Assignment !!

cezinha22
Chapter15PTT.ppt

15 - *

© 2014 Pearson Education, Inc.

Short-Term Scheduling

PowerPoint presentation to accompany

Heizer and Render

Operations Management, Eleventh Edition

Principles of Operations Management, Ninth Edition

PowerPoint slides by Jeff Heyl

15

© 2014 Pearson Education, Inc.

15 - *

© 2014 Pearson Education, Inc.

Outline

Global Company Profile:
Delta Air Lines

  • The Importance of Short-Term Scheduling
  • Scheduling Issues
  • Scheduling Process-Focused Facilities

*

15 - *

© 2014 Pearson Education, Inc.

Outline - Continued

Loading Jobs

Scheduling Jobs

Finite Capacity Scheduling (FCS)

Scheduling Services

*

15 - *

© 2014 Pearson Education, Inc.

Learning Objectives

When you complete this chapter you should be able to:

  • Explain the relationship between short-term scheduling, capacity planning, aggregate planning, and a master schedule
  • Draw Gantt loading and scheduling charts
  • Apply the assignment method for loading jobs

*

15 - *

© 2014 Pearson Education, Inc.

When you complete this chapter you should be able to:

Learning Objectives

  • Name and describe each of the priority sequencing rules
  • Use Johnson’s rule
  • Define finite capacity scheduling
  • Use the cyclical scheduling technique

*

15 - *

© 2014 Pearson Education, Inc.

Delta Airlines

  • About 10% of Delta’s flights are disrupted per year, half because of weather
  • Cost is $440 million in lost revenue, overtime pay, food and lodging vouchers
  • The $33 million Operations Control Center adjusts to changes and keeps flights flowing
  • Saves Delta $35 million per year

© 2014 Pearson Education, Inc.

*

15 - *

© 2014 Pearson Education, Inc.

Short-Term Scheduling

The objective of scheduling is to allocate and prioritize demand (generated by either forecasts or customer orders) to available facilities

15 - *

© 2014 Pearson Education, Inc.

Importance of Short-Term Scheduling

  • Effective and efficient scheduling can be a competitive advantage
  • Faster movement of goods through a facility means better use of assets and lower costs
  • Additional capacity resulting from faster throughput improves customer service through faster delivery
  • Good schedules result in more dependable deliveries

*

15 - *

© 2014 Pearson Education, Inc.

Scheduling Issues

  • Scheduling deals with the timing of operations
  • The task is the allocation and prioritization of demand
  • Significant factors are

Forward or backward scheduling

Finite or infinite loading

The criteria for sequencing jobs

*

15 - *

© 2014 Pearson Education, Inc.

Scheduling Decisions

TABLE 15.1 Scheduling Decisions
ORGANIZATION MANAGERS SCHEDULE THE FOLLOWING
Delta Air Lines Maintenance of aircraft Departure timetables Flight crews, catering, gate, ticketing personnel
Arnold Palmer Hospital Operating room use Patient admissions Nursing, security, maintenance staffs Outpatient treatments
University of Alabama Classrooms and audiovisual equipment Student and instructor schedules Graduate and undergraduate courses
Amway Center Ushers, ticket takers, food servers, security personnel Delivery of fresh foods and meal preparation Orlando Magic games, concerts, arena football
Lockheed Martin Factory Production of goods Purchases of materials Workers

*

15 - *

© 2014 Pearson Education, Inc.

Figure 15.1

Scheduling Flow

*

15 - *

© 2014 Pearson Education, Inc.

Forward and Backward Scheduling

  • Forward scheduling starts as soon as the requirements are known
  • Produces a feasible schedule though it may not meet due dates
  • Frequently results in
    buildup of work-in-
    process inventory

Due Date

Now

*

15 - *

© 2014 Pearson Education, Inc.

Forward and Backward Scheduling

  • Backward scheduling begins with the due date and schedules the final operation first
  • Schedule is produced by working backwards though the processes
  • Resources may not
    be available to
    accomplish the
    schedule

Due Date

Now

*

15 - *

© 2014 Pearson Education, Inc.

  • Backward scheduling begins with the due date and schedules the final operation first
  • Schedule is produced by working backwards though the processes
  • Resources may not
    be available to
    accomplish the
    schedule

Forward and Backward Scheduling

Often these approaches are combined to develop a trade-off between capacity constraints and customer expectations

Due Date

Now

*

15 - *

© 2014 Pearson Education, Inc.

Finite and Infinite Loading

  • Assigning jobs to work stations
  • Finite loading assigns work up to the capacity of the work station
  • All work gets done
  • Due dates may be pushed out
  • Infinite loading does not consider capacity
  • All due dates are met
  • Capacities may have to be adjusted

15 - *

© 2014 Pearson Education, Inc.

Scheduling Criteria

Minimize completion time

Maximize utilization of facilities

Minimize work-in-process (WIP) inventory

Minimize customer waiting time

*

15 - *

© 2014 Pearson Education, Inc.

Different Processes/
Different Approaches

TABLE 15.2 Different Processes Suggest Different Approaches to Scheduling
Process-focused facilities (job shops) Scheduling to customer orders where changes in both volume and variety of jobs/clients/patients are frequent Schedules are often due-date focused, with loading refined by finite loading techniques Examples: foundries, machine shops, cabinet shops, print shops, many restaurants, and the fashion industry
Repetitive facilities (assembly lines) Schedule module production and product assembly based on frequent forecasts Finite loading with a focus on generating a forward-looking schedule JIT techniques are used to schedule components that feed the assembly line Examples: assembly lines for washing machines at Whirlpool and automobiles at Ford.

*

15 - *

© 2014 Pearson Education, Inc.

Different Processes/
Different Approaches

TABLE 15.2 Different Processes Suggest Different Approaches to Scheduling
Product-focused facilities (continuous) Schedule high volume finished products of limited variety to meet a reasonably stable demand within existing fixed capacity Finite loading with a focus on generating a forward-looking schedule that can meet known setup and run times for the limited range of products Examples: huge paper machines at International Paper, beer in a brewery at Anheuser-Busch, and potato chips at Frito-Lay

*

15 - *

© 2014 Pearson Education, Inc.

Focus for Different
Process Strategies

Product-focused

(continuous)

Schedule finished product

Repetitive facilities (assemble lines)

Schedule modules

Process-focused

(job shops)

Schedule orders

Examples: Print shop Motorcycles Steel, Beer, Bread

Machine shop Autos, TVs Lightbulbs

Fine-dining restaurant Fast-food restaurant Paper

Typical focus of the master production schedule

Number of inputs

Number of end items

*

15 - *

© 2014 Pearson Education, Inc.

Scheduling Process-Focused Facilities

  • High-variety, low volume
  • Production differ considerably
  • Schedule incoming orders without violating capacity constraints
  • Scheduling can be complex

*

15 - *

© 2014 Pearson Education, Inc.

Loading Jobs

  • Assign jobs so that costs, idle time, or completion time are minimized
  • Two forms of loading
  • Capacity oriented
  • Assigning specific jobs to work centers

*

15 - *

© 2014 Pearson Education, Inc.

Input-Output Control

  • Identifies overloading and underloading conditions
  • Prompts managerial action to resolve scheduling problems
  • Can be maintained using ConWIP cards that control the scheduling of batches

*

15 - *

© 2014 Pearson Education, Inc.

Input-Output Control Example

Figure 15.2

Week Ending 6/6 6/13 6/20 6/27 7/4 7/11
Planned Input 280 280 280 280 280
Actual Input 270 250 280 285 280
Cumulative Deviation –10 –40 –40 –35
Planned Output 320 320 320 320
Actual Output 270 270 270 270
Cumulative Deviation –50 –100 –150 –200
Cumulative Change in Backlog 0 –20 –10 +5

Work Center DNC Milling (in standard hours)

*

15 - *

© 2014 Pearson Education, Inc.

Input-Output Control Example

Figure 15.2

Week Ending 6/6 6/13 6/20 6/27 7/4 7/11
Planned Input 280 280 280 280 280
Actual Input 270 250 280 285 280
Cumulative Deviation –10 –40 –40 –35
Planned Output 320 320 320 320
Actual Output 270 270 270 270
Cumulative Deviation –50 –100 –150 –200
Cumulative Change in Backlog 0 –20 –10 +5

Work Center DNC Milling (in standard hours)

Explanation:

270 input,

270 output implies

0 change

Explanation:

250 input,

270 output implies

–20 change

*

15 - *

© 2014 Pearson Education, Inc.

Input-Output Control Example

Options available to operations personnel include:

  • Correcting performances
  • Increasing capacity
  • Increasing or reducing input to the work center

*

15 - *

© 2014 Pearson Education, Inc.

Gantt Charts

  • Load chart shows the loading and idle times of departments, machines, or facilities
  • Displays relative workloads over time
  • Schedule chart monitors jobs in process
  • All Gantt charts need to be updated frequently to account for changes

*

15 - *

© 2014 Pearson Education, Inc.

Gantt Load Chart Example

Figure 15.3

Day

Monday

Tuesday

Wednesday

Thursday

Friday

Work Center

Metalworks

Mechanical

Electronics

Painting

Job 349

Job 349

Job 349

Job 408

Job 408

Job 408

Processing

Unscheduled

Center not available

Job 350

Job 349

Job 295

*

15 - *

© 2014 Pearson Education, Inc.

Gantt Schedule Chart Example

Figure 15.4

Job Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8
A
B
C

Now

Maintenance

Start of an activity

End of an activity

Scheduled activity time allowed

Actual work progress

Nonproduction time

Point in time when chart is reviewed

*

15 - *

© 2014 Pearson Education, Inc.

Assignment Method

  • A special class of linear programming models that assigns tasks or jobs to resources
  • Objective is to minimize cost or time
  • Only one job (or worker) is assigned to one machine (or project)

*

15 - *

© 2014 Pearson Education, Inc.

Assignment Method

  • Build a table of costs or time associated with particular assignments
TYPESETTER
JOB A B C
R-34 $11 $14 $ 6
S-66 $ 8 $10 $11
T-50 $ 9 $12 $ 7

*

15 - *

© 2014 Pearson Education, Inc.

Assignment Method

Create zero opportunity costs by repeatedly subtracting the lowest costs from each row and column

Draw the minimum number of vertical and horizontal lines necessary to cover all the zeros in the table. If the number of lines equals either the number of rows or the number of columns, proceed to step 4. Otherwise proceed to step 3.

*

15 - *

© 2014 Pearson Education, Inc.

Assignment Method

Subtract the smallest number not covered by a line from all other uncovered numbers. Add the same number to any number at the intersection of two lines. Return to step 2.

Optimal assignments are at zero locations in the table. Select one, draw lines through the row and column involved, and continue to the next assignment.

*

15 - *

© 2014 Pearson Education, Inc.

Assignment Example

A B C

Job

R-34 $11 $14 $ 6

S-66 $ 8 $10 $11

T-50 $ 9 $12 $ 7

Typesetter

A B C

Job

R-34 $ 5 $ 8 $ 0

S-66 $ 0 $ 2 $ 3

T-50 $ 2 $ 5 $ 0

Typesetter

Step 1a - Rows

A B C

Job

R-34 $ 5 $ 6 $ 0

S-66 $ 0 $ 0 $ 3

T-50 $ 2 $ 3 $ 0

Typesetter

Step 1b - Columns

*

15 - *

© 2014 Pearson Education, Inc.

Assignment Example

Because only two lines are needed to cover all the zeros, the solution is not optimal

The smallest uncovered number is 2 so this is subtracted from all other uncovered numbers and added to numbers at the intersection of lines

A B C

Job

R-34 $ 5 $ 6 $ 0

S-66 $ 0 $ 0 $ 3

T-50 $ 2 $ 3 $ 0

Typesetter

Step 2 - Lines

A B C

Job

R-34 $ 3 $ 4 $ 0

S-66 $ 0 $ 0 $ 5

T-50 $ 0 $ 1 $ 0

Typesetter

Step 3 - Subtraction

Smallest uncovered number

*

15 - *

© 2014 Pearson Education, Inc.

Assignment Example

Because three lines are needed, the solution is optimal and assignments can be made

Start by assigning R-34 to worker C as this is the only possible assignment for worker C.

Job T-50 must go to worker A as worker C is already assigned. This leaves S-66 for worker B.

A B C

Job

R-34 $ 3 $ 4 $ 0

S-66 $ 0 $ 0 $ 5

T-50 $ 0 $ 1 $ 0

Typesetter

Step 2 - Lines

A B C

Job

R-34 $ 3 $ 4 $ 0

S-66 $ 0 $ 0 $ 5

T-50 $ 0 $ 1 $ 0

Typesetter

Step 4 - Assignments

*

15 - *

© 2014 Pearson Education, Inc.

Assignment Example

A B C

Job

R-34 $ 3 $ 4 $ 0

S-66 $ 0 $ 0 $ 5

T-50 $ 0 $ 1 $ 0

Typesetter

A B C

Job

R-34 $11 $14 $ 6

S-66 $ 8 $10 $11

T-50 $ 9 $12 $ 7

Typesetter

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing Jobs

  • Specifies the order in which jobs should be performed at work centers
  • Priority rules are used to dispatch or sequence jobs
  • FCFS: First come, first served
  • SPT: Shortest processing time
  • EDD: Earliest due date
  • LPT: Longest processing time

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing Example

Apply the four popular sequencing rules to these five jobs

Job Job Work (Processing) Time (Days) Job Due Date (Days)
A 6 8
B 2 6
C 8 18
D 3 15
E 9 23

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing Example

FCFS: Sequence A-B-C-D-E

Job Sequence Job Work (Processing) Time Flow Time Job Due Date Job Lateness
A 6 6 8 0
B 2 8 6 2
C 8 16 18 0
D 3 19 15 4
E 9 28 23 5
28 77 11

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing Example

FCFS: Sequence A-B-C-D-E

Sum of total flow time

Number of jobs

Average completion time = = 77/5 = 15.4 days

Total job work time

Sum of total flow time

Utilization metric = = 28/77 = 36.4%

Sum of total flow time

Total job work time

Average number of jobs in the system

= = 77/28 = 2.75 jobs

Total late days

Number of jobs

Average job lateness = = 11/5 = 2.2 days

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing Example

SPT: Sequence B-D-A-C-E

Job Sequence Job Work (Processing) Time Flow Time Job Due Date Job Lateness
B 2 2 6 0
D 3 5 15 0
A 6 11 8 3
C 8 19 18 1
E 9 28 23 5
28 65 9

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing Example

SPT: Sequence B-D-A-C-E

Sum of total flow time

Number of jobs

Average completion time = = 65/5 = 13 days

Total job work time

Sum of total flow time

Utilization metric = = 28/65 = 43.1%

Sum of total flow time

Total job work time

Average number of jobs in the system

= = 65/28 = 2.32 jobs

Total late days

Number of jobs

Average job lateness = = 9/5 = 1.8 days

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing Example

EDD: Sequence B-A-D-C-E

Job Sequence Job Work (Processing) Time Flow Time Job Due Date Job Lateness
B 2 2 6 0
A 6 8 8 0
D 3 11 15 0
C 8 19 18 1
E 9 28 23 5
28 68 6

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing Example

EDD: Sequence B-A-D-C-E

Sum of total flow time

Number of jobs

Average completion time = = 68/5 = 13.6 days

Total job work time

Sum of total flow time

Utilization metric = = 28/68 = 41.2%

Sum of total flow time

Total job work time

Average number of jobs in the system

= = 68/28 = 2.43 jobs

Total late days

Number of jobs

Average job lateness = = 6/5 = 1.2 days

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing Example

LPT: Sequence E-C-A-D-B

Job Sequence Job Work (Processing) Time Flow Time Job Due Date Job Lateness
E 9 9 23 0
C 8 17 18 0
A 6 23 8 15
D 3 26 15 11
B 2 28 6 22
28 103 48

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing Example

LPT: Sequence E-C-A-D-B

Sum of total flow time

Number of jobs

Average completion time = = 103/5 = 20.6 days

Total job work time

Sum of total flow time

Utilization metric = = 28/103 = 27.2%

Sum of total flow time

Total job work time

Average number of jobs in the system

= = 103/28 = 3.68 jobs

Total late days

Number of jobs

Average job lateness = = 48/5 = 9.6 days

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing Example

Summary of Rules

Rule Average Completion Time (Days) Utilization Metric (%) Average Number of Jobs in System Average Lateness (Days)
FCFS 15.4 36.4 2.75 2.2
SPT 13.0 43.1 2.32 1.8
EDD 13.6 41.2 2.43 1.2
LPT 20.6 27.2 3.68 9.6

*

15 - *

© 2014 Pearson Education, Inc.

Comparison of
Sequencing Rules

  • No one sequencing rule excels on all criteria

SPT does well on minimizing flow time and number of jobs in the system

But SPT moves long jobs to
the end which may result
in dissatisfied customers

FCFS does not do especially
well (or poorly) on any
criteria but is perceived
as fair by customers

EDD minimizes maximum
lateness

*

15 - *

© 2014 Pearson Education, Inc.

Critical Ratio (CR)

  • An index number found by dividing the time remaining until the due date by the work time remaining on the job
  • Jobs with low critical ratios are scheduled ahead of jobs with higher critical ratios
  • Performs well on average job lateness criteria

Due date – Today’s date

Work (lead) time remaining

Time remaining

Workdays remaining

CR = =

*

15 - *

© 2014 Pearson Education, Inc.

Critical Ratio Example

Currently Day 25

With CR < 1, Job B is late. Job C is just on schedule and Job A has some slack time.

JOB DUE DATE WORKDAYS REMAINING
A 30 4
B 28 5
C 27 2
JOB CRITICAL RATIO PRIORITY ORDER
A (30 - 25)/4 = 1.25 3
B (28 - 25)/5 = .60 1
C (27 - 25)/2 = 1.00 2

*

15 - *

© 2014 Pearson Education, Inc.

Critical Ratio Technique

Helps determine the status of specific jobs

Establishes relative priorities among jobs on a common basis

Adjusts priorities automatically for changes in both demand and job progress

Dynamically tracks job progress

*

15 - *

© 2014 Pearson Education, Inc.

Sequencing N Jobs on Two Machines: Johnson’s Rule

  • Works with two or more jobs that pass through the same two machines or work centers
  • Minimizes total production time and idle time
  • An N/2 problem, N number of jobs through 2 workstations

*

15 - *

© 2014 Pearson Education, Inc.

Johnson’s Rule

List all jobs and times for each work center

Choose the job with the shortest activity time. If that time is in the first work center, schedule the job first. If it is in the second work center, schedule the job last.

Once a job is scheduled, it is eliminated from the list

Repeat steps 2 and 3 working toward the center of the sequence

*

15 - *

© 2014 Pearson Education, Inc.

Johnson’s Rule Example

JOB WORK CENTER 1 (DRILL PRESS) WORK CENTER 2 (LATHE)
A 5 2
B 3 6
C 8 4
D 10 7
E 7 12

*

15 - *

© 2014 Pearson Education, Inc.

Johnson’s Rule Example

JOB WORK CENTER 1 (DRILL PRESS) WORK CENTER 2 (LATHE)
A 5 2
B 3 6
C 8 4
D 10 7
E 7 12

A

C

B

D

E

*

15 - *

© 2014 Pearson Education, Inc.

Johnson’s Rule Example

JOB WORK CENTER 1 (DRILL PRESS) WORK CENTER 2 (LATHE)
A 5 2
B 3 6
C 8 4
D 10 7
E 7 12

B

A

C

D

E

WC 1

WC 2

Time 0 3 10 20 28 33

B

A

C

D

E

Job completed

Idle

*

15 - *

© 2014 Pearson Education, Inc.

Johnson’s Rule Example

Time 0 3 10 20 28 33

Time 0 1 3 5 7 9 10 11 12 13 17 19 21 22 23 25 27 29 31 33 35

JOB WORK CENTER 1 (DRILL PRESS) WORK CENTER 2 (LATHE)
A 5 2
B 3 6
C 8 4
D 10 7
E 7 12

B

A

C

D

E

B

A

C

D

E

WC 1

WC 2

B

E

D

C

A

B

A

C

D

E

Job completed

Idle

*

15 - *

© 2014 Pearson Education, Inc.

Limitations of Rule-Based Dispatching Systems

  • Scheduling is dynamic and rules need to be revised to adjust to changes
  • Rules do not look upstream or downstream
  • Rules do not look beyond due dates

*

15 - *

© 2014 Pearson Education, Inc.

Finite Capacity Scheduling

  • Overcomes disadvantages of rule-based systems by providing an interactive, computer-based graphical system
  • May include rules and expert systems or simulation to allow real-time response to system changes
  • FCS allows the balancing of delivery needs and efficiency

*

15 - *

© 2014 Pearson Education, Inc.

Finite Capacity Scheduling

Figure 15.5

Interactive Finite Capacity Scheduling

Planning Data

  • Master schedule
  • BOM
  • Inventory

Priority rules

  • Expert systems
  • Simulation models

  • Routing files
  • Work center information

Tooling and other resources

Setups and run time

*

15 - *

© 2014 Pearson Education, Inc.

Finite Capacity Scheduling

Figure 15.6

*

15 - *

© 2014 Pearson Education, Inc.

Scheduling Services

Service systems differ from manufacturing

MANUFACTURING SERVICES
Schedules machines and materials Schedule staff
Inventories used to smooth demand Seldom maintain inventories
Machine-intensive and demand may be smooth Labor-intensive and demand may be variable
Scheduling may be bound by union contracts Legal issues may constrain flexible scheduling
Few social or behavioral issues Social and behavioral issues may be quite important

*

15 - *

© 2014 Pearson Education, Inc.

Scheduling Services

  • Hospitals have complex scheduling system to handle complex processes and material requirements
  • Banks use a cross-trained and flexible workforce and part-time workers
  • Retail stores use scheduling optimization systems that track sales, transactions, and customer traffic to create work schedules in less time and with improved customer satisfaction

*

15 - *

© 2014 Pearson Education, Inc.

Scheduling Services

  • Airlines must meet complex FAA and union regulations and often use linear programming to develop optimal schedules
  • 24/7 operations like police/fire departments, emergency hot lines, and mail order businesses use flexible workers and variable schedules, often created using computerized systems

*

15 - *

© 2014 Pearson Education, Inc.

Scheduling Service Employees With Cyclical Scheduling

  • Objective is to meet staffing requirements with the minimum number of workers
  • Schedules need to be smooth and keep personnel happy
  • Many techniques exist from simple algorithms to complex linear programming solutions

*

15 - *

© 2014 Pearson Education, Inc.

Cyclical Scheduling Example

  • Determine the staffing requirements
  • Identify two consecutive days with the lowest total requirements and assign these as days off
  • Make a new set of requirements subtracting the days worked by the first employee
  • Apply step 2 to the new row
  • Repeat steps 3 and 4 until all requirements have been met

*

15 - *

© 2014 Pearson Education, Inc.

Cyclical Scheduling Example

M T W T F S S
Employee 1 5 5 6 5 4 3 3
Capacity (Employees)
Excess Capacity
DAY M T W T F S S
Staff required 5 5 6 5 4 3 3

*

15 - *

© 2014 Pearson Education, Inc.

Cyclical Scheduling Example

M T W T F S S
Employee 1 5 5 6 5 4 3 3
Employee 2 4 4 5 4 3 3 3
Capacity (Employees)
Excess Capacity
DAY M T W T F S S
Staff required 5 5 6 5 4 3 3

*

15 - *

© 2014 Pearson Education, Inc.

Cyclical Scheduling Example

M T W T F S S
Employee 1 5 5 6 5 4 3 3
Employee 2 4 4 5 4 3 3 3
Employee 3 3 3 4 3 2 3 3
Capacity (Employees)
Excess Capacity
DAY M T W T F S S
Staff required 5 5 6 5 4 3 3

*

15 - *

© 2014 Pearson Education, Inc.

Cyclical Scheduling Example

M T W T F S S
Employee 1 5 5 6 5 4 3 3
Employee 2 4 4 5 4 3 3 3
Employee 3 3 3 4 3 2 3 3
Employee 4 2 2 3 2 2 3 2
Capacity (Employees)
Excess Capacity
DAY M T W T F S S
Staff required 5 5 6 5 4 3 3

*

15 - *

© 2014 Pearson Education, Inc.

Cyclical Scheduling Example

M T W T F S S
Employee 1 5 5 6 5 4 3 3
Employee 2 4 4 5 4 3 3 3
Employee 3 3 3 4 3 2 3 3
Employee 4 2 2 3 2 2 3 2
Employee 5 1 1 2 2 2 2 1
Capacity (Employees)
Excess Capacity
DAY M T W T F S S
Staff required 5 5 6 5 4 3 3

*

15 - *

© 2014 Pearson Education, Inc.

Cyclical Scheduling Example

M T W T F S S
Employee 1 5 5 6 5 4 3 3
Employee 2 4 4 5 4 3 3 3
Employee 3 3 3 4 3 2 3 3
Employee 4 2 2 3 2 2 3 2
Employee 5 1 1 2 2 2 2 1
Employee 6 1 1 1 1 1 1 0
Capacity (Employees)
Excess Capacity
DAY M T W T F S S
Staff required 5 5 6 5 4 3 3

*

15 - *

© 2014 Pearson Education, Inc.

Cyclical Scheduling Example

M T W T F S S
Employee 1 5 5 6 5 4 3 3
Employee 2 4 4 5 4 3 3 3
Employee 3 3 3 4 3 2 3 3
Employee 4 2 2 3 2 2 3 2
Employee 5 1 1 2 2 2 2 1
Employee 6 1 1 1 1 1 1 0
Employee 7 1
Capacity (Employees) 5 5 6 5 4 3 3
Excess Capacity 0 0 0 0 0 1 0
DAY M T W T F S S
Staff required 5 5 6 5 4 3 3

*

15 - *

© 2014 Pearson Education, Inc.

All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of the publisher.

Printed in the United States of America.