraw-Hill Education 

7

2 - ‹#›

Plantwide Overhead Rate Method

8

Learning Objective P1: Allocate overhead costs to products using the plantwide overhead rate method.

Exhibit 17.2

© McGraw-Hill Education 

2 - ‹#›

8

For this method, the target of the cost assignment, or cost object, is the unit of product. The overhead rate is determined using a volume-related measure such as direct labor hours or machine hours, which are readily available in most manufacturing settings.

Under the single plantwide overhead rate method, total budgeted overhead costs are divided by the chosen allocation base, such as total direct labor hours, to arrive at a single plantwide overhead rate. This rate then is applied to assign overhead costs to all products based on their actual usage of the allocation base.

Let’s look at the Exhibit 17.3 and Exhibit 17.4 as an example.

Plantwide Overhead Rate Method Illustration (1 of 4)

9

Exhibit 17.3

Learning Objective P1: Allocate overhead costs to products using the plantwide overhead rate method.

Exhibit 17.4

© McGraw-Hill Education 

2 - ‹#›

9

Let’s look at an example. KartCo. manufactures two models of go-karts, standard and custom. They use a plantwide rate and use direct labor hours as the allocation base To calculate total direct labor hours, multiply the number of product units by direct labor hours per unit per product. Kartco’s budgeted overhead cost consists of indirect labor costs of $4,000,000 and factory utilities of $800,000 for a total of $4,800,000. This number will also be needed to calculate the plantwide overhead rate.

Plantwide Overhead Rate Method Illustration (2 of 4)

Plantwide overhead rate

=

Total budgeted overhead costs

Total budgeted DLH

10

Learning Objective P1: Allocate overhead costs to products using the plantwide overhead rate method.

© McGraw-Hill Education 

2 - ‹#›

10

Plantwide overhead rate is equal to total budgeted overhead cost divided by total budgeted direct labor hours.

Plantwide Overhead Rate Method Illustration (3 of 4)

Plantwide overhead rate

=

$4,800,000

100,000 DLH

=

$48/DLH

11

Overhead allocated to each unit produced =

$48 × DLH per unit

Learning Objective P1: Allocate overhead costs to products using the plantwide overhead rate method.

© McGraw-Hill Education 

2 - ‹#›

11

Dividing $4,800,000 by 100,000 hours gives us a plant overhead rate of $48 per DLH (direct labor hour). This plantwide overhead rate is then used to allocate overhead cost to products based on the number of direct labor hours required to produce each unit as follows.

Overhead allocated to each product unit = Plantwide overhead rate × DLH per unit.

Plantwide Overhead Rate Method Illustration (4 of 4)

12

Learning Objective P1: Allocate overhead costs to products using the plantwide overhead rate method.

© McGraw-Hill Education 

2 - ‹#›

12

Using the overhead rate of $48 per direct labor hour KartCo can determine the amount of factory overhead to allocate to each go-kart. They can then use this information to determine the total unit cost of each go-kart.

Allocate overhead costs to products using the departmental overhead rate method.

13

Learning Objective P2

© McGraw-Hill Education 

2 - ‹#›

Departmental Overhead Rate Method

14

Learning Objective P2: Allocate overhead costs to products using the departmental overhead rate method.

Exhibit 17.6

© McGraw-Hill Education 

2 - ‹#›

14

Exhibit 17.6 shows a four-step process for allocating costs under the departmental overhead rate method.

Assign overhead costs to departmental cost pools.

Select an allocation base for each department.

Compute overhead allocation rates for each department.

Use departmental overhead rates to assign overhead costs to cost objects (products).

The departmental overhead rate method uses several departments and several overhead rates. This allows each department to have its own overhead rate and its own allocation base.

Departmental Overhead Rate Method: First Step

Overhead Cost

$4,800,000

Machining Dept.

$4,200,000

Assembly Dept.

$600,000

15

Learning Objective P2: Allocate overhead costs to products using the departmental overhead rate method.

© McGraw-Hill Education 

2 - ‹#›

15

Let’s return to KartCo and calculate their departmental overhead rates. KartCo has two production departments, machining and assembly.

The first step requires that KartCo assign its $4,800,000 overhead cost to its two production departments. KartCo determines that $4,200,000 of its overhead costs are traceable to its machining department and the remaining $600,000 are traceable to its assembly department.

Departmental Overhead Rate Method: Second Step (1 of 2)

Product 1

Product 2

Product 3

16

Machining Dept.

Overhead Rate based on machine hours (MH)

Assembly Dept.

Overhead Rate based on direct labor hours (DLH)

Learning Objective P2: Allocate overhead costs to products using the departmental overhead rate method.

© McGraw-Hill Education 

2 - ‹#›

16

The second step requires each department to determine an allocation base. For KartCo, the Machining Department uses machine hours (MH) to allocate its overhead and the Assembly Department uses direct labor hours to allocate its overhead.

Departmental Overhead Rate Method: Second Step (2 of 2)

17

Learning Objective P2: Allocate overhead costs to products using the departmental overhead rate method.

© McGraw-Hill Education 

2 - ‹#›

17

Here is the budgeted departmental information about KartCo’s machining and assembly departments. They will be using machine hours as the allocation base in Machining, and direct labor hours in Assembly.

Departmental Overhead Rate Method: Third Step (1 of 2)

Departmental Overhead Rate

=

Total budgeted departmental overhead costs

Total amount of departmental allocation base

18

Learning Objective P2: Allocate overhead costs to products using the departmental overhead rate method.

© McGraw-Hill Education 

2 - ‹#›

18

In the third step, each department computes its own overhead rate using this formula:

Departmental overhead rate = Total budgeted departmental overhead costs / Total amount of departmental allocation base.

Departmental Overhead Rate Method: Third Step (2 of 2)

Machining Department Overhead Rate

=

$4,200,000

70,000 MH

=

$60/MH

Assembly Department Overhead Rate

=

$600,000

30,000 DLH

=

$20/DLH

19

Learning Objective P2: Allocate overhead costs to products using the departmental overhead rate method.

© McGraw-Hill Education 

2 - ‹#›

19

For KartCo, it’s departmental overhead rates are computed as follows:

Machining department overhead rate = $4,200,000 / 70,000 MH = $60 per MH

Assembly department overhead rate = $600,000 / 30,000 DLH = $20 per DLH

Departmental Overhead Rate Method: Fourth Step

20

Learning Objective P2: Allocate overhead costs to products using the departmental overhead rate method.

Exhibit 17.7

© McGraw-Hill Education 

Exhibit 17.8

2 - ‹#›

20

Step 4 applies overhead costs to each product using departmental overhead rates. Because each standard go-kart requires 10 MH from the Machining Department and 5 DLH from the Assembly Department, the overhead cost allocated to each standard go-kart is $600 from Machining Department (10 MH × $60/MH) and $100 from the Assembly Department (5 DLH × $20/DLH). The same procedure is applied for its custom go-kart. Next, we can compare the allocated overhead costs for standard and custom go-karts under the single plant wide overhead rate and the departmental overhead rate methods. The overhead cost allocated to each standard go-kart decreased from $720 under the plant wide overhead rate method to $700 under the departmental overhead rate method, whereas overhead cost allocated to each custom go-kart increased from $1,200 to $1,300. These differences occur because the custom go-kart requires more hours in the machining department (20 MH) than the standard go-kart requires (10 MH).

Identify and assess advantages and disadvantages of the plantwide overhead and departmental overhead rate methods.

21

Learning Objective A1

© McGraw-Hill Education 

2 - ‹#›

Plantwide Overhead Rate Method Advantages and Disadvantages

Advantages

Information is readily available

Easy to implement

Consistent with GAAP and can be used for external reporting

Disadvantages

With many different products, assumptions may not be reasonable.

Overhead costs may not bear a relationship with direct labor hours

All products may not use overhead costs in the same proportion

22

Learning Objective A1: Identify and assess advantages and disadvantages of the plantwide overhead and departmental overhead rate methods.

© McGraw-Hill Education 

2 - ‹#›

The usefulness of the single plantwide overhead rate depends on two assumptions: 1) overhead costs change with the allocation base such as direct labor hours; and 2) all products use overhead costs in the same proportions.

22

Departmental Overhead Rate Method Advantages and Disadvantages

Advantages

More accurate overhead allocations

More refined than the plantwide overhead rate method

Disadvantages

Assumes that products are similar in volume, complexity, batch size

Assumes that departmental overhead costs are proportional to the allocation base

Can distort product costs

23

Learning Objective A1: Identify and assess advantages and disadvantages of the plantwide overhead and departmental overhead rate methods.

© McGraw-Hill Education 

2 - ‹#›

23

The departmental overhead rate method assumes that 1) different products are similar in volume, complexity, and batch size, and 2) departmental overhead costs are directly proportional to the department allocation base such as direct labor hours or machine hours.

Explain cost flows for activity-based costing.

24

Learning Objective C2

© McGraw-Hill Education 

2 - ‹#›

Cost Flows Under Activity-Based Costing

25

Learning Objective C2: Explain cost flows for activity-based costing.

Exhibit 17.9

© McGraw-Hill Education 

2 - ‹#›

25

Activity-based costing (ABC) attempts to more accurately assign overhead costs by focusing on activities.

The basic principle underlying activity-based costing is that activities, which are tasks, operations, or procedures, are what cause costs to be incurred. An activity cost pool is a collection of costs that are related to the same or similar activity. Pooling costs to determine an activity overhead (pool) rate for all costs incurred by the same activity reduces the number of cost assignments required.

The four basic steps to the ABC method are:

Identify activities and the overhead costs they cause.

Trace overhead costs to cost pools.

Determine activity rates.

Use the activity overhead rates to assign overhead costs to cost objects (products).

Let’s take a closer look at the four basic steps of activity based costing.

Allocate overhead costs to products using activity-based costing.

26

Learning Objective P3

© McGraw-Hill Education 

2 - ‹#›

Applying Activity-Based Costing

4 STEPS:

Identify activities and the costs they cause.

Trace overhead costs to cost pools.

Determine activity rates.

Assign overhead costs to cost objects (products).

27

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

© McGraw-Hill Education 

2 - ‹#›

27

ABC differs from using multiple departmental rates in how overhead cost pools are identified and in how overhead cost in each pool is allocated.

This involves four steps:

1. Identify activities and the costs they cause.

2. Trace overhead costs to cost pools.

3. Determine activity rates.

4. Assign overhead costs to cost objects.

Step 1: Identify Activities and the Costs They Cause (1 of 2)

Machine setup

Machine repair

Factory

maintenance

Engineer

salaries

Assembly

line power

Heating and

lighting

28

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

© McGraw-Hill Education 

2 - ‹#›

Step 1 in applying ABC is to identify activities and the costs they cause. This is one of the biggest challenges. This is done mainly through discussions with employees in the production departments and reviewing production activities. However, tracking too many activities makes the system cumbersome and costly to maintain. The aim of this first step is to understand actions performed in the organization that drive costs.

Step 1: Identify Activities and the Costs They Cause (2 of 2)

29

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

Exhibit 17.10

© McGraw-Hill Education 

2 - ‹#›

29

Recall that a premise of ABC is that operations are a series of activities that cause costs to be incurred. Instead of combining costs from different activities into one plant wide pool or multiple departmental pools, ABC focuses on activities as the cost object in the first step of cost assignment. We are then able to trace costs to a cost object and then combine activities that are used by products in similar ways to reduce the number of cost allocations.

KartCo has total overhead cost of $4,800,000 consisting of $4,000,000 indirect labor costs and $800,000 factory utilities cost. After reviewing activities with production employees, KartCo identifies the activities and their costs as shown in Exhibit 17.10.

Step 2: Trace Overhead Costs to Activity Cost Pools (1 of 2)

Overhead Cost

Activity

Cost Pool (Craftsmanship)

Activity

Cost Pool (Setup)

Activity

Cost Pool (Design Modification)

30

Activity

Cost Pool (Plant Services)

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

© McGraw-Hill Education 

2 - ‹#›

30

Step 2 in applying ABC is to assign activities and their overhead costs to activity cost pools. KartCo management assigns its overhead costs into four activity cost pools: Craftsmanship, Setup, Design modification and Plant Services

Step 2: Trace Overhead Cost to Activity Cost Pools (2 of 2)

31

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

Exhibit 17.11

© McGraw-Hill Education 

2 - ‹#›

31

Exhibit 17.11 shows how KartCo’s management assigned its overhead costs into the four activity cost pools. To form cost pools we look for costs that are caused by the same activities within each activity level. For KartCo, there is only one activity driver within each activity pool, but that is not always the case. It is common to see several different activity drivers within each level of activity pool. We pool only those costs that are related to the same driver.

The exhibit above shows that $600,000 of its overhead costs are assigned to the craftsmanship activity pool, $2,000,000 to the set-up cost pool, $1,200,000 to the design modification cost pool, and $1,000,000 to the plant services cost pool. The use of cost pools reduces the potential number of overhead rates from six (one for each of its six activities) to four (one for each pool).

Step 3: Determine Activity Rates (1 of 4)

Step 3 is to compute the activity rates used to assign overhead costs to final cost objects such as products.

Activity Overhead

rate ?

Activity Overhead

Rate ?

Activity Overhead

rate ?

32

Activity

Cost Pool (Craftsmanship)

Activity

Cost Pool (Setup)

Activity

Cost Pool (Design Modification)

Activity

Cost Pool (Plant Services)

Activity Overhead

rate ?

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

© McGraw-Hill Education 

2 - ‹#›

32

Step 3 is to compute the activity overhead (cost pool) rates used to assign overhead costs to final cost objects such as products.

Step 3: Determine Activity Rates (2 of 4)

Proper identification of the factor that drives the cost

Proper measures of activities

Proper determination of activity rates depends on:

and

33

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

© McGraw-Hill Education 

2 - ‹#›

33

Proper determination of activity rates depends on:

Proper identification of the factor that drives the cost in each activity cost pool.

Proper measures of activities.

A cost driver is that activity causing the costs in the pool to be incurred. An activity driver is a measure of activity level and is determined for use as the allocation base.

Step 3: Determine Activity Rates (3 of 4)

For example:

Craftsmanship cost pool activity rate

= $600,000 / 30,000 DLH

= $20 per DLH

Cost Pool Activity Rate

=

Overhead costs assigned to pool

Expected activity level

34

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

© McGraw-Hill Education 

2 - ‹#›

In this step the activity rate is determined by dividing the overhead costs assigned to an activity pool by the expected activity level.

For example:

For KartCo, the activity rate for the craftsmanship cost pool is computed as:

Craftsmanship cost pool activity rate = $600,000 divided by 30,000 direct labor hours equals $20 per direct labor hour.

The activity rate computations for KartCo are summarized on the next slide.

34

Step 3: Determine Activity Rates (4 of 4)

35

=

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

Exhibit 17.12

© McGraw-Hill Education 

2 - ‹#›

Take a moment to review how the activity rates were calculated for each of the pools.

35

Step 4: Assign Overhead Costs to Cost Objects (1 of 4)

Step 4 is to assign overhead costs in each activity cost pool to final cost objects using activity rates.

Activity Overhead

rate

Activity Overhead

rate

Activity Overhead

rate

Product 1

Product 2

Product 3

36

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

© McGraw-Hill Education 

2 - ‹#›

36

Step 4 is to assign overhead costs in each activity cost pool to final cost objects using activity rates.

To do this, overhead costs are allocated to products based on the actual levels of activities used.

Step 4: Assign Overhead Costs to Cost Objects (2 of 4)

To illustrate, the overhead costs in the craftsmanship pool are allocated to standard go-karts as follows:

Overhead allocated from craftsmanship pool to standard go-kart =

Activities consumed × Activity rate

25,000 DLH × $20 per DLH = $500,000

37

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

© McGraw-Hill Education 

2 - ‹#›

37

To illustrate, the $500,000 of overhead costs in the craftsmanship pool is allocated to standard go-karts as follows:

Overhead allocated to standard go-kart = Activities consumed × Activity rate

=25,000 DLH × $20 =$500,000

Step 4: Assign Overhead Costs to Cost Objects (3 of 4)

38

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

© McGraw-Hill Education 

Exhibit 17.13

2 - ‹#›

38

Overhead costs allocated to Standard and Custom Go-karts under ABC for KartCo are summarized in Exhibit 17.13. This exhibit uses the activity rates from exhibit 17.12 to assign costs to Standard Go-karts and Custom Go-karts. Standard Go-karts used 25,000 direct labor hours and the activity rate for craftsmanship is $20 per direct labor hour. Multiplying the number of direct labor hours by the activity rate yields the craftsmanship costs assigned to Standard Go-karts. Custom Go-karts consumed 5,000 direct labor hours, so we assign $100,000 (5,000 DLH @ $20/DLH) to that product line. Similarly, we allocate overhead costs of setup, design modification, and plant services pools to each type of go-kart.

Step 4: Assign Overhead Costs to Cost Objects (4 of 4)

39

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

Exhibit 17.14

© McGraw-Hill Education 

2 - ‹#›

39

The unit overhead costs is computed by dividing total overhead cost allocated to each product by the number of product units. KartCo’s overhead cost per unit for it’s standard and custom go-karts is computed and shown in Exhibit 17.14.

Comparison of Overhead Allocations by Method

40

Learning Objective P3: Allocate overhead costs to products using activity-based costing.

Exhibit 17.15

© McGraw-Hill Education 

2 - ‹#›

40

Does the method of overhead allocation really make a difference? Overhead allocation to the standard go-karts is much less under ABC than under either of the volume-based costing methods. One reason for this difference is the large design modification costs that were spread over all go-karts under both the plantwide and departmental rate methods even though standard go-karts require no engineering modification.

Identify and assess advantages and disadvantages of activity-based costing.

41

Learning Objective A2

© McGraw-Hill Education 

2 - ‹#›

Activity-Based Costing Advantages and Disadvantages

Advantages:

More accurate overhead cost allocation

More effective overhead cost control

Better production /pricing decisions

Other Uses – ABC can be used to:

Allocate the S&A costs expensed by GAAP activities

Determine profitability of market segments

Costs of Quality

Disadvantages:

Costs to implement and maintain

Some product cost distortion remains

Uncertainty with decisions remains

42

Not acceptable under GAAP

Learning Objective A2: Identify and assess advantages and disadvantages of activity-based costing.

© McGraw-Hill Education 

2 - ‹#›

Take a minute to look over the advantages and disadvantages of activity based costing. As with all cost information, managers must be able to interpret the data and must use caution when making management decisions. Activity-based costing uses more cost pools and activity rates than other methods. This can increase overhead costing accuracy since the costs in each pool are caused by the same activity. it also has its limitations, and these must be weighed to determine the best approach for the company. It is also important to note that ABC is not acceptable under GAAP for external financial reporting.

42

Describe the four types of activities that cause overhead costs.

43

Learning Objective C3

© McGraw-Hill Education 

2 - ‹#›

Types of activities

Unit-level

Batch-level

Product-level

Facility-level

44

Learning Objective C3: Describe the four types of activities that cause overhead costs.

© McGraw-Hill Education 

2 - ‹#›

44

There are four types of activities that cause overhead costs. As mentioned earlier in this presentation, one of the biggest challenges is to identify the activities which cause the costs to occur.

Activities causing overhead cost in an organization are typically separated into four levels:

Unit-level activities

Batch-level activities

Product-level activities

Facility-level activities

Levels of Activities (1 of 4)

Unit-level activities are performed on each product unit; for example, providing electricity to power machinery in the machining department is needed to produce each unit of product.

Unit-level

45

Learning Objective C3: Describe the four types of activities that cause overhead costs.

© McGraw-Hill Education 

2 - ‹#›

45

Unit-level activities are those tasks that must be performed on each unit of product. For example, each unit may require that materials be cut, or components be assembled.

Levels of Activities (2 of 4)

Batch-level activities are performed only on each batch or group of units.

Batch-level

46

Learning Objective C3: Describe the four types of activities that cause overhead costs.

© McGraw-Hill Education 

2 - ‹#›

46

Batch-level activities are performed only on each batch or group of units; for example, machine setup is needed only for each batch regardless of the units in that batch, and customer order processing must be performed for each order regardless of the number of units ordered. Batch-level costs do not vary with the number of units, but instead with the number of batches.

Levels of Activities (3 of 4)

Product-level activities are performed on each product line and are not affected by either numbers of units or batches.

Product-level

47

Learning Objective C3: Describe the four types of activities that cause overhead costs.

© McGraw-Hill Education 

2 - ‹#›

47

Product-level activities are performed on each product line and are not affected by either numbers of units or batches; for example, product design is needed only for each product line. Product-level costs do not vary with the number of units or batches produced.

Levels of Activities (4 of 4)

Facility-level activities are performed to sustain facility capacity as a whole and are not caused by any specific product.

Facility-level

48

Learning Objective C3: Describe the four types of activities that cause overhead costs.

© McGraw-Hill Education 

2 - ‹#›

48

Facility-level activities are performed to sustain facility capacity as a whole and are not caused by any specific product; for example, factory maintenance costs are incurred to keep the plant clean and safe no matter what is being produced, and so is paying rent on a factory building. Facility-level costs do not vary with what is manufactured, how many batches are produced, or the output quantity.

Exhibit 17.16

Learning Objective C3: Describe the four types of activities that cause overhead costs.

© McGraw-Hill Education 

49

Examples of Activity Levels (1 of 2)

2 - ‹#›

Exhibit 17.16 shows additional examples of activities commonly found within each of the four activity levels. This list also includes common activity drivers.

49

Learning Objective C3: Describe the four types of activities that cause overhead costs.

© McGraw-Hill Education 

50

Examples of Activity Levels (2 of 2)

2 - ‹#›

50

Costs of Quality

Costs resulting from manufacturing defective products or providing services that do not meet customer expectations.

Cost of quality report lists costs of quality activities by category.

51

Learning Objective C3: Describe the four types of activities that cause overhead costs.

© McGraw-Hill Education 

Exhibit 17.17

2 - ‹#›

51

Costs resulting from manufacturing defective products or providing services that do not meet customer expectations.

Cost of quality report lists costs of quality activities by category.

Costs of Good and Poor Quality

Costs of Good Quality:

Prevention activities focus on quality training and improvement programs to ensure quality.

Appraisal activities include inspections to ensure materials meet specifications of finished goods.

Costs of Poor Quality:

Internal failure costs incurred after a defective product is manufactured but before product is delivered.

External failure costs incurred after customer has been provided a defective product/service.

52

Learning Objective C3: Describe the four types of activities that cause overhead costs.

© McGraw-Hill Education 

2 - ‹#›

52

Costs of Good Quality:

Prevention and appraisal costs are incurred before a good or service is provided to a customer. The purpose of these costs is to reduce the chance the customer is provided a defective good or service. These are the costs of trying to ensure that only good-quality items are produced.

Prevention activities focus on quality training and improvement programs to ensure quality is built into the product or service.

Appraisal activities include the costs of inspections to ensure that materials and supplies meet specifications and inspections of finished goods.

Costs of Poor Quality:

Internal and external failure costs are the costs of making poor-quality items.

Internal failure costs are incurred after a company has manufactured a defective product but before that product has been delivered to a customer. Internal failure costs include the costs of reworking products, reinspecting reworked products, and scrap.

External failure costs are incurred after a customer has been provided a defective product or service. Examples of this type of cost include costs of warranty repairs and costs of recalling products. This category also includes lost profits due to dissatisfied customers buying from other companies

Lean Operations

Lean Operations –common in lean manufacturing

Common features include:

Just-in-time (JIT) inventory systems to reduce costs of moving and storing inventory.

Cellular manufacturing - products made by teams of employees in small workstations called cells.

Building quality into products by focusing on costs of good quality.

Lean accounting - eliminates waste; uses alternative performance measures; and simplifies product costing.

© McGraw-Hill Education 

53

Learning Objective C3: Describe the four types of activities that cause overhead costs.

2 - ‹#›

Lean Operations – focusing on activities is common in lean manufacturing which strives to eliminate waste while satisfying customers. Common features include:

Just-in-time (JIT) inventory systems to reduce costs of moving and storing inventory.

Cellular manufacturing where products are made by teams of employees in small workstations called cells.

Building quality into products by focusing on costs of good quality.

Lean accounting includes eliminating waste; alternative performance measures; and simplified product costing.

53

ABC for Service Providers

ABC also applies to service providers.

Service companies must classify costs by activity levels of unit, batch, service, and facility.

54

Learning Objective C3: Describe the four types of activities that cause overhead costs.

© McGraw-Hill Education 

Exhibit 17.18

2 - ‹#›

54

ABC also applies to service providers.

Service companies must classify costs by activity levels of unit, batch, service, and facility.

Customer Profitability

Companies should assess the profitability of their customers.

Can create a customer profitability report to determine the profitability of each customer.

Encourages management to consider all resources consumed to serve a customer, not just manufacturing costs.

55

Learning Objective C3: Describe the four types of activities that cause overhead costs.

© McGraw-Hill Education 

2 - ‹#›

55

Companies should assess the profitability of their customers.

Can create a customer profitability report to determine the profitability of each customer.

Encourages management to consider all resources consumed to serve a customer, not just manufacturing costs.

End of Chapter 17

56

© McGraw-Hill Education 

2 - ‹#›

56

KartCo's Budgeted Direct Labor Hours

DirectTotal

Number LaborDirect Labor

of units

Hours per Unit

Hours

Standard go-kart5,000X15=

Custom go-kart1,000X25=

Total

Kartco's Budgeted Overhead Costs

Overhead Item:

75,000

25,000

$4,800,000

Indirect labor costs………………………………………………………………………………………………………………………………..

Factory utilities………………………………………………………………………………………………………………………………………..

Total budgeted overhead costs……………………………………………………………………………………………………………………………

$4,000,000

800,000

100,000

Sheet1

KartCo's Budgeted Direct Labor Hours
Direct Total
Number Labor Direct Labor
of units Hours per Unit Hours
Standard go-kart 5,000 X 15 = 75,000
Custom go-kart 1,000 X 25 = 25,000
Total 100,000
Kartco's Budgeted Overhead Costs
Overhead Item:
Indirect labor costs……………………………………………………………………………………………………………………………….. $4,000,000
Factory utilities……………………………………………………………………………………………………………………………………….. 800,000
Total budgeted overhead costs…………………………………………………………………………………………………………………………… $4,800,000

Allocation of overhead cost to products

OverheadAllocated

Rate PerPer

DLHDLHUnit

Standard go-kart$48X15=720$

Custom go-kart$48X25=1,200$

Total product cost per unit

Total

DirectDirectFactoryCost

MaterialsLaborOverheadper Unit

Standard go-kart400$ 350$ 720$ 1,470$

Custom go-kart600 500 1,200 2,300

Sheet1

Allocation of overhead cost to products
Overhead Allocated
Rate Per Per
DLH DLH Unit
Standard go-kart $48 X 15 = $ 720
Custom go-kart $48 X 25 = $ 1,200
Total product cost per unit
Total
Direct Direct Factory Cost
Materials Labor Overhead per Unit
Standard go-kart $ 400 $ 350 $ 720 $ 1,470
Custom go-kart 600 500 1,200 2,300

Sheet2

Sheet3

Number

of

Units

Hours per

Unit

Total

Hours

Hours per

UnitTotal Hours

Standard go-kart5,00010 MH 50,000 MH5 DLH 25,000 DLH

Custom go-kart1,00020 MH 20,000 MH5 DLH 5,000 DLH

Totals70,000 MH30,000 DLH

Exhibit 17.6 Allocation Information for Machining and Assembly Departments

Machining DepartmentAssembly Department

Sheet1

Exhibit 17.6 Allocation Information for Machining and Assembly Departments
Machining Department Assembly Department
Number of Units Hours per Unit Total Hours Hours per Unit Total Hours
Standard go-kart 5,000 10 MH 50,000 MH 5 DLH 25,000 DLH
Custom go-kart 1,000 20 MH 20,000 MH 5 DLH 5,000 DLH
Totals 70,000 MH 30,000 DLH

Departmental

Overhead Rate

Hours per

Unit

Overhead

Allocated

Hours per

Unit

Overhead

Allocated

Machining Dept.$60 per MH10 MH per unit$60020 MH per Unit1,200.00$

Assembly Dept.$20 per DLH5 DLH per unit1005 DLH per unit100.00$

Totals$7001,300.00$

Exhibit 17.8 Comparison of Plant wide OH Rate and Departmental OH Rate Methods:

Overhead per unit using:

Standard go KartCustom go-Kart

Plantwide OH Rate Method$7201,200$

Departmental OH Rate Method$7001,300

Exhibit 17.7 Overhead Allocation Using Departmental Overhead Rates

Standard go-kartCustom go-kart

Sheet1

Exhibit 17.7 Overhead Allocation Using Departmental Overhead Rates
Standard go-kart Custom go-kart
Departmental Overhead Rate Hours per Unit Overhead Allocated Hours per Unit Overhead Allocated
Machining Dept. $60 per MH 10 MH per unit $600 20 MH per Unit $ 1,200.00
Assembly Dept. $20 per DLH 5 DLH per unit 100 5 DLH per unit $ 100.00
Totals $700 $ 1,300.00
Exhibit 17.8 Comparison of Plant wide OH Rate and Departmental OH Rate Methods:
Overhead per unit using:
Standard go Kart Custom go-Kart
Plantwide OH Rate Method $720 $ 1,200
Departmental OH Rate Method $700 1,300

Activity

Indirect

Labor

Factory

Utilities

Total

Overhead

Machine setup700,000$ $700,000

Machine repair1,300,000$ 1,300,000

Factory maintenance800,000$ 800,000

Engineer salaries1,200,000$ 1,200,000

Assembly line power$600,000600,000

Heating and lighting200,000200,000

Totals$4,000,000$800,000$4,800,000

KartCo Overhead Cost Details

Sheet1

KartCo Overhead Cost Details
Activity Indirect Labor Factory Utilities Total Overhead
Machine setup $ 700,000 $700,000
Machine repair $ 1,300,000 1,300,000
Factory maintenance $ 800,000 800,000
Engineer salaries $ 1,200,000 1,200,000
Assembly line power $600,000 600,000
Heating and lighting 200,000 200,000
Totals $4,000,000 $800,000 $4,800,000

(A)

Total Overhead

cost allocated

(B)

Units of

production

(A/B)

Overhead cost

per Unit

Standard go-kart 1,500,000$ 5,000 units$300 per unit

Custom go-kart3,300,000$ 1,000 units$3,300 per unit

Overhead Cost per Unit for Go-Karts Using ABC

Sheet1

Overhead Cost per Unit for Go-Karts Using ABC
(A) Total Overhead cost allocated (B) Units of production (A/B) Overhead cost per Unit
Standard go-kart $ 1,500,000 5,000 units $300 per unit
Custom go-kart $ 3,300,000 1,000 units $3,300 per unit