Homework 2

ac1227
CalamariProject.pdf

© 2015 Tom Kendrick Project Risk Management Page 5

Calamari Printer Product Description: The Calamari is a tiny, self-propelled, single-color printer intended for printing anywhere. Using an infrared interface compatible with standard lap-tops, PDA’s, or other computers, the Calamari will print on any size rectangular paper (or other suitable medium) sitting on a flat, smooth, level surface. The Calamari will take five to ten seconds to initialize by determining the positions of all four corners. A 300 dot per inch print of text and graphics on letter (or A4) paper will take under one minute to complete. A set of four AA-size batteries will power the Calamari for at least one hour of printing, and the device, including batteries, will weigh 500 grams (~ ½ lb.) or less. Project Objective: Develop Calamari and release the product in eight months (by September 30, 20xx) with 12 full-time contributors. Priorities: Least flexible (Constrain) Schedule Moderately flexible (Optimize) Scope Most flexible (Accept) Resources Roles:

• Research and Development (R&D): Develop the product and create a working prototype.

• Learning Products (LP): Complete training, support and reference materials.

• Marketing (Mrk): Assess market situation and user needs, recommend solution, launch product.

• Manufacturing (Mfg): Set up for and produce the product in quantity.

• Finance (Fin): Provide financial analysis of costs, pricing, projected profit. Using the "PERT" chart supplied and the information below, fill in pessimistic estimates and, if you wish, optimistic estimates for the project tasks. The estimates already entered in the Gantt and PERT charts are "most likely". 1. The tasks assigned to Finance are all things they have done before and their

estimates are usually accurate to within a day. 2. There is a lot of data supporting the tasks of printing documents and preparing

marketing materials. These estimates are considered very accurate. 3. R&D is well-staffed with experienced people. You are confident of all the

Development task estimates, plus or minus 5%, except for electronic design. This project requires known software and controls, with which the team is very familiar, but miniaturization of the hardware is a new challenge. This work may take as much as an extra couple of weeks beyond the estimate given.

© 2015 Tom Kendrick Project Risk Management Page 6

4. Learning Products people are currently very busy completing work for the

“TVDinner” product, which is currently the highest priority project. Their estimates assume no higher priority work will conflict with Calamari. Even so, the tasks assigned to them are very unlikely to be completed more than a day early, and this group has a number of very inexperienced people. Slipping Development Phase LP estimates by as much as a third is likely, but Investigation Phase estimates seem fine.

5. Marketing has already started the needed research and has made a firm

commitment to completing all market research and other Investigation-phase tasks on time. Market research may be completed a week early.

6. All functional areas understand how important the review of LP output is to the

success of Calamari, and although no one has promised to take less time than the estimate, everyone believes the time for this will be sufficient.

7. Manufacturing reports that they expect to have no difficulty in moving Calamari

into production. Several engineers from a division experienced in similar production are assigned to work on Calamari. The only estimate that they are not too confident of is the time for ordering parts, as new suppliers will be used for the infrared interface hardware. They think this task might take as much as an additional three weeks. All the other estimates for the project seem accurate within a day or so.

8. The mini digital stepping motor research is the only task assigned to R&D in the

Investigation phase that seems risky. This may require an extra week, but the other estimates are good.

9. Marketing expects several other projects to start up during the Development

phase of Calamari. They report that their tasks of writing the marketing plan and product launch will not be finished earlier than estimated and both of these tasks may take up to two extra weeks due to higher priority conflicts.

Given this information, identify the tasks off the critical path that are most likely to cause project slippage. Consider any sequences of tasks that could cause the Manufacturing Release (MR) milestone to slip. Document the risky tasks, and determine a worst case Calamari schedule. Provide a one page discussion on your findings.

© 2015 Tom Kendrick Project Risk Management Page 7

Calamari Project Left side (some assembly required)

10

40

20 5

20

65

50

5

15 25

40

10

35

51

30

524

15

30

10

Start

17. Write

Software 23. Assemble

Prototype

13. Finalize

Specifications

8. Do High-Level

Design 4. Investigate

Feasibility

14.

Business

Decision

3. Hold Kick-off

Meeting

6. Get Get Infrared

Specs. From Austin

7. Locate Mini

Digital Stepping

Motor

16. Do Electronic

Design

18. Complete

Mechanical Design

9. Do Design for

Manufacturability

Requirements

10. Define User

Interface

Requirements

5. Do Market

Research

11. Recommend

Solution and

Selling Price

12. Forecast

Demand

19. Write

Marketing Plan

24. Prepare

Marketing

Materials

20. Write

Documentation

21. Develop

Training

25. Review and

Approve Docs,

Training, Support

22. Write

Support Plan

© 2015 Tom Kendrick Project Risk Management Page 8

Calamari Project Right side (some assembly required)

10

10

30

25

10

30

28. Launch

Product

30

20 20

10

10

105

5

39.

Manuf.

Release

41. End

33. Finalize

Design

Documents

35. Prepare

for Pilot

Production

36. Produce and

Test Pilot Run

37. Fix Problems,

Set Up for

Manufacturing

38. Ramp-up30. Fix

Defects 26. Test

Prototype

34. Order

Parts

27. Estimate

Manufacturing

Cost

40. Close

Project; Do

Retrospective

31. Do Financial

Analysis

29. Finalize Docs,

Training and

Support

32. Print

Documents

(Predecessor

Task 25)

(Predecessor

Task 24)

(Predecessor

Task 24)

(Predecessor

Task 23)

(Predecessor

Task 23)

© 2015 Tom Kendrick Project Risk Management Page 9

© 2015 Tom Kendrick Project Risk Management Page 10

© 2015 Tom Kendrick Project Risk Management Page 11

© 2015 Tom Kendrick Project Risk Management Page 12

Calamari Project

Research and

Develop

Calamari

Market

Calamari

Create Calamari

Learning Products

Manufacture

Calamari

31. Do Financial

Analysis for

Calamari

5

28. Launch

Product

30

28. Launch

Product

3010

33. Finalize

Design

Documents

10

33. Finalize

Design

Documents

30

35. Prepare

for Pilot

Production

30

35. Prepare

for Pilot

Production

10

36. Produce and

Test Pilot Run

10

36. Produce and

Test Pilot Run

20

37. Fix Problems,

Set Up for

Manufacturing

20

37. Fix Problems,

Set Up for

Manufacturing

20

38. Ramp-up

20

38. Ramp-up

10

30. Fix

Defects

10

30. Fix

Defects

5

26. Test

Prototype

5

26. Test

Prototype

10

34. Order

Parts

10

34. Order

Parts

10

27. Estimate

Manufacturing

Cost

10

27. Estimate

Manufacturing

Cost

10

40. Close

Project; Do

Retrospective

10

40. Close

Project; Do

Retrospective

25

29. Finalize Docs,

Training and

Support

25

29. Finalize Docs,

Training and

Support

30

32. Print

Documents

30

32. Print

Documents

40

17. Write

Software

40

17. Write

Software

5

23. Assemble

Prototype

5

23. Assemble

Prototype

5

13. Finalize

Specifications

5

13. Finalize

Specifications

24

8. Do High-Level

Design

24

8. Do High-Level

Design

30

4. Investigate

Feasibility

30

4. Investigate

Feasibility

1

3. Hold Kick-off

Meeting

1

3. Hold Kick-off

Meeting

10

6. Get Get Infrared

Specs. From Austin

10

6. Get Get Infrared

Specs. From Austin

15

7. Locate Mini

Digital Stepping

Motor

15

7. Locate Mini

Digital Stepping

Motor

30

16. Do Electronic

Design

30

16. Do Electronic

Design

35

18. Complete

Mechanical Design

35

18. Complete

Mechanical Design

10

9. Do Design for

Manufacturability

Requirements

10

9. Do Design for

Manufacturability

Requirements

20

10. Define User

Interface

Requirements

20

10. Define User

Interface

Requirements

20

5. Do Market

Research

20

5. Do Market

Research

5

11. Recommend

Solution and

Selling Price

5

11. Recommend

Solution and

Selling Price

5

12. Forecast

Demand

5

12. Forecast

Demand

15

19. Write

Marketing Plan

15

19. Write

Marketing Plan

25

24. Prepare

Marketing

Materials

25

24. Prepare

Marketing

Materials

65

20. Write

Documentation

65

20. Write

Documentation

50

21. Develop

Training

50

21. Develop

Training

10

25. Review and

Approve Docs,

Training, Support

10

25. Review and

Approve Docs,

Training, Support

40

22. Write

Support Plan

40

22. Write

Support Plan