The grAde

HunterPeng
case.doc

Court Denies Subcontractor’s

Constructive Acceleration Claim

O

n any troubled or delayed construction project, work

acceleration can occur in one of two ways. In the first,

the owner or contractor can affirmatively direct that the

remaining work be performed in a compressed period and agree

to cover the resultant costs. In the second, through what is called

constructive acceleration, the party that directs the acceleration

must cover the resultant costs even if it does not consider itself

responsible for those costs. In a case of first impression, the Seventh

Circuit Court of Appeals recently had occasion to consider a sub

-

contractor’s constructive acceleration claim.

The facts in this case,

Murdock & Sons Construction Co., Inc. v. Goheen

General Con

struction,

arose from the construction of a maximum secu

-

rity prison near Terre Haute, Indiana. Goheen General Construc

-

tion, Inc., was awarded the prime contract by the state for the prison

housing. Construction costs were expected to

be approximately $6,970,000. Goheen subcon

-

tracted the masonry work to the lowest bidder,

Murdock & Sons, as a result of a fixed-price

bid of $1,629,825. The other two masonry bids

came in at $2,747,000 and $2,475,000 and did

not include a price for rebar.

The subcontract called for the construc

-

tion of 288 cells having very dense masonry

walls. Each wall consisted of individual

cement blocks arranged in a “large honey

-

comb fashion.” The blocks were reinforced

with both horizontal and vertical rebar every

8 in. (20.3 cm). The specifications called

for continuous grouting with cement rather

than mortar. They also required the extensive

placement of embedments, necessitating that

a significant number of cuts be made in the

blocks. Although Murdock was an experienced masonry subcon

-

tractor, it had no experience with the amount of reinforcement

required on this project.

To make matters more difficult, the union masons Murdock

was required to use did not keep pace with the projections set forth

in its bid. While a mason can typically lay 200 blocks a day on a

typical project, Murdock had estimated that, given the difficulty

of this particular project, the masons would lay only 150 blocks a

day. Despite its estimate, however, Murdock’s masons were laying

just 50 blocks a day from the beginning of the project. Even though

Murdock dismissed slow workers, increased its crew from 35 to

83, provided additional equipment, and modified the construction

process, it still fell behind. The project experienced serious delays

and cost overruns, and the state was unwilling to grant Murdock

an extension. Murdock eventually walked off the job and filed suit

against the state and the general contractor, lodging a construction

acceleration claim. After the federal court at the district level ruled

against Murdock, the company took its case to the Seventh Circuit

Court of Appeals.

The appellate court began its analysis by noting that there was

no Indiana case law recognizing or applying a constructive accel

-

er at ion cl a i m . O n t he ba si s of dec i sion s i n ot her ju r i sd ic t ion s , how

-

ever, the court stated that it was a viable claim. The court set forth

the five elements for proving a constructive acceleration claim: (1)

the contractor experienced the delay entitling it to an extension;

(2) the contractor properly requested the extension; (3) the project

owner failed to grant or refused to grant the extension; (4) the proj

-

ect owner demanded that the project be completed by the original

completion date despite the excusable delay; and (5) the contractor

accelerated the work in order to complete the project by the origi

-

nal completion date and incurred added costs as a result.

Although the district court determined that Murdock could not

show that it provided written notice of the delays in a timely fashion, the

appellate court assumed that the formal notice requirement had been

waived by the general contractor. The latter

court explained, however, that Murdock’s delay

claim was ultimately without merit because the

firm had not established that the “slower than

anticipated pace of the masons” was beyond its

control. In fact, Murdock testified that it had

“no clue, really” as to the cause of the productiv

-

ity problem. And although it alleged that there

had been an organized work slowdown by the

masons, it was unable, beyond mere speculation,

to substantiate the charge. The court concluded

that Murdock’s estimate “grossly understated”

the time and effort required to perform this kind

of unique masonry work and that such a risk

should fall “squarely” on the subcontractor. The

court also rejected Murdock’s argument that a

force majeure event had occurred, noting that

Murdock had knowingly taken the risk of its

own productivity and that the force majeure clause was not a “buffer”

against the normal risks of contracting.

Construction litigators may find it difficult to believe that a party

would invest such a substantial amount of time and money in a fed

-

eral trial and an appeal without sufficient proof of its constructive

acceleration claim. Here, the court even quoted from Murdock’s

opening brief, which stated that “the reason for the [mason work]

slowdown was never determined.” At trial, Murdock’s witnesses

conceded they could only speculate as to why the productivity was

so low. The court asked how it was to determine the cause if the

claimant had not been able to do so. For those about to take a posi

-

tion in a lawsuit, this question is worth remembering.