Project management assignment
Sheet1
| Days | Tasks Done | Remaining | Ideal Done Per Day | Ideal Velocity | |
| Initial Value | 0 | 0 | 200 | 10 | 200 |
| 1 | 0 | 200 | 10 | 190 | |
| 2 | 5 | 195 | 10 | 180 | |
| 3 | 3 | 192 | 10 | 170 | |
| 4 | 12 | 180 | 10 | 160 | |
| 5 | 17 | 163 | 10 | 150 | |
| 6 | 9 | 154 | 10 | 140 | |
| 7 | 8 | 146 | 10 | 130 | |
| 8 | 13 | 133 | 10 | 120 | |
| 9 | 15 | 118 | 10 | 110 | |
| 10 | 6 | 112 | 10 | 100 | |
| 11 | 18 | 94 | 10 | 90 | |
| 12 | 15 | 79 | 10 | 80 | |
| 13 | 16 | 63 | 10 | 70 | |
| 14 | 11 | 52 | 10 | 60 | |
| 15 | 8 | 44 | 10 | 50 | |
| 16 | 13 | 31 | 10 | 40 | |
| 17 | 9 | 22 | 10 | 30 | |
| 18 | 6 | 16 | 10 | 20 | |
| 19 | 10 | 6 | 10 | 10 | |
| 20 | 6 | 0 | 10 | 0 |
Sprint 1 Burndown Chart
Remaining Initial Value 200 200 195 192 180 163 154 146 133 118 112 94 79 63 52 44 31 22 16 6 0 Ideal Velocity Initial Value 200 190 180 170 160 150 140 130 120 110 100 90 80 70 60 50 40 30 20 10 0