case study
11.2.1 Problem Statement
A contractor working on an outdoor construction project in a coastal area
is reviewing progress on August l. If normal progress is maintained and no
time is last due to hurricanes, the job will be completed on August 31. However,
due to the poor weather conditions in the area after August 16, there will be
only a 40 percent chance of finishing on time. It is estaimated that there is a
50 percent chance of a minor hurricane, which will cause a delay of 5 days, and
a 10 percent chance of a major hurricane, which will cause a delay of 10 days.
It must be decided now whether to start a crash program on August 2 at an addi-
tional cost of $75 per day and finish the project on August 16. As an alternative,
the normal schedule can be maintained and progress reviewed on August 31.
At that time if a hurricane has occurred and the project is delayed, there will be
a choice of accepting the delay at a certain penalty cost or trying to crash the
program then. The penalty cost for delay of completion will be $400 per day
for the first 5 days and $600 per day for the second 5 days. The additional cost
of a crash program after the hurricane will be $200 per day. The total addi-
tional cost is computed as the sum of delay penalty cost and crash cost.
It is also estimated that the possible results (outcomes) of a crash program
after a minor hurricane causes a 5-day delay will be as follows:
Crash Program
Result
Save 1 day
Save 2 days
Save 3 days
Probability Total Additional Cost
0.5 $1600 + 800 = $2400
0.3 $1200 + 600 $1800
0.2 $800 + 400 $1200
The possible results of a crash program after a major hurricane causes a
10-day delay is estimated as follows :
Crash Program
Result
Save 2 days
Save 3 days
Save 4 days
Probability Total Additional Cost
0.7 $(2000 + 1800) + 1600 $5400
0.2 $(2000 + 1200) + 1400 $4600
0.1 $(2000 + 600) + 1200 = $3800