can you help me agian
Resource Evaluation
Produce and complete a a Gantt Chart using MS Project software.
- Using the Table below enter the information into MS Project software. Assume that each resource has been assigned to the project activity on a full-time (8 hours /day or 40 hours per week) basis
| Activity | Duration | Predecessors | Resource Assigned |
| A. User Survey | 4 | None | Gail Wilkins |
| B. Coding | 12 | A | Tom Hodges |
| C. Debugging | 5 | B | Wilson Pitts |
| D. Design Interface | 6 | A,C | Sue Ryan |
| E. Develop Training | 5 | D | Reed Taylor |
Include a title page and adhere to the Publication Manual of the American Psycholgical Association (APA), (6th ed., 2nd printing) when writing and submitting assignments and papers.