2 Machine flow
14.
The times required to complete each of eight jobs in a two-machine flow shop are shown in the table that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B. |
TIME (hours) | ||
| Job | Machine A | Machine B |
| a | 16 | 5 |
| b | 3 | 13 |
| c | 9 | 6 |
| d | 8 | 7 |
| e | 2 | 14 |
| f | 12 | 4 |
| g | 18 | 14 |
| h | 20 | 11 |
| a. | Determine a sequence that will minimize makespan time. |
| The sequence is . |
| b. | Find machine B’s idle time. |
| Idle time | [removed] hrs |
| c. | For the sequence determined in part a, how much would machine B's idle time be reduced by splitting the last two jobs in half? |
| New idle time [removed] hrs, savings of [removed] hrs. |
11 years ago 6
Answer(0)
Bids(0)
other Questions(10)
- Choose one author from the early American and colonial period. Identify what he or she wrote and describe his or...
- HOMEWORK 1
- for Nancy Carol
- Help 4
- autocad
- W3 Assignment
- I need help ASAP plz
- week 2 assignment
- Prof.moses ONLY
- Submit your first draft (that does NOT mean you have not proofread or edited, it means that you will get another chance to submit after I make suggestions) here. The essay should be 400-500 words, standard essay format of 5 paragraphs with introduction, c