| Activity I | |||
| Activity | Description | Predecessors | Duration (Days) |
| A | Site selection | None | 4 |
| B | Buy concessions | A | 4 |
| C | Rent facilities | A | 2 |
| D | Build stands | A | 5 |
| E | Generator & wiring installation | C | 2 |
| F | Security | B | 4 |
| G | Lighting installation | E | 2 |
| H | Sound system installation | E, F | 2 |
| I | Stage construction | D | 3 |
| J | Tear down | G, H, I | 4 |
| Activity II | |||
| Activity | Expected Duration | Predecessors | |
| A | 4 days | — | |
| B | 9 days | A | |
| C | 11 days | A | |
| D | 5 days | B | |
| E | 3 days | B | |
| F | 7 days | C | |
| G | 3 days | D, F | |
| H | 2 days | E, G | |
| I | 1 day | H |