Multiple choice
1. The HMO Act of 1973 was a landmark piece of federal legislation that:
A: caused members of HMOs to grow because of the availability of federal money
B: actually reduced the number of HMOs because the guidelines were so strict they were too hard to comply with
C: states did not want to comply with because it cost the money
D: essentially did away with indemnity insurance
2. _________________ is an amount the contractor may want to include to cover the unexpected items.
A: overhead
B: contingency
C: labor
D: profits
3. The amount of time that a particular activity can be delayed without delaying the succeeding activities earliest start time is:
A: total slack
B: free slack
C: scheduling
D: what-if period
4. The equation for calculating an activity’s latest start time is LS=________________
A: LF-duration estimate
B: LF-actual finish
C: early finsh+duration estimate
D: late finish+duration estimate
12 years ago
Purchase the answer to view it
- 5.doc