Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2013 and was completed in 2014. Data relating to the contract are summarized below: |
| 2013 | 2014 | |||||
| Costs incurred during the year | $ | 300,000 | $ | 1,575,000 | ||
| Estimated costs to complete as of 12/31 | 1,200,000 | 0 | ||||
| Billings during the year | 380,000 | 1,620,000 | ||||
| Cash collections during the year | 250,000 | 1,750,000 | ||||
| Required: | |||||||
| 1. | Compute the amount of gross profit or loss to be recognized in 2013 and 2014 using the percentage-of-completion method. | ||||||
| |||||||