The Baxter Corporation has the following budgeted and actual results.
The Baxter Corporation has the following budgeted and actual results.
Budgeted data Actual results
Unit sales35,000 Unit sales36,000
Unit production35,000 Unit production37,000
Fixed overhead Fixed overhead
Supervision $25,000 Supervision $23,500
Depreciation $40,000 Depreciation $40,000
Rent $20,000 Rent $20,000
Variable costs per unitVariable costs
Direct materials $25.00 Direct materials $900,000
Direct labor $26.00 Direct labor $950,000
Supplies $0.25 Supplies $9,000
Indirect labor $1.30 Indirect labor $50,000
Electricity $0.20 Electricity $7,500
Required:
Prepare a performance report for all costs, showing flexible budget variances (indicate F or U).