Order 1270563: inventory management
Managing
Inventories
Chapter 9
Copyright ©2016 Pearson Education, Limited.
9-‹#›
What is a Inventory Management?
Inventory Management
The planning and controlling of inventories to meet the competitive priorities of the organization.
Copyright ©2016 Pearson Education, Limited.
9-‹#›
2
What is Inventory?
Inventory
A stock of materials used to satisfy customer demand or to support the production of services or goods.
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Inventory Trade-Offs
Scrap flow
Inventory level
Output flow of materials
Input flow of materials
Figure 9.1
Copyright ©2016 Pearson Education, Limited.
9-‹#›
4
Pressures for Small Inventories
Inventory holding cost
Cost of capital
Storage and handling costs
Taxes
Insurance
Shrinkage
Pilferage
Obsolescence
Deterioration
Copyright ©2016 Pearson Education, Limited.
9-‹#›
5
Pressures for Large Inventories
Customer service
Ordering cost
Setup cost
Labor and equipment utilization
Transportation cost
Payments to suppliers
Copyright ©2016 Pearson Education, Limited.
9-‹#›
6
Types of Inventory
Accounting Inventories
Raw materials
Work-in-process
Finished goods
Copyright ©2016 Pearson Education, Limited.
9-‹#›
7
Types of Inventory
Figure 9.2
Copyright ©2016 Pearson Education, Limited.
9-‹#›
8
Types of Inventory
Operational Inventories
Cycle Inventory
Safety Stock Inventory
Anticipation Inventory
Pipeline Inventory
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Cycle Inventory
Lot sizing principles
The lot size, Q, varies directly with the elapsed time (or cycle) between orders.
The longer the time between orders for a given item, the greater the cycle inventory must be.
Average cycle inventory = =
Q + 0
2
Q
2
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Cycle Inventory
Copyright ©2013 Pearson Education
09- 11
d = Average demand per time period = Q/P
= slope of the consumption linear function
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Safety Stock Inventory Anticipation Inventory
Copyright ©2013 Pearson Education
09- 12
Safety stock inventory is surplus inventory that protects against uncertainties in demand, lead time, and supply changes.
Inventory used to absorb uneven rates of demand or supply, which businesses often face, is referred to as anticipation inventory
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Pipeline Inventory
Average demand during lead time = DL
Average demand per period = d
Number of periods in the item’s lead time = L
Pipeline inventory = DL = dL
Assume that every period P we order a quantity Q.
The pipeline inventory is Q during L and 0 during P-L.
The average inventory is therefore:
[Q⨯L+0⨯(P-L)]÷[L+(P-L)] = (Q/P) L = dL
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.1
A plant makes monthly shipments of electric drills to a wholesaler in average lot sizes of 280 drills. The wholesaler’s average demand is 70 drills a week, and the lead time from the plant is 3 weeks. The wholesaler must pay for the inventory from the moment the plant makes a shipment. If the wholesaler is willing to increase its purchase quantity to 350 units, the plant will give priority to the wholesaler and guarantee a lead time of only 2 weeks. What is the effect on the wholesaler’s cycle and pipeline inventories?
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.1
The wholesaler’s current cycle and pipeline inventories are
Cycle inventory = = 140 drills
Q
2
(70 drills/week)(3 weeks)
= 210 drills
Pipeline inventory = DL = dL =
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.1
The wholesaler’s cycle and pipeline inventories if they accept the new proposal
(70 drills/week)(2 weeks)
= 140 drills
Pipeline inventory = DL = dL =
Cycle inventory = = 175 drills
Q
2
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Inventory Reduction Tactics
Cycle inventory
Reduce the lot size
Reduce ordering and setup costs and allow Q to be reduced
Increase repeatability to eliminate the need for changeovers
Safety stock inventory
Place orders closer to the time when they must be received
Improve demand forecasts
Cut lead times
Reduce supply uncertainties
Rely more on equipment and labor buffers
PL = primary lever
SL = secondary lever
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Inventory Reduction Tactics
Anticipation inventory
Match demand rate with production rates
Add new products with different demand cycles
Provide off-season promotional campaigns
Offer seasonal pricing plans
Pipeline inventory
Reduce lead times
Find more responsive suppliers and select new carriers
Change Q in those cases where the lead time depends on the lot size
Copyright ©2016 Pearson Education, Limited.
9-‹#›
What is an ABC Analysis?
A stock-keeping unit (SKU) is an individual item or product that has an identifying code and is held in inventory somewhere along the supply chain.
ABC analysis is the process of dividing SKUs into three classes, according to their dollar usage, so that managers can focus on items that have the highest dollar value.
See Solved Problem 2
09- 19
Copyright ©2013 Pearson Education
Copyright ©2016 Pearson Education, Limited.
9-‹#›
What is an ABC Analysis?
ABC Analysis
The process of dividing SKUs into three classes, according to their dollar usage, so that managers can focus on items that have the highest dollar value.
10
20
30
40
50
60
70
80
90
100
Percentage of SKUs
Percentage of dollar value
100 —
90 —
80 —
70 —
60 —
50 —
40 —
30 —
20 —
10 —
0 —
Class C
Class A
Class B
Figure 9.4
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Economic Order Quantity
The lot size, Q, that minimizes total annual inventory holding and ordering costs
Five assumptions
Demand rate is constant and known with certainty.
No constraints are placed on the size of each lot.
The only two relevant costs are the inventory holding cost and the fixed cost per lot for ordering or setup.
Decisions for one item can be made independently of decisions for other items.
The lead time is constant and known with certainty.
Copyright ©2016 Pearson Education, Limited.
9-‹#›
21
Economic Order Quantity
Don’t use the EOQ
Make-to-order strategy
Order size is constrained
Modify the EOQ
Quantity discounts
Replenishment not instantaneous
Use the EOQ
Make-to-stock strategy with relatively stable demand.
Carrying and setup costs are known and relatively stable
Copyright ©2016 Pearson Education, Limited.
9-‹#›
22
Calculating EOQ
Inventory depletion (demand rate)
Receive order
1 cycle
On-hand inventory (units)
Time
Q
Average
cycle
inventory
Q
2
Figure 9.5
Copyright ©2016 Pearson Education, Limited.
9-‹#›
23
Calculating EOQ
Annual holding cost
Annual holding cost = (Average cycle inventory) (Unit holding cost)
Total costs = Annual holding cost + Annual ordering or setup cost
Annual ordering cost = (Number of orders/Year) (Ordering or setup costs)
Annual ordering cost
Total annual cycle inventory cost
Copyright ©2016 Pearson Education, Limited.
9-‹#›
24
Annual cost (dollars)
Lot Size (Q)
Holding cost
Ordering cost
Total cost
Calculating EOQ
Figure 9.6
Copyright ©2016 Pearson Education, Limited.
9-‹#›
25
Calculating EOQ
Total annual cycle-inventory cost
where
C = total annual cycle-inventory cost
Q = lot size (in units)
H = holding cost per unit per year
D = annual demand (in units)
S = ordering or setup costs per lot
C = (H) + (S)
Q
2
D
Q
Copyright ©2016 Pearson Education, Limited.
9-‹#›
26
Example 9.2
A museum of natural history opened a gift shop which operates 52 weeks per year.
Top-selling SKU is a bird feeder.
Sales are 18 units per week, the supplier charges $60 per unit.
Ordering cost is $45.
Annual holding cost is 25 percent of a feeder’s value.
Management chose a 390-unit lot size.
What is the annual cycle-inventory cost of the current policy of using a 390-unit lot size?
Would a lot size of 468 be better?
Copyright ©2016 Pearson Education, Limited.
9-‹#›
27
Example 9.2
We begin by computing the annual demand and holding cost as
D =
H =
C = (H) + (S)
Q
2
D
Q
The total annual cycle-inventory cost for the alternative lot size is
= ($15) + ($45)
= $2,925 + $108 = $3,033
390
2
936
390
The total annual cycle-inventory cost for the current policy is
(18 units/week)(52 weeks/year) = 936 units
0.25($60/unit) = $15
C =
($15) + ($45) = $3,510 + $90 = $3,600
468
2
936
468
Copyright ©2016 Pearson Education, Limited.
9-‹#›
28
Example 9.2
3000 –
2000 –
1000 –
0 –
| | | | | | | |
50 100 150 200 250 300 350 400
Lot Size (Q)
Annual cost (dollars)
Current
Q
Current
cost
Lowest
cost
Best Q (EOQ)
Total cost
= (H) + (S)
Q
2
D
Q
Ordering cost = (S)
D
Q
Holding cost = (H)
Q
2
Figure 9.7
Copyright ©2016 Pearson Education, Limited.
9-‹#›
29
Calculating EOQ
The EOQ formula:
EOQ =
2DS
H
TBOEOQ = (12 months/year)
EOQ
D
Time Between Orders (TBO):
Copyright ©2016 Pearson Education, Limited.
9-‹#›
30
Example 9.3
For the bird feeders in Example 9.2, calculate the EOQ and its total annual cycle-inventory cost. How frequently will orders be placed if the EOQ is used?
Using the formulas for EOQ and annual cost, we get
EOQ = =
2DS
H
= 74.94 or 75 units
2(936)(45)
15
Copyright ©2016 Pearson Education, Limited.
9-‹#›
31
Example 9.3
Below shows that the total annual cost is much less than the $3,033 cost of the current policy of placing 390-unit orders.
Figure 9.8
Copyright ©2016 Pearson Education, Limited.
9-‹#›
32
Example 9.3
When the EOQ is used, the TBO can be expressed in various ways for the same time period.
TBOEOQ =
EOQ
D
TBOEOQ = (12 months/year)
EOQ
D
TBOEOQ = (52 weeks/year)
EOQ
D
TBOEOQ = (365 days/year)
EOQ
D
= = 0.080 year
75
936
= (12) = 0.96 month
75
936
= (52) = 4.17 weeks
75
936
= (365) = 29.25 days
75
936
Copyright ©2016 Pearson Education, Limited.
9-‹#›
33
Application 9.1
Suppose that you are reviewing the inventory policies on an $80 item stocked at a hardware store. The current policy is to replenish inventory by ordering in lots of 360 units. Additional information is:
D = 60 units per week, or 3,120 units per year
S = $30 per order
H = 25% of selling price, or $20 per unit per year
What is the EOQ?
EOQ = =
2DS
H
= 97 units
2(3,120)(30)
20
Copyright ©2016 Pearson Education, Limited.
9-‹#›
| Current Policy | EOQ Policy | |
Application 9.1
What is the total annual cost of the current policy (Q = 360), and how does it compare with the cost with using the EOQ?
| Q = 360 units |
| Q = 97 units |
| C = 3,600 + 260 |
| C = $3,860 |
| C = (360/2)(20) + (3,120/360)(30) |
| C = 970 + 965 |
| C = $1,935 |
| C = (97/2)(20) + (3,120/97)(30) |
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Application 9.1
What is the time between orders (TBO) for the current policy and the EOQ policy, expressed in weeks?
TBO360 =
TBOEOQ =
(52 weeks per year) = 6 weeks
360
3,120
(52 weeks per year) = 1.6 weeks
97
3,120
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Managerial Insights from the EOQ
| SENSITIVITY ANALYSIS OF THE EOQ | ||||
| Parameter | EOQ | Parameter Change | EOQ Change | Comments |
| Demand | ↑ | ↑ | Increase in lot size is in proportion to the square root of D. | |
| Order/ Setup Costs | ↓ | ↓ | Weeks of supply decreases and inventory turnover increases because the lot size decreases. | |
| Holding Costs | ↓ | ↑ | Larger lots are justified when holding costs decrease. |
Table 9.1
2DS
H
2DS
H
2DS
H
Copyright ©2016 Pearson Education, Limited.
9-‹#›
37
Continuous Review System
Continuous review (Q) system
Reorder point system (ROP) and fixed order quantity system
Tracks inventory position (IP)
Includes scheduled receipts (SR), on-hand inventory (OH), and back orders (BO)
Inventory position = On-hand inventory + Scheduled receipts – Backorders
IP = OH + SR – BO
Copyright ©2016 Pearson Education, Limited.
9-‹#›
38
Continuous Review System
Time
On-hand inventory
TBO
TBO
L
L
TBO
L
Order
placed
Order
placed
Order
placed
IP
IP
IP
R
Q
Q
Q
OH
OH
OH
Order
received
Order
received
Order
received
Order
received
Figure 9.9
Selecting the Reorder Point
When Demand and Lead Time are Constant
Copyright ©2016 Pearson Education, Limited.
9-‹#›
39
Example 9.4
Demand for chicken soup at a supermarket is always 25 cases a day and the lead time is always 4 days. The shelves were just restocked with chicken soup, leaving an on-hand inventory of only 10 cases. No backorders currently exist, but there is one open order in the pipeline for 200 cases. What is the inventory position? Should a new order be placed?
R = Total demand during lead time = (25)(4) = 100 cases
= 10 + 200 – 0 = 210 cases
IP = OH + SR – BO
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Application 9.2
The on-hand inventory is only 10 units, and the reorder point R is 100. There are no backorders and one open order for 200 units. Should a new order be placed?
IP = OH + SR – BO =
10 + 200 – 0 = 210
R = 100
Decision: Place NO new order
Copyright ©2016 Pearson Education, Limited.
9-‹#›
41
Continuous Review Systems
Time
On-hand inventory
TBO1
TBO2
TBO3
L1
L2
L3
R
Order
received
Q
Order
placed
Order
placed
Order
received
IP
IP
Q
Order
placed
Q
Order
received
Order
received
0
IP
Figure 9.10
Selecting the Reorder Point When Demand is Variable and Lead Time is Constant
Copyright ©2016 Pearson Education, Limited.
9-‹#›
42
Example 9.5
A distribution center (DC) in Wisconsin stocks Sony plasma TV sets. The center receives its inventory from a mega warehouse in Kansas with a lead time (L) of 5 days. The DC uses a reorder point (R) of 300 sets and a fixed order quantity (Q) of 250 sets. Current on-hand inventory at the end of Day 1 is 400 sets. There are no scheduled receipts (SR) and no backorders (BO). All demands and receipts occur at the end of the day.
Determine when to order using a Q system
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.5
| Day | Demand | OH | SR | BO | IP | Q |
| 1 | 50 | 400 | ||||
| 2 | ||||||
| 3 | ||||||
| 4 | ||||||
| 5 | ||||||
| 6 | ||||||
| 7 |
400 + 0 = 400
340 + 0 = 340
250 after ordering
260 < R before ordering
60
80
40
75
55
95
260 + 250 = 510 after ordering
260
220
145
90
0
340
250 due
Day 8
250
250
250
220 + 250 = 470
145 + 250 = 395
90 + 250 = 340
250+ 250 = 500
after ordering
0 + 250 – 5 = 245 < R before ordering
245 + 250 = 495 after ordering
250 due
Day 12
5
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.5
| Day | Demand | OH | SR | BO | IP | Q |
| 8 | ||||||
| 9 | ||||||
| 10 | ||||||
| 11 | ||||||
| 12 | ||||||
| 13 | ||||||
| 14 |
195 + 250 = 445
150 + 250 = 400
250
120 + 250 = 370
45
30
50
60
40
50
120
70
70 – 60 + 250
= 260
260 – 40 = 220
170
195 – 45 = 150
250
250 after
ordering
250
70 + 250 = 320
220 + 250 = 470
250
260 < R before ordering
260 + 250 = 510 after ordering
250 due
Day 17
170 + 250 = 420
250
250
50
0 + 250 – 50 -5 = 195
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.5
The demands at the DC are fairly volatile and cause the reorder point to be breached quite dramatically at times.
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Continuous Review Systems
Selecting the reorder point with variable demand and constant lead time
Reorder point = Average demand during lead time + Safety stock
= dL + safety stock
where
d= average demand per week (or day or months)
L = constant lead time in weeks (or days or months)
Copyright ©2016 Pearson Education, Limited.
9-‹#›
47
Continuous Review System
Choosing a Reorder Point
Choose an appropriate service-level policy
Determine the distribution of demand during lead time
Determine the safety stock and reorder point levels
Copyright ©2016 Pearson Education, Limited.
9-‹#›
48
Continuous Review System
Step 1: Service Level Policy
Service Level (Cycle Service Level) – The desired probability of not running out of stock in any one ordering cycle, which begins at the time an order is placed and ends when it arrives in stock.
Protection Interval – The period over which safety stock must the user from running out of stock.
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Continuous Review System
Specify mean and standard deviation
Standard deviation of demand during lead time
σdLT = σd2L = σd L
Step 2: Distribution of Demand during Lead Time
Copyright ©2016 Pearson Education, Limited.
9-‹#›
50
σd = 15
+
75
Demand for week 1
σdlt = 25.98
225
Demand for 3-week lead time
+
75
Demand for week 2
σd = 15
=
75
Demand for week 3
σd = 15
Continuous Review System
Figure 9.11
Copyright ©2016 Pearson Education, Limited.
9-‹#›
51
Continuous Review System
Average demand during lead time
Cycle-service level = 85%
Probability of stockout
(1.0 – 0.85 = 0.15)
zσdLT
R
Figure 9.12
Copyright ©2016 Pearson Education, Limited.
9-‹#›
52
Continuous Review System
Step 3: Safety Stock and Reorder Point
Safety stock = zσdLT
where
z = number of standard deviations needed to achieve the cycle-service level
σdLT = stand deviation of demand during lead time
Reorder point = R = dL + safety stock
Copyright ©2016 Pearson Education, Limited.
9-‹#›
53
Example 9.6
Let us return to the bird feeder in Example 9.3.
The EOQ is 75 units.
Suppose that the average demand is 18 units per week with a standard deviation of 5 units.
The lead time is constant at two weeks.
Determine the safety stock and reorder point if management wants a 90 percent cycle-service level.
Safety stock = zσdLT = 1.28(7.07) =
9.05 or 9 units
Reorder point = d L + Safety stock =
2(18) + 9 = 45 units
Copyright ©2016 Pearson Education, Limited.
9-‹#›
54
Application 9.3
Suppose that the demand during lead time is normally distributed with an average of 85 and σdLT = 40. Find the safety stock, and reorder point R, for a 95 percent cycle-service level.
Safety stock = zσdLT =
Find the safety stock, and reorder point R, for an 85 percent cycle-service level.
R = Average demand during lead time + Safety stock
R = 85 + 66 = 151 units
1.645(40) = 65.8 or 66 units
Safety stock = zσdLT =
1.04(40) = 41.6 or 42 units
R = Average demand during lead time + Safety stock
R = 85 + 42 = 127 units
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Continuous Review System
Selecting the Reorder Point When Demand and Lead Time are Variable
Safety stock = zσdLT
R = (Average weekly demand Average lead time) + Safety stock
= d L + Safety stock
Copyright ©2016 Pearson Education, Limited.
9-‹#›
56
Example 9.7
The Office Supply Shop estimates that the average demand for a popular ball-point pen is 12,000 pens per week with a standard deviation of 3,000 pens.
The current inventory policy calls for replenishment orders of 156,000 pens.
The average lead time from the distributor is 5 weeks, with a standard deviation of 2 weeks.
If management wants a 95 percent cycle-service level, what should the reorder point be?
Copyright ©2016 Pearson Education, Limited.
9-‹#›
57
Example 9.7
Safety stock = zσdLT =
(1.65)(24,919.87) = 41,117.79 or 41,118 pens
We have d = 12,000 pens, σd = 3,000 pens, L = 5 weeks, and σLT = 2 weeks
σdLT = L σd2 + d 2σLT2 =
(5)(3,000)2 + (12,000)2(2)2
= 24,919.87 pens
Reorder point = d L + Safety stock =
(12,000)(5) + 41,118
= 101,118 pens
Copyright ©2016 Pearson Education, Limited.
9-‹#›
58
Continuous Review Systems
Two-Bin system
A visual system version of the Q system in which a SKU’s inventory is stored at two different locations.
Calculating Total Q System Costs
Total cost = Annual cycle inventory holding cost + Annual ordering cost + Annual safety stock holding cost
C = (H) + (S) + (H) (Safety stock)
Q
2
D
Q
Copyright ©2016 Pearson Education, Limited.
9-‹#›
59
Continuous Review System
Advantages of the Q System
The review frequency of each SKU may be individualized.
Fixed lot sizes can results in quantity discounts.
The system requires low levels of safety stock for the amount of uncertainty in demands during the lead time.
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Application 9.5
The Discount Appliance Store uses a continuous review system (Q system). One of the company’s items has the following characteristics:
Demand = 10 units/week (assume 52 weeks per year)
Ordering or setup cost (S) = $45/order
Holding cost (H) = $12/unit/year
Lead time (L) = 3 weeks (constant)
Standard deviation in weekly demand = 8 units
Cycle-service level = 70%
Copyright ©2016 Pearson Education, Limited.
9-‹#›
61
Application 9.5
What is the EOQ for this item?
D =
10/wk 52 wks/yr = 520 units
EOQ = =
2DS
H
= 62 units
2(520)(45)
12
What is the desired safety stock?
σdLT = σd L =
8 3 = 14 units
Safety stock = zσdLT =
0.525(14) = 8 units
Copyright ©2016 Pearson Education, Limited.
9-‹#›
62
Application 9.5
What is the desired reorder point R?
R = Average demand during lead time + Safety stock
R =
What is the total annual cost?
3(10) + 8 = 38 units
($12) + ($45) + 8($12) = $845.42
62
2
520
62
C =
Copyright ©2016 Pearson Education, Limited.
9-‹#›
63
Application 9.5
Suppose that the current policy is Q = 80 and R = 150. What will be the changes in average cycle inventory and safety stock if your EOQ and R values are implemented?
Reducing Q from 80 to 62
Cycle inventory reduction = 40 – 31 = 9 units
Safety stock reduction = 120 – 8 = 112 units
Reducing R from 150 to 38
Copyright ©2016 Pearson Education, Limited.
9-‹#›
64
Periodic Review System (P)
Fixed interval reorder system or periodic reorder system
Four of the original EOQ assumptions maintained
No constraints are placed on lot size
Holding and ordering costs
Independent demand
Lead times are certain and supply is known
Copyright ©2016 Pearson Education, Limited.
9-‹#›
65
Periodic Review System (P)
P
P
T
L
L
L
Protection interval
Time
On-hand inventory
IP3
IP1
IP2
Order
placed
Order
placed
Order
placed
Order
received
Order
received
Order
received
IP
IP
IP
OH
OH
Q1
Q2
Q3
Figure 9.13
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.8
Refer to Example 9.5
Suppose that the management want to use a Periodic Review System for the Sony TV sets. The first review is scheduled for the end of Day 2. All demands and receipts occur at the end of the day. Lead time is 5 Days and management has set T = 620 and P = 6 days.
Determine how much to order (Q) using a P System.
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.8
| Day | Demand | OH | SR | BO | IP | Q |
| 1 | 50 | |||||
| 2 | ||||||
| 3 | ||||||
| 4 | ||||||
| 5 | ||||||
| 6 | ||||||
| 7 |
400
340 before ordering
280
260 + 280 = 540
60
80
40
75
55
95
260
220
145
90 + 280 – 95 = 275
90
340
620 – 340 = 280 due Day 7
280
280
280
220 + 280 = 500
145 + 280 = 425
90 + 280 = 370
400
280 after
ordering
340 + 280 = 620 after ordering
270 + 0 = 275
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.8
| Day | Demand | OH | SR | BO | IP | Q |
| 8 | 50 | |||||
| 9 | ||||||
| 10 | ||||||
| 11 | ||||||
| 12 | ||||||
| 13 | ||||||
| 14 |
340 + 0 = 340 before ordering
395
150 + 395 = 545
45
30
50
60
40
50
150
100
40
40 + 395 – 40 = 395
345
180
620 – 225 = 395 due Day 13
395
395
100 + 395 = 495
40 + 395 = 435
395 + 0 = 395
225
345 + 275 = 620 after ordering
180 + 395 = 575
395
275 after
ordering
395 after
ordering
225 + 0 = 225 before ordering
225 + 395 = 620 after ordering
620 – 345 = 275 due Day 19
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.8
The P system requires more inventory for the same level of protection against stockouts or backorders.
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Periodic Review System
Selecting the time between reviews, choosing P and T
Selecting T when demand is variable and lead time is constant
IP covers demand over a protection interval of P + L
The average demand during the protection interval is d(P + L), or
T = d (P + L) + safety stock for protection interval
Safety stock = zσP + L , where σP + L =
Copyright ©2016 Pearson Education, Limited.
9-‹#›
71
Example 9.9
Again, let us return to the bird feeder example.
Recall that demand for the bird feeder is normally distributed with a mean of 18 units per week and a standard deviation in weekly demand of 5 units.
The lead time is 2 weeks, and the business operates 52 weeks per year. The Q system called for an EOQ of 75 units and a safety stock of 9 units for a cycle-service level of 90 percent.
What is the equivalent P system?
Answers are to be rounded to the nearest integer.
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.9
We first define D and then P. Here, P is the time between reviews, expressed in weeks because the data are expressed as demand per week:
D =
(18 units/week)(52 weeks/year) = 936 units
P = (52) =
EOQ
D
(52) = 4.2 or 4 weeks
75
936
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Example 9.9
We now find the standard deviation of demand over the protection interval (P + L) = 6:
For a 90 percent cycle-service level z = 1.28:
Safety stock = zσP + L =
1.28(12.25) = 15.68 or 16 units
We now solve for T:
= (18 units/week)(6 weeks) + 16 units = 124 units
T = Average demand during the protection interval + Safety stock
= d (P + L) + safety stock
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Application 9.6
The on-hand inventory is 10 units, and T is 400. There are no back orders, but one scheduled receipt of 200 units. Now is the time to review. How much should be reordered?
IP = OH + SR – BO
The decision is to order 190 units
= 10 + 200 – 0 = 210
T – IP =
400 – 210 = 190
Copyright ©2016 Pearson Education, Limited.
9-‹#›
75
Periodic Review System
Selecting the Target Inventory Level When Demand and Lead Time are Variable
Simulation
Systems Based on the P System
Single-Bin System
Optional Replenishment System
Calculating Total P System Costs
C = (H) + (S) + HzσP + L
dP
2
D
dP
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Periodic Review System
Advantages of the P System
It is convenient because replenishments are made at fixed intervals.
Orders for multiple items from the same supplier can be combined into a single purchase order.
The inventory position needs to be known only when a review is made (not continuously).
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Application 9.7
Return to Discount Appliance Store (Application 9.5), but now use the P system for the item.
Previous information:
Demand = 10 units/wk (assume 52 weeks per year) = 520
EOQ = 62 units (with reorder point system)
Lead time (L) = 3 weeks
Standard deviation in weekly demand = 8 units
z = 0.525 (for cycle-service level of 70%)
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Application 9.7
Reorder interval P, if you make the average lot size using the Periodic Review System approximate the EOQ.
P = (EOQ/D)(52) =
(62/520)(52) = 6.2 or 6 weeks
Safety stock
Target inventory
T = 10(6 + 3) + 13 = 103 units
T = d(P + L) + safety stock for protection interval
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Application 9.7
Total cost
C = (H) + (S) + HzσP + L
dP
2
= ($12) + ($45) + (13)($12) = $906.00
10(6)
2
520
10(6)
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 1
A distribution center experiences an average weekly demand of 50 units for one of its items.
The product is valued at $650 per unit. Average inbound shipments from the factory warehouse average 350 units.
Average lead time (including ordering delays and transit time) is 2 weeks.
The distribution center operates 52 weeks per year; it carries a 1-week supply of inventory as safety stock and no anticipation inventory.
What is the value of the average aggregate inventory being held by the distribution center?
Copyright ©2016 Pearson Education, Limited.
9-‹#›
81
Solved Problem 1
| Type of Inventory | Calculation of Average Inventory | |
| Cycle | ||
| Safety stock | ||
| Anticipation | ||
| Pipeline | ||
1-week supply
None
Q
2
=
350
2
= 175 units
= 50 units
dL = (50 units/week)(2 weeks)
Average aggregate inventory
Value of aggregate inventory
= 100 units
= 325 units
= $650(325)
= $211,250
Copyright ©2016 Pearson Education, Limited.
9-‹#›
82
Solved Problem 2
Booker’s Book Bindery divides SKUs into three classes, according to their dollar usage. Calculate the usage values of the following SKUs and determine which is most likely to be classified as class A.
| SKU Number | Description | Quantity Used per Year | Unit Value ($) | ||
| 1 | Boxes | 500 | 3.00 | ||
| 2 | Cardboard (square feet) | 18,000 | 0.02 | ||
| 3 | Cover stock | 10,000 | 0.75 | ||
| 4 | Glue (gallons) | 75 | 40.00 | ||
| 5 | Inside covers | 20,000 | 0.05 | ||
| 6 | Reinforcing tape (meters) | 3,000 | 0.15 | ||
| 7 | Signatures | 150,000 | 0.45 |
Copyright ©2016 Pearson Education, Limited.
9-‹#›
83
Solved Problem 2
| SKU Number | Description | Quantity Used per Year | Unit Value ($) | Annual Dollar Usage ($) | ||||||
| 1 | Boxes | 500 | | 3.00 | = | 1,500 | ||||
| 2 | Cardboard (square feet) | 18,000 | | 0.02 | = | 360 | ||||
| 3 | Cover stock | 10,000 | | 0.75 | = | 7,500 | ||||
| 4 | Glue (gallons) | 75 | | 40.00 | = | 3,000 | ||||
| 5 | Inside covers | 20,000 | | 0.05 | = | 1,000 | ||||
| 6 | Reinforcing tape (meters) | 3,000 | | 0.15 | = | 450 | ||||
| 7 | Signatures | 150,000 | | 0.45 | = | 67,500 | ||||
| Total | 81,310 |
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 2
Figure 9.14
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 2
Figure 9.14
Copyright ©2016 Pearson Education, Limited.
9-‹#›
86
Solved Problem 3
Nelson’s Hardware Store stocks a 19.2 volt cordless drill that is a popular seller. Annual demand is 5,000 units, the ordering cost is $15, and the inventory holding cost is $4/unit/year.
a. What is the economic order quantity?
b. What is the total annual cost for this inventory item?
a. The order quantity is
EOQ = =
2DS
H
2(5,000)($15)
$4
= 37,500 = 193.65 or 194 drills
b. The total annual cost is
C = (H) + (S) =
Q
2
D
Q
($4) + ($15) = $774.60
194
2
5,000
194
Copyright ©2016 Pearson Education, Limited.
9-‹#›
87
Solved Problem 4
A regional distributor purchases discontinued appliances from various suppliers and then sells them on demand to retailers in the region. The distributor operates 5 days per week, 52 weeks per year. Only when it is open for business can orders be received. The following data are estimated for the countertop mixer:
Copyright ©2016 Pearson Education, Limited.
9-‹#›
88
Solved Problem 4
What order quantity Q, and reorder point, R, should be used?
What is the total annual cost of the system?
If on-hand inventory is 40 units, one open order for 440 mixers is pending, and no backorders exist, should a new order be placed?
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 4
a. Annual demand is
The order quantity is
D = (5 days/week)(52 weeks/year)(100 mixers/day)
= 26,000 mixers/year
EOQ = =
2DS
H
2(26,000)($35)
$9.40
= 193,167 = 440.02 or 440 mixers
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 4
The standard deviation of the demand during lead time distribution is
A 92 percent cycle-service level corresponds to z = 1.41
σdLT = σd L =
30 3 = 51.96
Safety stock = zσdLT =
1.41(51.96 mixers) = 73.26 or 73 mixers
Reorder point (R) = Average demand during lead time + Safety stock
= 300 mixers + 73 mixers = 373 mixers
With a continuous review system, Q = 440 and R = 373
100(3) = 300 mixers
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 4
b. The total annual cost for the Q systems is
C = (H) + (S) + (H)(Safety stock)
Q
2
D
Q
C = ($9.40) + ($35) + ($9.40)(73) = $4,822.38
440
2
26,000
440
c. Inventory position = On-hand inventory + Scheduled receipts – Backorders
IP = OH + SR – BO =
40 + 440 – 0 = 480 mixers
Because IP (480) exceeds R (373), do not place a new order
Copyright ©2016 Pearson Education, Limited.
9-‹#›
92
Solved Problem 5
Suppose that a periodic review (P) system is used at the distributor in Solved Problem 4, but otherwise the data are the same.
a. Calculate the P (in workdays, rounded to the nearest day) that gives approximately the same number of orders per year as the EOQ.
b. What is the target inventory level, T? Compare the P system to the Q system in Solved Problem 4.
c. What is the total annual cost of the P system?
d. It is time to review the item. On-hand inventory is 40 mixers; receipt of 440 mixers is scheduled, and no backorders exist. How much should be reordered?
Copyright ©2016 Pearson Education, Limited.
9-‹#›
93
Solved Problem 5
a. The time between orders is
P = (260 days/year) =
EOQ
D
(260) = 4.4 or 4 days
440
26,000
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 5
The OM Solver data below shows that T = 812 and safety stock = (1.41)(79.37) = 111.91 or about 112 mixers.
The corresponding Q system for the counter-top mixer requires less safety stock.
Figure 9.15
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 5
c. The total annual cost of the P system is
C = (H) + (S) + (H)(Safety stock)
C = ($9.40) + ($35) + ($9.40)(1.41)(79.37)
100(4)
2
26,000
100(4)
= $5,207.80
d. Inventory position is the amount on hand plus scheduled receipts minus backorders, or
IP = OH + SR – BO =
40 + 440 – 0 = 480 mixers
The order quantity is the target inventory level minus the inventory position, or
Q = T – IP =
An order for 332 mixers should be placed.
812 mixers – 480 mixers = 332 mixers
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 6
Grey Wolf Lodge is a popular 500-room hotel in the North Woods. Managers need to keep close tabs on all room service items, including a special pine-scented bar soap. The daily demand for the soap is 275 bars, with a standard deviation of 30 bars. Ordering cost is $10 and the inventory holding cost is $0.30/bar/year. The lead time from the supplier is 5 days, with a standard deviation of 1 day. The lodge is open 365 days a year.
a. What is the economic order quantity for the bar of soap?
b. What should the reorder point be for the bar of soap if management wants to have a 99 percent cycle-service level?
c. What is the total annual cost for the bar of soap, assuming a Q system will be used?
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 6
a. We have D = (275)(365) = 100,375 bars of soap; S = $10; and H = $0.30. The EOQ for the bar of soap is
EOQ = =
2DS
H
2(100,375)($10)
$0.30
= 6,691,666.7 = 2,586.83 or 2,587 bars
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 6
(5)(30)2 + (275)2(1)2 = 283.06 bars
Safety stock = zσdLT =
(2.33)(283.06) = 659.53 or 660 bars
(275)(5) + 660 = 2,035 bars
Copyright ©2016 Pearson Education, Limited.
9-‹#›
Solved Problem 6
c. The total annual cost for the Q system is
C = (H) + (S) + (H)(Safety stock)
Q
2
D
Q
C = ($0.30) + ($10) + ($0.30)(660) = $974.05
2,587
2
100,375
2,587
Copyright ©2016 Pearson Education, Limited.
9-‹#›
L
P
d
+
s
(
)
(
)
units
13
or
12.6
3
6
8
0.525
=
+
=