Lewis Noodles has the following cooking procedures. You will need to compute the cycle time per day and the minimum number of workstations assuming eight working hours a day and 500 units need to be made per day.

 

      TASK    DESCRIPTION              TASK TIME    PRECEDING TASK

 

A         Cook vegetables          2 minutes

 

B         Cut noodles                 1 minute          A

 

C         Cook noodles               5 minutes        B

 

D         Cook meat                   3 minutes         C

 

E          Mix ingredients           1 minute          D

 

           --------------

                                                            12 minutes

 