excel
Assignment:
This exercise consists of a list of tasks for a home yard project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors. Set a start date for your project of April 30, 2013. Enter the following tasks, including the duration, where specified. Tasks with unspecified duration are summary tasks and the rest are sub-tasks. When completed save the file and submit the file via Canvas.
ID: Task List: Duration: Predecessors:
1 Preparation
2 Get trash bags 5 min
3 Pick up trash 15 min 2
4 Put gas in the equipment 5 min
5 Get the hedge clippers 5 min
6 Do the work
7 Trim weeds 30 min 3,4
8 Mow front yard 45 min 3,4
9 Edge sidewalk 15 min 3,4
10 Trim Hedge 30 min 5
11 Mow back yard 30 min 8
12 Clean up
13 Bag grass 30 min 7,9,10,11
14 Bundle trash 15 min 7,9,10,11
15 Haul trash 45 min 13,14
13 years ago 12
Purchase the answer to view it
- project.mpp
- DUE NOW 300 words
- What were the economic rewards that the Assyrian, Hittites, and Alexander's Empire got?
- Help
- Accounting
- what was the conservative resurgence in the mid 1900s?
- Graph quadrilateral ABCD. Then determin the most precise name for each quadrilateral. A (0,5) B (-5,0) C (0,-5) D (5,0)
- geometry assignment help needed fast!
- I need help with a spanish two assignment ASAP- will pay!
- Problem 3-25 Comprehensive cycle problem: Perpetual system At the beginning of 2012, the Jeater Company had the following balances in...
- the ratio of the biomass of water plants to the biomass of insects is 5:1 calculate the ratio of the biomass...