const cost & Bid project 6

moore05
Assignment6.pdf

WEEK 6

COURSE: CONSTRUCTION COST ANALYSIS AND BIDDING

LEVEL: GRADUATE

ASSIGNMENT # 6

TOTAL POINTS: 100

LEARNING OBJECTIVES:

After successfully completing this assignment, students will be able to:

• Prepare an estimate for studs and drywall

• Estimate cost of electrical work

Note: Your work should be professionally presented and all the steps for calculations must

be included.

Q1.

a) Determine the number of steel studs needed for the tenant finish shown in Figure below. The exterior walls are existing. The studs are spaced 16 inches on center. Add two studs

for each door and each intersection.

b) Also, determine the number of 4-foot-wide by 8-foot-high sheets of drywall needed for the tenant finish in Figure below. The walls are 8 feet high. The exterior walls need

drywall on the interior side only. The interior walls need drywall on both sides. Add 5

percent waste. 60points

WEEK 6

Q2.

Determine the estimated cost of the electrical for the residence shown in Figure below using the

following assembly costs. The associated wiring is included in the cost of each assembly. What

is the fixture allowance for the residence?

Switches = $50 Duplex outlets = $50 GFCI outlets = $60 Light fixtures (includes $30

fixture allowance) = $80 Main service = $1,000

40 points

Quote of the Week: “Enthusiasm is the electricity of life. How do you get it? You act

enthusiastic until you make it a habit.”― Gordon Parks