For Crane Company, units to be produced are 4,000 in quarter 1 and 5,600 in quarter 2. It takes 1.6 hours to make a �nished unit, and the expected hourly wage rate is $14 per hour.
Prepare a direct labor budget by quarters for the 6 months ending June 30, 2022.
CRANE COMPANY Direct Labor Budget
Quarter
1 2 Six Months
$ $