Given in the following table are the tasks necessary for final assembly of a hospital bed, the length of time needed to perform each task, and the operations that must be completed prior to subsequent operations. Construct a precedence diagram and balance the assembly line for a desired cycle time of 14 minutes. Draw a schematic diagram of the balanced line. How many beds can actually be assembled in an eight-hour period?
Element | Precedence | Time (min) |
A | None | 4 |
B | None | 5 |
C | None | 8 |
D | A | 4 |
E | A, B | 3 |
F | B | 3 |
G | D, E | 5 |
H | F | 7 |
I | G, H | 1 |
J | I | 7 |
K | C, J | 4 |