business_case_financials_assignment.xlsx

Sheet1

Financial Analysis for Project Name
Created by: Date:
Note: Change the inputs, shown in green below (i.e. interest rate, number of years, costs, and benefits). Be sure to double-check the formulas based on the inputs.
Discount rate 8.00%
Assume the project is completed in Year 0 Year
0 1 2 3 Total
Costs 140,000 40,000 40,000 40,000
Discount factor 1.00 0.93 0.86 0.79
Discounted costs 140,000 37,200 34,400 31,600 243,200
Benefits 0 200,000 200,000 200,000
Discount factor 1.00 0.93 0.86 0.79
Discounted benefits 0 186,000 172,000 158,000 516,000
Discounted benefits - costs (140,000) 148,800 137,600 126,400 272,800 NPV
Cumulative benefits - costs (140,000) 8,800 146,400 272,800
ROI 112%
Payback in Year 1
Assumptions
Enter assumptions here

Sheet2

Financial Analysis for Project Name
Created by: Date:
Note: Change the inputs, shown in green below (i.e. interest rate, number of years, costs, and benefits). Be sure to double-check the formulas based on the inputs.
Discount rate 8.00%
Assume the project is completed in Year 0 Year
0 1 2 3 4 5 Total
Costs 50,000 0 0 0 0 0
Discount factor 1.00 0.93 0.86 0.79 0.74 0.68
Discounted costs 50,000 - 0 - 0 - 0 50,000
Benefits 0 10,000 15,000 20,000 20,000 20,000
Discount factor 1.00 0.93 0.86 0.79 0.74 0.68
Discounted benefits 0 9,300 12,900 15,800 14,800 13,600 66,400
Discounted benefits - costs (50,000) 9,300 12,900 15,800 14,800 13,600 16,400 NPV
Cumulative benefits - costs (50,000) (40,700) (27,800) (12,000) 2,800 16,400
ROI 33%
Payback in Year 1
Assumptions
Enter assumptions here

Sheet3

cost_estimate.xlsx

Sheet1

XXX Project Cost Estimate
Prepared by: Date:
Note: Change the WBS items and other entries to meet your project needs. This data is from Figure 7-1 of Schwalbe's text
Information Technology Project Management, Fourth Edition. Also make sure the formulas work properly based on the data you enter.
# Units/Hrs. Cost/Unit/Hr. Subtotals WBS Level 1 Totals % of Total
WBS Items
1. Project Management $306,300 20%
1.1 Project manager 960 $100 $96,000
1.2 Project team members 1920 $75 $144,000
Contractors (10% of software development and testing) $66,300
2. Hardware $76,000 5%
2.1  Handheld devices 100 $600 $60,000
2.2  Servers 4 $4,000 $16,000
3. Software $614,000 40%
3.1 Licensed software 100 $200 $20,000
3.2 Software development* $594,000
4. Testing (10% of total hardware and software costs) $69,000 $69,000 5%
5. Training and Support $202,400 13%
5.1 Trainee cost 100 $500 $50,000
5.2 Travel cost 12 $700 $8,400
5.3 Project team members 1920 $75 $144,000
6. Reserves (20% of total estimate) $253,540 $253,540 17%
Total project cost estimate $1,521,240
* See software development estimate

Sheet2

* Software development
Contractor labor estimate 3000 $150 $450,000
Project team member estimate 1920 $75 $144,000
Total labor estimate $594,000
Function point estimate Quantity Conversion Factor Function Points
External inputs 10 4 40
External interface files 3 7 21
External outputs 3 5 15
External queries 3 4 12
Logical internal tables 6 10 60
Total function points 148
Java 2 languange equivalency value 46
Source lines of code (SLOC) estimate 6,808
Productivity *KSLOC^Penalty (person months) 30.27
Total labor hours (160 hours/month) 4,842.55
Cost/labor hour ($120/hour) $120
Total software development estimate 581,106