Activity- 10 Exe Project
Given the following information, answer the questions about this project:
|
Activity |
Expected Duration |
Predecessors |
|
A |
4 days |
— |
|
B |
9 days |
A |
|
C |
11 days |
A |
|
D |
5 days |
B |
|
E |
3 days |
B |
|
F |
7 days |
C |
|
G |
3 days |
D, F |
|
H |
2 days |
E, G |
|
I |
1 day |
H |
1. Draw the network as a Gantt chart.
2. What is the critical path? Which activities have slack time?
3. What would happen if activities B and D each took 5 extra days to complete instead of the expected duration? How would the critical path change?