Answer the following question

z.doud

6. (TCO F) Analyze and compare the performance of the following two projects in terms of cost, schedule, and efficiency. Make sure to show your calculations and analyze and explain the results. (Note: Providing just numbers will earn you only partial credit.)

Project A: The EV is $92,000, and the actual cost is $175,000. The PV is $173,000. (15 points)

Project B: The EV is $68,000, and the actual cost is $69,000. The PV is $71,000. (15 points)
 (Points : 30)